DENVER, Aug. 18 /PRNewswire-FirstCall/ -- Vista Gold Corp.
("Vista" or the "Company") (TSX & NYSE Amex Equities:
VGZ) is pleased to announce estimated proven and probable mineral reserves of
two million ounces and the positive results of a Preliminary Feasibility Study
("PFS") for the Batman deposit at the Company's wholly-owned Mt. Todd
gold project in Northern Territory, Australia. The PFS was managed by
TetraTech MM Inc. ("TetraTech") of Golden, Colorado, which also
undertook the resource modeling and estimation, geotechnical, environmental and
site reclamation engineering and design. Mr. John Rozelle, PG, Manager of
TetraTech's Mineral Resource Division and Principal Geologist, an independent
Qualified Person as defined by Canadian National Instrument 43-101 ("NI
43-101"), prepared or supervised the preparation of material on behalf of
TetraTech. Thomas Dyer, P.E., of Mine Development Associates, an
independent Qualified Person as defined by NI 43-101, prepared or supervised
the preparation of material on behalf of Mine Development Associates. Mr.
Rozelle and Mr. Dyer prepared or supervised the preparation of the information
that forms the basis for the scientific and technical information disclosed
herein and have reviewed this press release and have consented to its release.
The PFS study will be filed on SEDAR (at www.sedar.com)
in its entirety within 45 days. All dollar amounts in this press release
are in US dollars unless otherwise noted. Management plans to review the
results of the PFS in a conference call, details of which are shown at the end
of the press release.
The PFS base case (the "Base Case") was evaluated using the
three-year trailing average gold (Au) price of $950 per ounce. Mineral reserve
estimates and production highlights from the Base Case are tabulated below.
Base Case Production Highlights
|
|
Base
Case Reserves and Production Estimates at $950/ounce Au
|
|
Proven
and Probable Mineral Reserves (at a 0.55 g Au/tonne cut-off)*(1)
|
60.05 million tonnes at 1.05 g
Au/tonne
|
|
Contained
Gold
|
2,026,000 ounces
|
|
Life
of Mine Production
|
1,662,000 ounces
|
|
Average
Annual Production (based on 8.86 year mine life)
|
187,500 ounces gold per year
|
|
Mining
Rate
|
22.9 million tonnes per year
|
|
Mill
Throughput Rate
|
18,500 tonnes per day
|
|
Stripping
Ratio (waste:ore)
|
2.37
|
|
Mine
Life
|
8.86 years
|
|
|
|
|
*
Elevated cutoff grades were used to constrain the total estimated mineral
reserve tonnes to the remaining tailings capacity while maximizing return.
In most areas, a cutoff grade of 0.55 g Au/tonne was used. Select
benches in the first two phases of mining used a cutoff grade of 0.60 g
Au/tonne.
|
|
|
|
|
|
The PFS was completed using a foreign exchange rate of $0.85 = A$1.00 and
incorporates mid-2010 costs. The following table summarizes the Base Case
economic results with a comparison to the Base Case sensitivity at a gold price
of $1200 per ounce and a foreign exchange rate of $0.90 = A$1.00.
Summary of Base Case Economic
Results
|
|
|
$950/oz Au & $0.85/A$1.00
|
$1200/oz Au & $0.90/A$1.00
|
|
Average
Cash Operating Cost ($ per oz Au produced)
|
$476
|
$493
|
|
Average
Total Cash Production Costs ($ per oz Au produced)
|
$487
|
$507
|
|
Pre-Production
Capital Cost:
|
$441,258,000
|
$459,820,000
|
|
Sustaining
Capital Cost:
|
$32,981,000
|
$32,981,000
|
|
Internal
Rate of Return
|
14.9% before tax
9.8%
after tax
|
25.4% before tax
16.2%
after tax
|
|
Cumulative
Cash Flow (pre-tax)
|
$472,615,000
|
$848,724,000
|
|
Net
Present Value at 5% discount (pre-tax)
|
$210,144,000
|
$487,156,000
|
|
|
|
|
|
In addition to the Base Case, Vista also studied a larger 30,000 tonnes per
day case (the "Sensitivity Case") using a gold price of $1200 per
ounce. The operating costs in the Sensitivity Case were completed to
pre-feasibility level standards. The mining capital costs are based on
mid-2010 costs, while the process capital costs are based on late-2009 costs.
The capital costs for the tailings impoundment are factored from the Base
Case, as were the water treatment and closure costs and do not meet the
standards required for a preliminary feasibility study, however they are within
the level of accuracy for a preliminary assessment. Vista intends to commission
TetraTech to undertake further work to optimize and bring the Sensitivity Case
to a preliminary feasibility level over the next few months. Highlights from
the Sensitivity Case are tabulated below.
Sensitivity Case Production
Highlights
|
|
Sensitivity
Case Production Estimates at $950/ounce Au
|
|
In
Pit Estimated Measured & Indicated Mineral Resources (at a 0.40 g
Au/tonne cut-off)(2)
|
139.18 million tonnes at 0.87 g
Au/tonne
|
|
Contained
Gold
|
3,897,000 ounces gold
|
|
Life
of Mine Production
|
3,196,000 ounces gold
|
|
Average
Annual Production
|
251,600 ounces gold per year
|
|
Mining
Rate
|
33.2 million tonnes per year
|
|
Mill
Throughput Rate
|
30,000 tonnes per day
|
|
Stripping
Ratio (waste:ore)
|
2.03
|
|
Mine
Life
|
12.7 years
|
|
|
|
|
Sensitivity Case Economic
Highlights
|
|
|
$950/oz Au & $0.85/A$1.00
|
$1200/oz Au & $0.90/A$1.00
|
|
Average
Cash Operating Cost ($ per oz Au produced)
|
$525
|
$545
|
|
Average
Total Cash Production Costs ($ per oz Au produced)
|
$541
|
$563
|
|
Pre-Production
Capital Cost:
|
$646,904,000
|
$677,113,000
|
|
Sustaining
Capital Cost:
|
$230,951,000
|
$230,951,000
|
|
Internal
Rate of Return
|
10.1% before tax,
6.2%
after tax
|
21.0% before tax,
13.0%
after tax
|
|
Cumulative
Cash Flow (pre-tax)
|
$513,006,000
|
$1,219,408,000
|
|
Net
Present Value at 5% discount (pre-tax)
|
$154,524,000
|
$631,027,000
|
|
|
|
|
|
Commenting on the positive Mt. Todd PFS, Fred Earnest, President and COO of
Vista, stated, "We believe that the comprehensive program of work we have
undertaken over the last four years has addressed the technical issues
experienced by Pegasus, Mt. Todd's prior owner. It is our view that based
on our improved understanding of the ore body, together with the selection of a
proven milling process and equipment, the proposed re-opening of Mt. Todd will
be technically, operationally and economically attractive at a conservative
gold price of $950 per ounce and very attractive at current gold prices. The
larger Sensitivity Case has good economics at current gold prices and we intend
to optimize and upgrade this alternative to a pre-feasibility level study over
the next few months. If the proposed work confirms the Sensitivity Case
results, we believe we may be able to double the project's proven and probable
mineral reserves estimates to approximately 3.5 to 4.0 million ounces.
Additionally, we believe there is significant potential to grow Mt.
Todd's mineral resource estimates through exploration on the project's 160,878
hectares of exploration tenements."
General
The Mt. Todd gold project mine site is located 230 km southeast of the port
of Darwin and 56 km by road north-northeast of the regional center of
Katherine. Katherine and Darwin are connected by a railroad and the Stuart
Highway. An existing paved road connects the mine site to the Stuart Highway.
Vista acquired the project in February 2006 for approximately $2.0 million,
reaching agreements with Ferrier Hodgson, the Deed Administrators for Pegasus
Gold Australia Pty Ltd., the government of the Northern Territory of Australia
and the Jawoyn Association Aboriginal Corporation. Pegasus reported investing over
$200 million to develop the Mt. Todd gold project mine and operated it from
1993 to 1997, when the Mt. Todd gold project was closed as a result of
technical difficulties and low gold prices. The mine's plant and most of the
equipment were sold in June 2001 and removed from the mine, but the tailings
facility, fresh water storage reservoir, natural gas pipeline (for power
generation), and various buildings and useful foundations remain. Since
acquiring the project in 2006, Vista has undertaken various studies and
programs, including an initial Preliminary Economic Assessment
("PEA") issued on December 29, 2006, an updated PEA issued on June
11, 2009, extensive sampling and diamond drilling (over 26,000 meters), an
extensive metallurgical test program which included crushing and grinding,
flotation and leach test work, mine design, as well as various preliminary
engineering studies and cost estimates.
Mineral Resources and Reserves Estimates
The PFS is based on Vista's updated gold mineral resource estimate for the
Batman deposit as of June 11, 2009, which assumed a cutoff grade of 0.40 grams
of gold per tonne. The resource estimate is detailed in the report "Mt.
Todd Gold Project - Updated Preliminary Economic Assessment Report - Northern
Territory, Australia" dated June 11, 2009 and is available on SEDAR at www.sedar.com.
The resources are tabulated below.
Resource
Classification
|
Metric Tonnes
(x1000)
|
Average Grade
(grams/tonne)
|
Short Tons
(x1000)
|
Average Grade
(ounces/ton)
|
Contained Gold
Ounces
(x1000)
|
|
Measured
(2)
|
52,919
|
0..91
|
58,333
|
0.026
|
1,543
|
|
Indicated
(2)
|
138,020
|
0.81
|
152,139
|
0.024
|
3,581
|
|
Measured
&
Indicated
(2)
|
190,939
|
0.84
|
210,472
|
0.024
|
5,125
|
|
Inferred
(3)
|
94,008
|
0.74
|
103,625
|
0.022
|
2,244
|
|
|
|
|
|
|
|
|
The estimated measured and indicated mineral resources included in the table
above includes 60.049 million tonnes of proven and probable reserves shown in
the table of estimated proven and probable reserves below.
Mine Development Associates used the June 2009 resource model to develop an
open pit mine design, including intermediate pits plans and production
schedules.
The mineral reserve estimates prepared and reported by Mine Development
Associates, under the supervision of Mr. Dyer, and using the June 2009 resource
model at a gold price of $950 per ounce of gold and cut-off grade of 0.55*
grams of gold per tonne are summarized in the following table.
Mt. Todd Proven & Probable
Reserve Estimate
|
|
Reserve
Classification
|
Metric Tonnes
(x1000)
|
Average
Grade
(grams/tonne)
|
Short Tons
(x1000)
|
Average
Grade
(ounces/ton)
|
Contained
Gold
Ounces
(x1000)
|
|
Proven
(1)
|
24,458
|
1.09
|
26,960
|
0.032
|
854
|
|
Probable
(1)
|
35,591
|
1.02
|
39,232
|
0.030
|
1,172
|
|
Proven
& Probable (1)
|
60,049
|
1.05
|
66,192
|
0.031
|
2,026
|
|
|
|
|
|
|
|
|
*Elevated
cutoff grades were used to constrain the total reserve tonnes to the
remaining tailings capacity while maximizing return. In most areas, a
cutoff grade of 0.55 g Au/tonne was used. Select benches in the first
two phases of mining used a cutoff grade of 0.60 g Au/tonne.
|
|
|
|
Capital and Operating Cost Estimate
Estimated life-of-mine average total cash production costs are projected to
be $487 per ounce, with the highest costs occurring in the first five years of
the project. The latter half of the project life benefits from decreases
in the required stripping. Pre-production capital costs including
contingency, owner's costs and working capital are estimated to be $441 million
and sustaining capital over the life of the mine is estimated to be $33
million. Post-operation reclamation costs are not included in the total
capital costs, but are included in the cash flow analyses and return on
investment calculations.
Mining
Vista plans to extract ore from the mine using conventional open pit mining
equipment and techniques. A waste mining fleet consisting of 180-tonne
trucks and 21 m3 shovels has been selected to complement the 140-tonne truck
and loader ore mining fleet. The Company would be the owner and operator
of the mining fleets and expects to enter into maintenance and repair contracts
for the major mining equipment. In the Base Case, ore will be mined in three
pit development phases over a period of 8.86 years. Waste rock will be
placed in a single waste dump and concurrent reclamation is planned for the
lower benches of the dump.
Processing
Following an extensive review of the plant performance data from previous
operators, it was clear to Vista that there were a number of key reasons why
these operations were unsuccessful. As a result, Vista undertook mineralogical
and metallurgical studies to fully understand the type of ore that would be
treated over the life of the proposed mine. This was followed by laboratory
test programs that evaluated the metallurgical process, proposed equipment and
the expected performance and cost parameters. Vista believes that principal
reasons that led to the previous operational failure were:
- Ore hardness - the plant
built by the previous operator was poorly designed to handle the hard ore
and failed to produce a satisfactory product or achieve design capacity.
Vista tested and determined the expected ore hardness and then
evaluated various combinations of equipment. The best combination of
equipment involved primary and secondary crushing, tertiary crushing
employing high pressure grinding rolls (HPGR) followed by a large
ball mill. The use of HPGR is expected to result in a product which
significantly improves the efficiency of the grinding circuit. For the
Base Case the circuit is very simple with a large primary gyratory
crusher, a secondary cone crusher, a single HPGR unit and a single ball
mill. HPGR technology is currently being successfully used by
Newmont Mining Corporation, at Australia's largest gold mine, the 20
million ounce Boddington mine in Western Australia. The circuit has
been designed to reflect the results of leach tests that indicate that the
optimum grind size should be 80% passing 100 mesh, coarser than used in
previous operations.
- Metallurgy – A number of
metallurgical problems were encountered in the past, mostly related to
copper minerals in the ore. Vista's test program focused first on
understanding the form and distribution of the copper minerals in the ore
body and then on the best metallurgical approach to deal with the copper.
In the mineralogical review it became apparent that the form of the copper
minerals changes with depth. In the upper part of the ore body, mostly
mined out by previous operators the copper existed mainly as secondary
copper minerals such as chalcocite, bornite and covellite; these minerals
are very soluble in cyanide which greatly increased the expense of
leaching. The remaining ore contains mainly primary copper minerals like
chalcopyrite which generally has a very minor effect on leaching and
cyanide consumption. The tests Vista undertook on representative samples
of the ore to be mined showed that whole ore leaching combined with a
carbon-in-pulp recovery circuit yields acceptable recoveries of 82%.
The proposed plant for the Base Case will have a design capacity of 18,500
tonnes per day and has been designed to be simple, efficient and easy to
maintain. The proposed flowsheet indicates that following grinding the
slurried ore will be sized by cyclones, thickened, pre-aerated, and then
leached in tanks prior to recovery in a hybrid carbon-in-pulp circuit..
Gold will be stripped from the carbon and precipitated in an electrowinning
cell prior to refining into doré bars. The tailings would be detoxified
using the SO2/Air process and deposited in the existing tailings impoundment
facility.
Further contributing to lower costs, the proposed project will self-generate
power using low cost natural gas which can be supplied to the site via the
existing natural gas pipeline. The project also includes plans to produce
lime from near-by limestone deposits, thereby significantly reducing the
supply cost for this reagent.
Infrastructure
As a previously operated project, the Mt. Todd gold project site has
existing infrastructure which includes: a fresh water storage reservoir with
sufficient capacity to sustain the proposed operation, paved access roads,
concrete foundations for some of the crushing circuit, a natural gas pipeline
and an electrical power line. Power will be generated on site using a
gas-turbine generator which is included in the project capital. The power plant
is designed to have excess capacity to meet higher loads during large equipment
starting up. Excess power during operations will be sold into the grid
further reducing expected costs. During the 9-year post-closure period,
Vista intends to continue operating the natural gas turbine power generating
plant. Revenues derived from selling power to the grid during this period
are expected to fund all of the reclamation activities.
Environmental
Both the Base Case and Sensitivity Case include engineering designs for the
closure of the mine site following cessation of production. The closure
plan was designed to meet all requirements for long-term reclamation of the
site and cost estimates include provisions for monitoring required under
applicable law.
Economic Analysis
The Base Case economic analysis was completed using the three-year trailing
average gold price of $950 per ounce and a foreign exchange rate of $0.85 =
$A1.00. Vista has also completed sensitivity analyses calculated at gold
prices of $1000, $1100, $1200 and $1500 per ounce. The $1200 and $1500
sensitivity analyses incorporate the current foreign exchange rate of $0.90 =
A$1.00. Estimated before and after tax economic results, showing the
internal rate of return (IRR) and net present value at a 5% discount rate
(NPV5%), cumulative cash flow and sensitivity to changes in gold price are
shown in the following tables.
Before–Tax Economic Results
|
|
Gold Price Scenario
|
Before Tax
IRR
(%)
|
Before Tax
NPV5%
($ 000's)
|
Before Tax
Cumulative
Cash Flow
($
000's)
|
|
Base
Case $950 Gold Price
|
14.9 %
|
$ 210,144
|
$ 472,615
|
|
$1000
Gold Price
|
17.5 %
|
$ 272,260
|
$ 554,865
|
|
$1100
Gold Price
|
22.6 %
|
$ 396,494
|
$ 719,366
|
|
$1200
Gold Price
|
25.4 %
|
$ 487,156
|
$ 848,724
|
|
$1500
Gold Price
|
39.3 %
|
$ 859,856
|
$ 1,342,227
|
|
|
|
|
|
|
|
|
After-Tax Economic Results
|
|
Gold Price Scenario
|
After Tax
IRR
(%)
|
After Tax
NPV5%
($ 000's)
|
After Tax
Cumulative
Cash Flow
($
000's)
|
|
Base
Case $950 Gold Price
|
9.8 %
|
$ 71,127
|
$ 252,490
|
|
$1000
Gold Price
|
11.4 %
|
$ 100,497
|
$ 207,598
|
|
$1100
Gold Price
|
14.5 %
|
$ 158,192
|
$ 359,190
|
|
$1200
Gold Price
|
16..2 %
|
$ 198,827
|
$ 418,218
|
|
$1500
Gold Price
|
23.9 %
|
$ 359,612
|
$ 624,317
|
|
|
|
|
|
|
|
|
Mike Richings, Executive Chairman and CEO of Vista added the followings
comments, "We are very pleased with the results of the Mt. Todd gold
project PFS. We believe we have demonstrated that development of the Mt.
Todd gold project can generate value that is a multiple of Vista's current
market capitalization for a project we acquired for less than three million
dollars. This once again underscores the benefits of Vista's historic
value-based acquisition strategy to acquire discovered gold projects and to
hold them for higher gold prices. In 2007, we created significant value for our
shareholders through the spin-out of Allied Nevada Gold Corp. and we are once
again posed to take advantage of high current gold prices to generate
additional value for shareholders through development or execution of other
strategic alternatives for the Mt. Todd gold project."
Exploration Potential
Vista controls a large land package (160,878 hectares) of Exploration
Tenements surrounding the Mt. Todd gold project. As previously announced by the
Company, Vista's geologists have identified four new exploration targets at the
Mt. Todd gold project that are now being followed up on through additional
sampling and testing. Of note, at the target identified as MSTS-4, rock chip
sampling, in an area with limited exposure, returned a 25.0 g/t gold sample
from a small outcrop of fault breccia. Further sampling returned 23.0 g/t
and 7.7 g/t gold assays in vein and breccias located 15 meters and 50 meters,
respectively, north of the original sample. Due to the sparse outcrop,
the orientation and thickness of the mineralized zone is not currently known.
A soil sampling program over the area has recently been completed on a 20
meter grid. The survey returned a strong coherent gold anomaly
approximately 400 meters in diameter with coincident anomalous base metals and
arsenic. The Company plans to conduct diamond core drilling in the area
of this target later this year.
Management Conference Call
A conference call with management to review the Mt. Todd gold project
preliminary feasibility results is scheduled on Monday, August 23, 2010, at
4:00 p.m. ET.
Toll-free in North America: 1-866-443-4188
International: 1-416-849-6196
This call will also be web-cast and can be accessed at the following web
location:
http://www.snwebcastcenter.com/event/?event_id=1075
This call will be archived and available at www.vistagold.com
after September 13, 2010. Audio replay will be available for three weeks
by calling in North America: 1-866-245-6755, passcode 59130.
If you are unable to access the audio or phone-in on the day of the
conference call, please feel free to email questions to Connie Martinez,
Manager - Investor Relations, (email: connie@vistagold.com)
and we will try to address these questions prior to or during the conference
call.
About Vista Gold Corp.
Vista is focused on the development of the Paredones Amarillos gold project
in Baja California Sur, Mexico, and the Mt. Todd gold project in Northern
Territory, Australia, to achieve its goal of becoming a gold producer. Vista's
other holdings include the Guadalupe de los Reyes gold project in Mexico, the
Yellow Pine gold project in Idaho, the Awak Mas gold project in Indonesia, and
the Long Valley gold project in California. For more information about our
projects, including technical studies and resource estimates, please visit our
website at www.vistagold.com.
(1) Cautionary Note to U.S. Investors concerning estimates of Reserves: This
press release and the PFS referred to in this press release use the term
"Proven and Probable Reserves" and "Mineral Reserves". We
advise U.S. investors that while these terms are defined in and required by
Canadian regulations, such definitions differ from the definitions in U.S.
Securities and Exchange Commission ("SEC") Industry Guide 7.
Under SEC Industry Guide 7 standards, a "final" or
"bankable" feasibility study is required to report reserves, the
three-year historical average price is used in any reserve or cash flow
analysis to designate reserves and the primary environmental analysis or report
must be filed with the appropriate governmental authority. U.S.
investors are cautioned not to assume that any part or all of mineral deposits
in this category will ever be converted into SEC Industry Guide 7 reserves.
(2) Cautionary Note to U.S. Investors concerning estimates of Measured
and Indicated Resources: This press release and the PEA referred to in this
press release use the terms "Measured Resources", "Indicated
Resources" and "Measured & Indicated Resources." We advise
U.S. investors that while these terms are defined in and required by Canadian
regulations, these terms are not defined terms under SEC Industry Guide 7 and are
normally not permitted to be used in reports and registration statements filed
with the SEC. The SEC normally only permits issuers to report mineralization
that does not constitute SEC Industry Guide 7 compliant "reserves" as
in-place tonnage and grade without reference to unit measures. The term
"contained gold ounces" used in this press release is not permitted
under the rules of the SEC. U.S. investors are cautioned not to assume
that any part or all of mineral deposits in these categories will ever be
converted into SEC Industry Guide 7 reserves.
(3) Cautionary Note to U.S. Investors concerning estimates of Inferred
Resources: This press release and the PEA referred to in this press release
use the term "Inferred Resources". We advise U.S. investors that
while this term is defined in and required by Canadian regulations, this term
is not a defined term under SEC Industry Guide 7 and is normally not permitted
to be used in reports and registration statements filed with the SEC.
"Inferred Resources" have a great amount of uncertainty as to their
existence, and great uncertainty as to their economic and legal feasibility. It
cannot be assumed that all or any part of an Inferred Resource will ever be
upgraded to a higher category. The SEC normally only permits issuers to report
mineralization that does not constitute SEC Industry Guide 7 compliant
"reserves" as in-place tonnage and grade without reference to unit
measures. The term "contained gold ounces" used in this press
release is not permitted under the rules of the SEC. U.S. investors
are cautioned not to assume that any part or all of an Inferred Resource exists
or is economically or legally minable.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of
the U.S. Securities Act of 1933, as amended, and U.S. Securities Exchange Act
of 1934, as amended, and forward-looking information within the meaning of
Canadian securities laws. All statements, other than statements of
historical facts, included in this press release that address activities,
events or developments that Vista expects or anticipates will or may occur in
the future, including such things as the production and economic analysis and
forecasts, estimates of mineral reserves and resources, the conversion of
inferred resources to measured and indicated resources, the conversion of
mineral resources to mineral reserves, life of mine estimates, the potential
for gold resources in the Batman deposit and other targets within the Mt. Todd
gold project, the waste-to-ore ratio at the Mt. Todd gold project, the
successful completion of a metallurgical testing program at the Mt. Todd gold
project, the completion of a Mt. Todd pre-feasibility study for the Sensitivity
Case, future gold prices, future U.S.-to-Australian dollar exchange rates, the
improved efficiencies of high pressure grinding roll technology, the effect of
copper on leaching at the Mt. Todd gold project, operating efficiencies at the
Mt. Todd gold project, revenues from the future sale of electricity generated
at the Mt. Todd into the grid and the use of those revenues to cover
reclamation costs, the recovery of lime from lime-stone deposits at the Mt.
Todd gold project, the favorable effects of Mt. Todd gold project economics,
the Base Case and Sensitivity Case production and economic highlights,
favorable effects of Mt. Todd project economics and Vista's ability to add
value in a cost-effective manner, the estimated operating and capital costs and
the cash flow analysis and sensitivity analysis in the Mt. Todd Preliminary
Economic Assessment and the Mt. Todd Preliminary Feasibility Study, and
anticipated processing capacity and tailings management and other such matters
are forward-looking statements and forward-looking information. When used
in this press release, the words "optimistic", "potential",
"indicate", "expect", "intend",
"hopes," "believe," "may," "will,"
"if, "anticipate" and similar expressions are intended to
identify forward-looking statements and forward-looking information.
These statements involve known and unknown risks, uncertainties and other
factors which may cause the actual results, performance or achievements of
Vista to be materially different from any future results, performance or
achievements expressed or implied by such statements. Such factors
include, among others, uncertainty of reserve and resource estimates, estimates
of results based on such reserve and resource and reserve estimates; risks
relating to completing metallurgical testing and scheduling for a
pre-feasibility study on the Sensitivity Case; risks relating to cost increases
for capital and operating costs including cost of power; risks relating to
delays at the Mt. Todd gold project; risks related to decreased efficiencies
from the high pressure grinding roll technology, risks related to copper
affecting the leaching at the Mt. Todd gold project, risks related to the
generation and sale of electricity produced at the Mt. Todd gold project to
cover reclamation costs, risks related to the ability to economically recover
lime from lime-stone deposits at the Mt. Todd gold project, risks of shortages
and fluctuating costs of equipment or supplies; risks relating to fluctuations
in the price of gold; the inherently hazardous nature of mining-related activities;
potential effects on Vista's operations of environmental regulations in the
countries in which it operates; risks due to legal proceedings; risks relating
to political and economic instability in certain countries in which it
operates; risks related to repayment of debt; risks related to increased
leverage and uncertainty of being able to raise capital on favorable terms or
at all; as well as those factors discussed under the headings "Uncertainty
of Forward-Looking Statements" and "Risk Factors" in Vista's
latest Annual Report on Form 10-K as filed on March 16, 2010, and Quarterly
Report on Form 10-Q, as filed August 6, 2010, and other documents filed with
the U.S. Securities and Exchange Commission and Canadian securities
commissions. Although Vista has attempted to identify important factors
that could cause actual results to differ materially from those described in
forward-looking statements and forward-looking information, there may be other
factors that cause results not to be as anticipated, estimated or intended.
Except as required by law, Vista assumes no obligation to publicly update
any forward-looking statements or forward-looking information; whether as a
result of new information, future events or otherwise.
Without limiting the foregoing, this press release uses terms that comply
with reporting standards in Canada and certain estimates are made in accordance
with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities
Administrators that establishes standards for all public disclosures an issuer
makes of scientific and technical information concerning mineral projects.
All mineral resource and reserve estimates contained in this press
release, including the terms "measured mineral resources,"
"indicated mineral resources", "inferred mineral
resources", "proven mineral reserves" and "probable mineral
reserves" have been prepared in accordance with NI 43-101, and these
standards differ significantly from the requirements of the SEC. The
resource and reserve information contained in this press release is not
comparable to similar information disclosed by U.S. companies. See the
Cautionary Notes to U.S. Investors above.
For further information, please contact Connie Martinez at (720) 981-1185,
or visit the Vista Gold Corp. website at www.vistagold.com.