West African Resources Limited (ASX, TSXV: WAF) is pleased to report activities on its 100%-owned gold and copper-gold projects in Burkina Faso, West Africa, for the quarter ending 30 September 2016.
Highlights
Tanlouka Gold Project
Further spectacular results including
- TAN16-DD052: 4m at 32.04 g/t Au from 122m Au and 10m at 18.33g/t Au from 172m
- TAN16-DD055: 9m at 11.17 g/t Au, from 197m and 16m at 69.11 g/t Au from 209m
Maiden Mineral Resource for M1 & M3 deposits, updated estimate for M5 deposit
- Project mineral resources now 9.8Mt tonnes at 2.1 g/t Au for 670,000 ounces of gold (Indicated) and a further 10.7Mt tonnes at 2.0 g/t Au for 695,000 ounces of gold (Inferred)
- 34% increase in Indicated mineral resources for Tanlouka Gold Project
- Maiden M1 South Indicated mineral resource of 290,000 tonnes at 10.3 g/t Au for 96,000 ounces of gold and Inferred mineral resource of 410,000 tonnes at 6.4 g/t Au for 83,000 ounces of gold1
- M1 South structure averages 1,600 ounces per vertical metre 30m to 130m below surface and remains open along strike and down plunge
- Resource update in Q4 following a 10,000m Diamond drilling campaign to test mineralisation down to 300 vertical metres.
Permitting & Feasibility Study
- Resettlement Action Plan (RAP) and the Environmental and Social Impact Assessment (ESIA) approved by Burkina Faso�s Ministry of Environment, Green Economy and Climate Change. Final step before approval of Mining Permit, expected by end of 2016.
- Feasibility Study on track for completion in Q4 2016, with results to be reported in January 2017.
Corporate
- $21 million placement completed
- US$5 million debt facility repaid
September 2016 Quarter Summary
- 7,150 m drilled
- $2.39m Exploration and Development Expenditure
- $0.5m Administration Costs
- $21.2m cash in bank at 30 September 2016
December 2016 Quarter Plans
- Further drilling at M1, M3 and M5 prospects
- Upgraded Mineral Resource estimates for M1, M3 and M5
- Feasibility study in progress on track for completion in Q4 2016
- Mining Permit expected Q4 2016