Trinidad Operations Update |
b17719d1-6b94-4857-8dcc-41c90b456e2e.pdf
Range Resources Limited
('Range' or 'the Company') 2 November 2015
Trinidad Operations Update
Range provides the following update with respect to its operations in Trinidad.
The average production in Trinidad during the last 30 days was 560 barrels of oil per day ('bopd'). The Company has maintained existing oil production by conducting multiple workovers on current wells. The previously announced production target of 1,000 bopd by the end Monday, November 2, 2015 |
|
| 24hGold - Noodls |
Quarterly Activities Report, Appendix 5B |
818a8b74-a63e-4ff2-9357-5fc05096f45e.pdf
Quarterly Activities Report
For the period ended 30 September 2015
Range Resources Limited
('Range' or 'the Company') 30 October 2015
Highlights
Average oil production of 575 bopd in Trinidad (previous quarter 602 bopd);
The Company published updated reserves statement to 30 June 2015: 1P of 19.4mmbbls, 2P of 22mmbbls, 3P of 27.6mmbbls and 2C of 3.2mmbbls. Also prospective resources of 91.3mmbbls (estimates do not include St MMonday, November 2, 2015 |
|
| 24hGold - Noodls |
Trinidad Drilling Operations Update |
da4f04a11286a451f9e56a.pdf
Range Resources Limited
('Range' or 'the Company') 5 October 2015
Trinidad Drilling Operations Update
Range is pleased to provide the following update with respect to its drilling programme in Trinidad.
The MD 42N development well, located at the Company's Morne Diablo field, which was spudded on 4 September 2015, has reached total depth.
During the drilling operations, the decision was made to drill the well to a revised total depth of 2,610 ft. (iMonday, October 5, 2015 |
|
| 24hGold - Noodls |
Trinidad Operations Update |
Range Resources Limited
('Range' or 'the Company')
24 September 2015
Trinidad Operations Update
Range is pleased to provide the following update with respect to its Trinidad operations, with the following highlights:
The MD 42N well is drilling ahead at 2,180 ft. to a target depth of 3,120 ft.;
Four further wells are expected to spud before the end of October;
The new 4,000m rig has been successfully mobilised to the Morne Diablo field, ahead of spudding. Three directional wellThursday, September 24, 2015 |
|
| 24hGold - Noodls |
Trinidad Update |
Range Resources Limited
('Range' or 'the Company')
24 August 2015
Trinidad Update
Drilling programme update
Range is pleased to advise that it has finalised the drilling schedule with LandOcean for the next 22 development and exploration wells, as summarised in the table below. This schedule complements the work programme released on 7 August 2015.
Proposed Well
Well Location
Target
Depth
(ft.)
Target Horizon
Drilling Rig
Proposed
Spud
Date
GY 161S
Monday, August 24, 2015 |
|
| 24hGold - Noodls |
Investor QA |
Range Resources Limited
('Range' or 'the Company')
12 August 2015
Investor Q&A
The Company is pleased to provide its ongoing investor Q&A setting out responses to questions from investors. It should be noted that those queries that were already addressed in the previous Company announcements and Q&A forums, are not included in this Q&A. The wording of similar questions has been amalgamated to better reflect a broader spread of investor interests.
Trinidad
1. What work is currently out Wednesday, August 12, 2015 |
|
| 24hGold - Noodls |
Trinidad Update |
Range Resources Limited
('Range' or 'the Company')
7 August 2015
Trinidad Update
Range provides the following update with respect to its Trinidad operations with the following highlights:
Four new development wells are scheduled to be drilled during Q3 2015. The drilling sites of the first two wells have been prepared;
The Company continues to prepare for spudding of the Canari North exploration well on the
Guayaguayare block, now expected in October, subject to necessary approvaFriday, August 7, 2015 |
|
| 24hGold - Noodls |
Canari North Exploration Well Update |
Range Resources Limited
('Range' or 'the Company')
14 July 2015
Canari North Exploration Well Update
Range is pleased to announce that following the Company's announcement on 21 May 2015 relating to the upcoming Canari North exploration well on the Guayaguayare Block onshore Trinidad, the drilling site and construction of a 620 metre road have been completed and the drilling rig (Rig 8) has been successfully mobilised and rigged up on the drill pad. The contractor was required to carry outTuesday, July 14, 2015 |
|