17/10/2014: Crusher rectification and first ore shipment


ACN. 000 317 251

Time lodged with ASX: 10.00 am (Brisbane)

MARKET RELEASE 17th October 2014

ROCKLANDS COPPER PROJECT (CDU 100%)

ROCKLANDS CRUSHER OPERATING DELIVERY OF PRIMARY ORE TO GLENCORE'S ERNEST HENRY MINE COMMENCES

Rocklands Rectification and Re-commissioning Completed to Operational Capacity, with Potential for Significantly Increased Throughput

The Company is pleased to advise shareholders that re-commissioning of the Rocklands Copper projects main crusher circuit has now been completed, with only fine tuning and small in-house modifications being implemented to increase operational time and to decrease operational down time. Feed rates up to the nameplate capacity of 550 tonnes per hour achieved. Indications are from our experienced crusher operators that up to an additional 200 tonnes per hour is achievable as a result of the rectification work undertaken.
The Company has been carrying out rectification works to the Main Crushing circuit, which was supplied and installed by Queensland company Index Industrial Brokers (Index-EMS), from Brisbane.

Figure 1: Scalping screen used for removal of the coarse (+40mm) native copper


Unit 34, Brickworks Annex,19 Brolga Avenue, SOUTHPORT 4215
Phone: +617 5503 1955 Facsimile: +617 5503 0288 Email: a dmin@c ude c o.c om. a u

Figure 2: Conveying ore from the Primary Jaw Crusher to the screen above No 1 Rolls Crusher

The crusher plant has required major rectification works and improvements of the electrical systems, particularly because the installation failed to comply with relevant contractual standards, Australian Standards and Queensland Mining Regulations. The Company also had to replace two failed gearboxes in the secondary and tertiary roller crusher circuits and was required to replace a number of other sub-standard parts during this period.
The Company issued legal proceedings in the
Supreme Court of Queensland against Equipment
& Machinery Sales Pty Ltd for the recovery of all costs and damages associated with the substandard installation.

CRUSHER NOW OPERATING

The crusher is now operational and commissioned and the CuDeco metallurgical and process team are fine tuning the circuit so that production can commence for the coarse (+40mm fraction size) native copper product.
The full range of operating parameters are being evaluated on a range of feed rock hardness.
The crushing circuit testwork has now operated satisfactorily at 500 tonnes per hour with room for increased feed rates.

Figure 3: Crusher Operator Bevan Nolan checks settings on the Crusher Control Panel

Page 2


Recent experience with processing the High-grade Native Copper Ore through the Company's mobile crusher to produce DSO native copper (see ASX Announcement 08th September, 2014) gave a good indication of the potential size of native copper nuggets that could be encountered (see Figure 05 below).

In response to this the team has also installed an additional scalping screen above Number 1 Rolls Crusher to enable the separation of the oversize (+200 mm fraction size) native copper nuggets for recovery and sale as part of the DSO.

Figure 5: large predominately native copper mass weighing

~130kg, with marks from the mobile jaw crusher imprinted onto its surface.

Significant interest exists for these remarkably rare mineral specimens.

Figure 4: Conveying Screen 1 ore product to the crushed ore stockpile, which feeds to the main Processing Plant via the underground reclaim feeders

Figure 6; End piece cut from the above large nugget to create a base revealed near solid native copper metal (99.65% Cu), surrounding chalcocite (79.9% Cu), minor cuprite (88.8% Cu), and remnant minor calcite. This sample estimated at ~95% copper content by weight.

Page 3


Shipment of High-grade Primary Ore to Glencore's Ernest Henry Mine (EHM) Underway

Following on from the recent announcement regarding trial processing of Rocklands high-grade primary ore at the EHM processing plant (Refer ASX announcement 14th October, 2014), CuDeco is pleased to advise shareholders that shipment of this ore has commenced.
On behalf of the Board
- ends

Figure 7: Approximately 20 thousand tonnes of primary ore stockpiled and ready for shipment to EHM.

Figure 8: Contractor loading road trains with Rocklands primary ore ready for shipment to EHM processing plant

Page 4


Competent Person Statement

The information in this report insofar as it relates to Metallurgical Test Results and Recoveries, is based on information compiled by Mr Peter Hutchison, MRACI Ch Chem, MAusIMM, a full-time executive director of CuDeco Ltd. Mr Hutchison has sufficient experience in hydrometallurgical and metallurgical techniques which is relevant to the results under consideration and to the activity which he is undertaking to qualify as a competent person for the purposes of this report. Mr Hutchison consents to the inclusion in this report of the information, in the form and context in which it appears.

Disclaimer and Forward-looking Statements

This report contains forward-looking statements that are subject to risk factors associated with resources businesses. It is believed that the expectations reflected in these statements are reasonable, but they may be affected by a variety of variables and changes in underlying assumptions which could cause actual results or trends to differ materially,

including, but not limited to: price fluctuations, actual demand, currency fluctuations, drilling and production results,

reserve estimates, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal and regulatory developments, economic and financial market conditions in various countries and regions, political risks, project delays or advancements, approvals and cost estimates.

The estimation of grades of the native copper product is visual and may be slightly higher or slightly lower. The only contamination maybe some small amounts of rock still being attached after crushing, but visually the native copper nuggets are very clean and the rock fractured off with minimal crushing. The purpose of having these various types and grades tested in the smelters to give an accurate grade and smelter recovery."

Page 5

Read the rest of the article at www.noodls.com

CuDeco Limited

EXPLORATION STAGE
CODE : CDU.AX
ISIN : AU000000CDU1
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

CuDeco is a copper producing company based in Australia.

CuDeco holds various exploration projects in Australia.

Its main exploration properties are LAS MINERALE and ROCKLANDS in Australia.

CuDeco is listed in Australia. Its market capitalisation is AU$ 90.7 millions as of today (US$ 62.0 millions, € 55.9 millions).

Its stock quote reached its highest recent level on August 13, 2010 at AU$ 4.38, and its lowest recent point on February 09, 2018 at AU$ 0.20.

CuDeco has 394 280 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate news of CuDeco Limited
8/2/2016Update on Concentrate Production
7/29/2016Shipment of Native Copper
7/11/2016Update on Commissioning
6/30/2016Update on Commissioning
6/21/2016CuDECO Welcomes Resources Minister
6/21/2016Terms Sheet Sign for Offtake
6/2/2016Letter to Shareholders from Managing Director
6/1/2016Update on Commissioning of Plant
5/30/2016Update on Rights Issue
5/26/2016Terms of Employment for Managing Director
5/24/2016Rights Issue Update and Appendix 3B
5/20/2016Management Changes
5/16/2016Rocklands Commissioning Update
5/13/2016CuDECO Research Report
5/11/2016Rights Issue Update
5/11/2016Market Update
5/6/2016Update Rights Issue and Website
5/5/2016Updated Timetable for Rights Issue
5/5/2016Rights Issue
5/5/2016Prospectus for Rights Issue
5/5/2016High Voltage Energisation of Process Plant Commences
1/30/201629/01/2016: Appointment of Non-Executive Chairman
1/30/201620/01/2016: Resignation of Director and Final Interest Notic...
12/26/201521/12/2015: Letter Sent to Option Holders
12/18/201517/12/2015: Update on Rights Issue
12/15/201515/12/2015: Director Appointment
12/14/201514/12/2015: Chairman's Address to AGM
12/14/201514/12/2015: Results of Meeting
12/14/201509/12/2015: Revised Rights Issue Timetable
12/14/201511/12/2015: Maiden Ore Reserve Estimate
11/30/201530/11/2015: Update on Annual General Meeting
11/30/201530/11/2015: Investor Presentation for Rights Issue
11/25/201525/11/2015: Non-Renounceable Revised Rights Issue
11/25/201525/11/2015: Initial Substantial Shareholder Notice
11/20/201520/11/2015: 2015 Annual Report
11/19/201518/11/2015: 2015 Financial Statement
11/2/201502/11/2015: Logistics Update
11/2/201502/11/2015: September Quarterly Activity Report
11/2/201502/11/2015: Update on AGM and Annual Report
10/29/201529/10/2015: Funding Update
10/1/201501/10/2015: Rights Issue Correction
10/1/201501/10/2015: Update on Financial Statement to 30 June
9/18/201518/09/2015: Director Resignation
9/17/201518/09/2015: Native Cu Processing and Company Funding
9/17/201517/09/2015: Rights Issue
9/14/201508/09/2015: Appointment of Alternate Director
9/14/201504/09/2015: Update on Voluntary Suspension
8/21/201520/08/2015: Update on Voluntary Suspension
8/3/201531/07/2015: June Quarterly Activity Report
7/30/201530/07/2015: Rocklands Project Moving Forward
7/28/201528/07/2015: Company Update
7/28/201524/07/2015: Update on Funding
7/28/201524/07/2015: Update on Changes to Board of Directors
7/23/201523/07/2015: Rocklands Copper Metal Casting Plant Commissione...
6/30/201530/06/2015: Results of EGM
6/29/201529/06/2015: Rocklands Pictorial Update
6/26/201526/06/2015: Increase in Copper Grade During Mining
6/25/201525/06/2015: Native Copper Supply Agreement
6/12/201512/06/2015: Focus Sun FIRB Approval
3/23/201523/03/2015: Market Update on Progress at Rocklands
3/17/201502/03/2015: Half Yearly Report & Accounts
3/2/201502/03/2015: Company Update
1/5/201505/01/2015: Hong Kong Dual Listing
12/22/201422/12/2014: Capital Raisings & MOU
12/4/201404/12/2014: Assays for Bulk Ore Processing Trial
12/3/201403/12/2014: Binding MOU with Sinosteel
11/28/201428/11/2014: Native Copper Shipment
10/23/201423/10/2014: Response to AFR Article
10/17/201417/10/2014: Crusher rectification and first ore shipment
3/18/201418/03/2014: Rockland's Copper Project Update
3/17/201415/03/2014: Half Year Accounts
2/25/201425/02/2014: Direct Shipping Ore Crushing Underway
2/17/201417/02/2014: Mining reaches upto 56% Cu in massive sulphides
2/3/201403/02/2014: Multi User Rail Load Facility update
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (CDU.AX)
0.2300.00%
AUSTRALIA
Prev close Open
Low High
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  - -100.00%
Volume 1 month var.
-100.00%
Produces
Develops
Explores for Copper
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20200.00%0.240.24
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.06+0.57%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 9.16-2.76%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.61-4.06%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+3.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.56+0.64%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.32-5.88%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.18+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.81+1.12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.46+2.07%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.