Doray Minerals Limited

Published : June 16th, 2015

19th May 2015 Deflector Project Approved for Development

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

19th May 2015 Deflector Project Approved for Development

Deflector Project Approved

ASX Announcement

19 May 2015

DEFLECTOR PROJECT APPROVED FOR DEVELOPMENT

Doray Board approves development of Deflector subject to funding

Project review confirms a high-grade/low cost project with by-product credits

6 year initial mine life with substantial exploration upside

LOM average C1 cost of A$654/oz and AISC of A$787/oz after Cu credits

Pre-production capex of $88.2M, including capitalised mining costs

Doray Minerals Limited (ASX:DRM, Doray) is pleased to announce that, following the completion of a detailed review, the Board has formally approved the development of the 100% owned Deflector Gold- Copper Project ("Deflector")in the southern Murchison region of Western Australia, subject to completion of funding requirements and final approvals.

Following construction and commissioning of Deflector, Doray will become a multi-mine high-grade gold producer with the Company targeting 160,000 ounces1 production per annum with average All-In Sustaining Costs (AISC) of less than A$1,000/oz between Deflector and the Company's existing Andy Well gold operation.
The review capitalised on Doray's recent experience in the design, construction and operation of the
Andy Well Gold Project and covered the following areas:

Construction costs and timing

Open pit and underground mining costs and schedule

Processing plant design

Site layout, including accommodation village

Status of permitting and approvals

Copper-gold concentrate offtake

Doray's Managing Director, Mr Allan Kelly, said the review reconfirmed the Company's assessment that the Deflector Project will be a high-grade, low-cost gold project with robust financials and significant upside and the Company looks forward to commencing construction as soon as possible once funding is completed
"When we completed due diligence on Deflector as part of the initial discussions with Mutiny last year, we were very excited about the project and the ability to use our recent experience at Andy Well to optimise the construction and operation of Deflector and create significant value for our shareholders," Mr Kelly said.
"The review confirmed our thoughts on the project, with the numbers in line with those presented to the Doray Board at the time of the transaction. Deflector is one of the best development projects in Australia at the moment."

1 Au equivalent. See Appendix for Au equivalent calculations

Doray Minerals Ltd, 19 May 2015

Deflector Project Summary

Mining

Mining at Deflector will initially comprise an open pit mining method, transitioning to an underground operation towards the end of the first year.
The Western and Central Lodes at Deflector are steep mineralised structures dipping between 80o-90o, typically 1m to 5m wide and hosted within a competent basalt host. The total strike length of the orebody is about 850m.
Open pit mining will occur in stages, initially focusing on mining the narrower Central lode pit. Underground access will be gained through a portal established in the Central lode pit at a depth of
35m below surface. Mining of the wider Western lode pit and the smaller northern pit on the Central lode will then continue to a maximum depth of 85m, concurrent with underground mining.

Table 1. Summary of mining and processing parameters

Physicals

Open Pit Mining

Total movement (bcm)

1.79M

Ore tonnes (t)

348,258

Grade (Au g/t, Cu %)

5.5g/t, 1.63%

Ounces mined (oz)

61,972

Underground Mining

Ore tonnes (t)

2,301,051

Grade (Au g/t, Cu %)

4.7g/t, 0.6%

Ounces mined (oz)

348,592

Total Mining

Ore tonnes (t)

2,649,308

Grade (Au g/t, Cu %)

4.8g/t, 0.7%

Ounces mined (oz)

410,564

Processing

Tonnes processed

2,649,308t

Average Mill throughput

454,000/yr

LOM Average head grade (Au g/t, Cu %)

4.8g/t, 0.7%

Metallurgical recovery - Primary Ore (Au, Cu)

89.5%, 93%

Average annualised production (Au/ Au Eq)

61koz / 74.5koz

Total recovered Au ounces

355,452

Total recovered Cu tonnes

14,279

Mine life

Approx. 6 years

Note: Life of Mine inventories are based on those previously disclosed by MYG in the ASX Release dated 4th August 2014. Open Pit inventories are as previously stated. Underground inventories have been altered by the addition of 30% unplanned dilution at 0.0g/t Au and 0% Cu grade.

ASX:DRM

Doray Minerals Ltd, 19 May 2015


Following the establishment of the portal, underground mining will be carried out utilising a conventional sub-level long-hole open stope mining method at 20m sub-level intervals. Underground ore access will be gained via a 5.3m x 5.5m decline to mine 3.2m x 4m and 4m x 4m ore development drives to suit lode widths.
The decline and level access development is located centrally between the Western and Central orebodies. Underground mining is currently planned to 270m vertical metres below a 15m crown pillar, limited only by current drilling depth.
The top-down mining method employed, retreating to a centrally located access cross-cut allows stoping to commence as soon as level development has been completed. Any ore remaining within a stope is then able to be extracted from a lower level, ensuring minimised ore loss due to mining.

Rock mass characteristics assessed by two specialist geotechnical consultants evaluate the basalt host rock to be competent and have high strength (Uniaxial Compressive Strength averaging 250MPa). Full depth rib pillars will be left at appropriate intervals in accordance with geotechnical recommendations.

Figure 1. Isometric view of proposed Deflector open pits and underground development.

Processing and Production

Doray will construct a new processing plant at Deflector which is specifically designed to suit the metallurgy of the orebody. The plant, to be built by GR Engineering Services ("GRES"), will comprise:

Three stage crushing and screening

Ball mill

Gravity circuit

Elution circuit and gold room

Flotation circuit

The fit-for-purpose plant will be built adjacent to the orebody to minimise mine haulage costs from the open pits and underground.

Throughput of the plant will average 454ktpa with expected average recoveries of 89.5% for Au and
93% for Cu from the primary ore, which provides 82% of total ore feed to the plant.

ASX:DRM

Doray Minerals Ltd, 19 May 2015

Table 2. Processing Plant Recoveries

Oxide

Transitional

Fresh

Au

78.0%

92.0%

89.5%

Cu

65.0%

81.0%

93.0%

Based on the above recoveries, the project will produce approximately 61,000 ounces of gold per annum or approximately 74,500 ounces per annum on a gold-equivalent basis.

70,000

Deflector Annual Production

60,000

50,000

40,000

30,000

20,000

10,000

0

2016 2017 2018 2019 2020 2021 2022

Au Bullion Au in con

Figure 2. Deflector annual gold production

Site Infrastructure and Accommodation Village

Doray will utilise the existing tailings storage facility (TSF) located at the Gullewa mine site, with tailings to be transferred from the new Deflector plant via a purpose built pipeline. Two further pipelines will supply raw water of very good quality (
Site offices, workshop and stores will be located in close proximity to the mine, along with the power station, fuel farm and underground mining contractor facilities.
The Company plans to construct a new accommodation village within 1km of the mine, minimising the level of traffic on the Deflector access road and integrating medical services and administrative management of the mine site and village.

Project Upside Opportunities

Doray believes there is substantial upside to the Project through further optimisation of mining, development and processing once underway.
Doray has taken a relatively conservative approach to mining dilution whilst stoping, based on recent experience at Andy Well. There is potential to reduce the overall dilution, which would have a significant positive effect on the project financials.

It is anticipated that the rougher-concentrate tailings will contain some residual gold. After depletion of oxide and transition ore, a section of the flotation circuit will be redundant when treating only primary ore. Potentially either a further concentrate of pyrite containing gold may be able to be produced

ASX:DRM

Doray Minerals Ltd, 19 May 2015


utilising these tanks, or the installation of a small CIP plant might be able to extract more gold. Once a suitable sample of these tailings is available from the plant, testwork will be undertaken to establish if these or other options are viable.
Doray considers the Deflector Project to have significant exploration potential, enabling the company to capitalise on the investment in the Deflector processing infrastructure. Doray is currently undertaking a project wide data compilation and review, with a view to generating near-mine exploration targets for testing. Targets encompass exploration for both Deflector style Au-Cu mineralisation, as well as traditional Archean Au mineralisation as present at the nearby Gullewa workings.
Since taking control of the project, Doray has been developing a coherent geological model of the mineralisation at Deflector, as well as validating historic data from previous mining operations at Gullewa. Recent work on the Deflector orebody has highlighted the applicability of electro-magnetic geophysical techniques (EM), and as such, a heli-VTEM survey is planned for the upcoming weeks. This survey is designed to cover a 10.5km x 3.5km corridor of the geological sequence that hosts the Deflector deposit, with an aim of delineating conductive bodies that represent massive sulphide hosted Au-Cu mineralisation similar to Deflector.
In addition to target generation work underway, drilling completed at Deflector during 2014 discovered a new zone of mineralisation located ~350m to the southwest of the proposed Deflector development. Results received include 3.08m @ 9.9g/t Au and 7.5% Cu (14DEFDD015). This new zone of mineralisation has not been subject to any follow up drilling.

Development Timeline

The critical path to commencement of production is the installation of the processing plant, which is scheduled to commence July 2015. Detailed final design work is advanced, long lead delivery items have been identified and an order has been placed for the ball mill to enable plant commissioning, followed by the start of production, during Q4 FY16.
The village will be built concurrently with earthworks for the plant foundations. A small existing camp
7km from Deflector will be used during this initial construction period and will be retained as overflow capacity for specific periods such as mill relining or exploration drilling campaigns.
Open pit mining is scheduled to commence in February 2016 to provide initial ore feed for the mill, with underground mining to commence in June 2016 to access underground ore.

Copper-Gold Concentrate Offtake Agreements

Doray is currently in discussions with a number of potential purchasers of the high grade copper-gold- silver concentrate which will be produced from Deflector.

The response from these companies has been very positive and several draft agreements have been received for review and discussion

ASX:DRM

Doray Minerals Ltd, 19 May 2015

438.000mE 44 1.000mE

M59/356

E59/1241

L59/71

- TOGULLEWA

Proposed Pipleine

MGA94 Zone 50

M59/442

1km

LEGEND Tenement Oulline Road

- Proposed Pipelni e

Existing Pit

DORAY

MINERALS UMITED

DEFLECTOR PROJECT

PROPOSED SITE ANO INFRASTRUCTURE LAYOUT

438,000mE 439,500mE 441.000mE

Proposed Pit Oulines Waste Dump Proposed Buildings

Figure 3. Proposed Deflector site layout.

Doray Minerals Ltd, 19 May 2015

Financial Analysis

Table 3. Summary of Project Financials

Financials

A$M

Notes

Pre-production Capex

88.2

Incl. mining costs

LOM Revenue

648.1

LOM Operating Costs

348.4

LOM Operating cash surplus

265.6

Incl. royalties/refining

IRR

28%

Project payback

3.2yrs

LOM average cash operating cost (C1) A$/oz

980 / 654

Pre / Post Cu credits

LOM average AISC A$/oz

1,113 / 787

Pre / Post Cu credits

Assumptions:

Gold Price Assumed (USD$/oz)

1,150

AUD/USD exchange rate

0.77

Table 4. Summary of Pre-production Capital Items

A$M

Notes

Processing Plant

53.8

EPC

Accommodation village

6.7

Site offices

2.0

Labour/Accommodation & Flights

5.0

Fuel/Communications/Miscellaneous/

6.2

Incl. contingency

Open pit establishment/mining

12.3

Incl. capitalised mining costs

Underground establishment

2.2

Total

88.2

150

Deflector LOM cashflow

100

50

0

‐50

2016 2017 2018 2019 2020 2021 2022

‐100

‐150

Net revenue capex operating cashflow

Figure 4. LOM cash flow. Net revenue includes royalties and refining charges.

Doray Minerals Ltd, 19 May 2015

Permitting and Approvals

The existing infrastructure facilities and previous mining areas have been under care and maintenance, with approvals and permits kept in place since mining ceased in 2004.
All critical principal approvals and permits are in place with the regulatory authorities. Only minor amendments regarding revised locations for the plant and village are awaiting final acceptance.

Table 5. Status of permits/approvals

Permit

Authority

Status

Works approval

DER

Approved - mill & mine water discharge.

Awaiting approval of revised location of plant & village

Clearing Permit (5128)

DMP

Approved - Covers total required clearance area.

Awaiting approval of boundary limits to suit revised location of plant & village

Project Management

Plan

DMP Safety

Approved - PMP to Mine Deflector and Milling.

Awaiting approval of revised location of plant & village & of

Construction Management Implementation

Mining Proposal

DMP Environment

Approved - MP open pit mining.

Awaiting approval of revised location of plant & village

TSF + 1 Lift

DMP/DER

Approved - Mining Proposal: existing TSF & one lift

Funding Update

Doray recently appointed PCF Capital as the debt finance advisor for the Project and has received substantial interest from a range of potential domestic and international financiers.
With the completion of the internal review of the Project physicals and financials, the data will be provided to the various interested parties to enable them to provide proposed financing terms.
Is it the Company's intention to maximise the use of debt and Andy Well cash flows to minimise the requirement for additional equity.

-ENDS-

ASX:DRM

Doray Minerals Ltd, 19 May 2015

For further information, please contact:

Allan Kelly Margie Livingston

Managing Director Associate
Doray Minerals Limited AMN Corporate
+61 (08) 9226 0600 +61 (0)438 661 131 [email protected][email protected]

About Doray Minerals Limited

Doray Minerals Limited is a high-grade Australian gold producer, developer and explorer.
The Company controls two high-grade Western Australian gold assets - the operating Andy Well Gold Project (Andy Well) and the development-ready Deflector Gold Project (Deflector). Doray's complementary project portfolio provides increased scale, liquidity and market presence, and a potential re-rating based on its strengthened market positioning.
Doray has a strategic portfolio of gold exploration properties within Western Australia and South Australia and each presents multiple discovery opportunities. The Company's Board and management team has expertise in discovery, development, and production.

Competent Person Statements

The information in this announcement that relates to Au-equivalent calculations and Production Forecasts is based on information compiled by Peter Bamford. Mr Bamford is a full-time employee of Doray Minerals Ltd and is a Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr Bamford has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activities, which he is undertaking. This qualifies Mr Bamford as a "Competent Person" as defined in the 2012 edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Mr Bamford consents to the inclusion of information in this announcement in the form and context in which it appears. Mr Bamford holds shares and options in Doray Minerals Ltd.

The information in this announcement regarding Doray's Mineral Resources and Exploration Results has been extracted from various Doray ASX announcements and is available on the Doray website at www.dorayminerals.com.au or through the ASX website at www.asx.com.au (using ticker code "DRM"). Doray confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and that all material assumptions and technical parameters underpinning the estimates in that market announcement continue to apply and have not materially changed. Doray confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the original market announcement.

ASX:DRM

Doray Minerals Ltd, 19 May 2015

Appendix

Au-Equivalent Calculation Methodology

Multi-element production totals have been converted to Au-equivalent oz through the following:

Assumed Au Price: US$1,150/oz

Assumed Cu Price: US$6,100/t

Assumed AUD:USD exchange rate: 0.77

The Au-equivalent production totals are based on produced metal, and hence have relevant metallurgical recoveries applied as per Table 2 of this release. The calculation formula utilised for Au- equivalents is:

Au-equivalent oz (produced) =

(Au produced oz x Au Price $/oz) + (Cu produced t x Cu Price $/t)(Au Price $/oz)

ASX:DRM

Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Australia | All
Gold and Silver Prices for these countries : Australia | All

Doray Minerals Limited

EXPLORATION STAGE
CODE : DRM.AX
ISIN : AU000000DRM6
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Doray Minerals is a exploration company based in Australia.

Its main exploration properties are MEEKATHARRA NORTH, MINGAH, MAGNET NORTH, LAKE MAGENTA, ABBOTTS, WESTERN QUEEN, NUCKULLA HILL and HICKS in Australia.

Doray Minerals is listed in Australia. Its market capitalisation is AU$ 117.8 millions as of today (US$ 85.0 millions, € 80.8 millions).

Its stock quote reached its highest recent level on November 26, 2010 at AU$ 1.70, and its lowest recent point on December 08, 2017 at AU$ 0.16.

Doray Minerals has 357 089 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Project news of Doray Minerals Limited
9/13/2011Doray Minerals Ltd - Drilling Increases Wilber Lode Strike L...
7/28/2011Doray Minerals - Drilling Doubles Strike Length of Wilber Lo...
6/22/2011Doray Minerals - Diamond Drilling Increases Depth of Wilber ...
6/1/2010(Meekatharra North)Doray Recommences Drilling at Andy Well
Corporate news of Doray Minerals Limited
6/29/2016Resignation of Director
6/24/2016Chairman's Letter to Shareholders
5/16/2016Doray Signs Farm-In Agreement Over Mount Fisher Gold Project
4/28/2016March 2016 Quarterly Summary
4/28/2016Quarterly Results Presentation - March 2016
4/26/2016UK/European Roadshow Presentation
1/26/2016• Quarterly Activities & Cash Flow Report Dec 2015
1/20/2016Deflector Project Progressing on Schedule
12/21/2015Doray moves to 60% ownership of Horse Well
12/17/2015High-Grade Gold Results Extend Wilber Lode
12/17/2015Deflector Construction on Schedule and on Budget
10/20/2015• Half Year Report June 2015
10/8/201511th Sep 2015 Doray Announces Significant Production and Pro...
9/30/201510th Sep 2015 Numerous large gold targets in Western Gawler ...
9/13/2015• New Meekatharra gold project
9/11/20154th Sep 2015 Deflector Project Update
9/11/20151st Sep 2015 Entitlement Issue Prospectus
9/11/201531st Aug 2015 Doray Secures Funding for Deflector
9/10/201525th Aug 2015 Doray To Present At Mid West Economic & Resour...
9/1/20154th Aug 2015 Site Works Commence at Deflector
8/4/201524th Jul 2015 Quarterly Activities Report
8/4/201520th Jul 2015 Expiry of Listed Options
7/24/201530th Jun 2015 Board Changes
6/16/201519th May 2015 Deflector Project Approved for Development
3/26/201511th Mar 2015 Half Yearly Report and Accounts
3/10/201525th Feb 2015 Doray Minerals Wins Craig Oliver Award
3/10/201525th Feb 2015 Resource takes Andy Well to over 500,000 ounce...
2/27/20155th Feb 2015 Dorays Takeover Offer for Mutiny, Compulsory Ac...
2/26/20153rd Feb 2015 Investor Update Presentation - February 2015
11/27/201417th Nov 2014 Landmark Exploration Farm-In Agreement with Il...
11/17/2014Doray Minerals Announcement - Exploration Farm-in Agreement ...
10/27/201428th Oct 2014 Doray Minerals and Mutiny Gold to Merge
7/26/2011DORAY MINERALS - HIGH-GRADE GOLD RESULTS FROM SIDE WELL DRIL...
6/23/2011Doray Minerals - Further High Grade Results from Andy Well D...
2/28/2011Meetings available with ASX-listed gold explorer Doray Miner...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (DRM.AX)
0.330+0.00%
AUSTRALIA
AU$ 0.330
01/06 10:00 -
0%
Prev close Open
0.330 0.330
Low High
0.330 0.330
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.330 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : -26
Produces
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 4/29/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20240.00%
20230.00%0.330.33
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 6.69-0.15%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.26+2.29%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.61+3.40%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
 2.11+1.44%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.99+0.00%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
 0.30+7.14%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
 0.20+2.56%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 2.20+1.38%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 38.96-0.38%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.10-4.55%Trend Power :
Sun Res.(Oil)SUR.AX
Released ASX Announcement: Quarterly Activities Report
AU$ 0.00+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.