Metals Exploration Limited

Published : June 02nd, 2016

Annual Results 2015

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Cash | Debt | Gold | Lead | Mines | Saving | Storage | Technology | Water |

Annual Results 2015

METALS EXPLORATION PLC

26 May 2016

METALS EXPLORATION PLC

FINAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2015

Metals Exploration plc (AIM: MTL) (the "Company" or the "Group"), the natural resources exploration and development company with assets in the Pacific Rim region, is pleased to announce its final audited results for the year ended 31 December 2015.

Highlights Operational

  • Equipment and construction materials continued to arrive throughout the reporting period.

  • Construction activity and final handover of the constructed project to the operating team was completed in November 2015.

  • Staged dry and wet commissioning of processing plant and associated operations commenced in June 2015 and continued through the second half of the reporting period.

  • The project was fully permitted with in excess of 400 permits from various regulators by January 2016.

  • Super Typhoon Lando (known internationally as Koppu) struck Central and Northern Luzon in mid-October.

  • Following a site inspection into water damage caused by the typhoon, the Company's Philippine subsidiary company, FCF Minerals Corporation, was issued with a Partial Suspension Order by the Mines and Geosciences Bureau ("MGB") to suspend construction works at the Residual Storage Impoundment and Malilibeg Dump Site areas belonging to the Runruno project.

  • Working closely and diligently with the MGB to complete a programme of rehabilitation and enhancement works, the Partial Suspension Order was lifted post-period end in April 2016.

  • Ore commissioning and debugging of the processing plant and associated operations commenced post period end in May 2016.

  • No material health and safety incidents experienced throughout the reporting period.

    Corporate

  • Mr Lucian Eduard Simovici joined the Board of Directors as a Non-Executive Director in January 2015.

  • The Company's average number of personnel and full-time workforce numbers during the period were 677.

  • Launch of a wide variety of community based programmes to ensure the positive impacts of the Project elevate the economic status of the company's host community.

    Financial

  • Cash and cash equivalents of £10.969 million (US $16.261 million) at period end.

  • US $83 million debt facilities provided by HSBC and BNP Paribas were fully drawn down during the period.

  • Equity of US $14.447 million raised during the period, via a share placing of US $5 million and an open offer of £3 million, together with a loan facility of US $5 million. Funds were raised for general corporate and working capital requirement, and to complete the project.

    • An additional equity raise of US $6.2 million was completed post period end, in March 2016 to ensure the Company's short term funding needs were met. The total amount of debt and equity raised within the period and post period end is approximately US $20.647 million.

    • An initial rescheduling of capital repayments to funders regarding the Company's senior debt facility was completed in the period.

    • The auditors drew attention to the Going Concern principle by way of emphasis in their report on the statutory accounts for the year ended 31 December 2015

    • FCF Minerals Corporation has a US $2.181m top-up payment to make to a Debt Service Reserve Account by 30 May 2016 latest and this will be funded out of the Project's funds

    • As a result of the delay experienced in commencing commercial operations, negotiations continue with funders with regards to the Company's existing debt repayment schedule to ensure the project is not in technical breach through a default on payments due on 30 June 2016.

For further information please visit or contact www.metalsexploration.com

Ian R. Holzberger +61 (0) 730 409 006

(Chairman) +61 (0) 418 886 165

Liam A. Ruddy +44 (0) 208 133 3433

(Company Secretary) +61 (0) 498 648 615

Nominated Adviser: STOCKDALE SECURITIES Ltd

Robert Finlay, Edward Thomas +44 (0) 207 601 6100

Public Relations: TAVISTOCK

Edward Portman; Jos Simson +44 (0) 207 920 3150

Broker: SP ANGEL CORPORATE FINANCE LLP

Ewan Leggat +44 (0) 203 470 0470

CHAIRMAN'S STATEMENT

Dear Shareholder,

I have great satisfaction in presenting Metals Exploration plc's (the "Company" or the "Group") results for the year ending 31 December 2015. The Strategic Report will provide you with a review of progress and developments for the Group covering the year to 31 December 2015 as well as the period subsequent to the financial year-end.

Significant change occurred in 2015 as the Company successfully realised the construction completion of the Runruno Gold Project (the "Project") and moved into commissioning. The Project is now positioned to move as efficiently as possible towards commercial production, which is expected to result in the realisation of significant value to shareholders, staff and other stakeholders.

The transition from commissioning towards commercial production presented the Company with a number of significant challenges which prevented the Project from achieving commercial production in 2015.

By January 2016 the Company had achieved all the operating and occupancy permits necessary to commence ore commissioning and ramp-up of the process plant. However, the permitting process had proved to be far more detailed and involved than could have been reasonably predicted which resulted in a consequential delay to the Project. The number of permits required for operations totalled well in excess of 400 the majority of which were secured in this period - an effort that I am proud to say was achieved with considerable diligence by the Company personnel involved and the full engagement of the various responsible regulators.

The impact of Super Typhoon Lando (international Koppu) was as unfortunate as it was ill-timed for the Project. The progression of permitting was significantly accomplished with expectations of moving into ore commissioning to occur in Q4 2015. Stage 2 of the Residual Storage Impoundment (the "RSI") had been completed to design and was being prepared for the finalisation of the tailings pipeline. The erosional damage caused by the extreme rainfall event associated with the typhoon downstream of the RSI (which itself incurred no structural damage) and other areas lead to the Mines and Geosciences Bureau (MGB) issuing a partial suspension order (the "Order") which prevented ongoing construction work in the RSI area and on the Malilibeg Dump Site and the tailings pipeline in those areas. The Order required that the Company undertake a program of rehabilitation and enhancement works in the affected areas to the satisfaction of the MGB before the Order would be lifted. This unfortunately resulted in delays in ore commissioning of the plant and a consequential delay in commencing production.

The Order was lifted in April 2016. Since then the Company has rapidly moved into the ore commissioning and "debugging" phase as it ramps up towards achieving full commercial production. This has also resulted in a significant morale boost for staff who have finally been able to put their training into practice in actual production level activities through this phase.

The delay in commercial production has placed significant pressure on the cash reserves of the Group. The shareholders have steadfastly supported the Group through this period providing over £13.8 million through additional equity and a debt facility through 2015 and to March 2016. A project of this nature could not have achieved what it has without this ongoing shareholder support.

Pleasingly the Company has not been subject to any significant legal actions in 2015 of a similar nature to the Writ of Kalikasan reported in the past. Any actions over the reporting period were "in the normal nature of business" and have been progressively dealt with accordingly. The Company however has not seen any progression of a resolution through its action to recover VAT paid to the BIR

incorrectly levied on imported capital equipment. Relief from such imposts is provided under the Company's Financial and Technical Assistance Agreement, however the BIR has chosen not to recognise the provisions within the agreement. The Company continues to pursue this matter through various means.

Construction and Commissioning

The completion of the construction of the process plant in 2015 was a tremendous milestone. Given the slippage caused by design drawing delays the decision to build the process plant under the "self- manage" model has proven to be a significant cost saving and not exposed the Company to "extension of time" claims which would have resulted out of alternate Contractor driven construction models.

Highlights during this period included:

  • Staged dry commissioning commenced in June 2015 with the crusher, transfer station and conveyor areas. The various stages of the process circuit followed under a detailed commissioning strategy lead by Company personnel and supported by Plant & Infrastructure Engineering Pty Ltd who had been involved in the project throughout the project's construction.

  • Final handover of the constructed project to the operating team in November 2015.

  • Connection of the Project's switchyard to the National Grid.

  • Transitioning from dry commissioning into wet commissioning in preparation for ore commissioning. Ore commissioning was commenced following the lifting of the partial suspension order.

  • Construction of stage 2 of the RSI. Stage 3 is well progressed under the design of GHD and is expected to be complete in Q3 2016.

  • The process mini plant has successfully confirmed the application of the technology to the Runruno ores and generated 300 cubic metres of the BIOX® culture in preparation for the commissioning of the operational BIOX® circuit.

  • The mining operations and process plant were well prepared for operational readiness prior to the lifting of the suspension order.

  • Well progressed in achieving ISO14001 accreditation of the Company's environmental systems.

A more detailed explanation of these achievements is found in the Strategic Report.

Cash Position and Project Finance

As at 31 December 2015 the Group's cash at bank position was £10,969,449. The funds available under Facility Agreement are fully drawn including the cost overrun facility.

Resulting from the delay in commercial production the Company agreed a rescheduling of the repayments with the lenders under the existing facility agreement. This was designed to reschedule principal payments to allow the Company the flexibility in cash management whilst moving through the ramp up phase into commercial production.

Through the further delay resulting from rehabilitation activities required prior to the lifting of the suspension order the Company has also been working with the lenders to determine an alternative lending structure to ensure the project does not default on payments in June 2016.

The lenders remain supportive of the project and recognise its economic fundamentals have not changed, with the working relationship with Management continuing to be strong and constructive. Similarly to the improved moral of staff, the lifting of the suspension order has created an impetus towards finding a solution that will be beneficial to all parties that will assist the Project to achieve its financial returns.

Read the rest of the article at www.publicnow.com

Metals Exploration Limited

DEVELOPMENT STAGE
CODE : MTL.L
ISIN : GB00B0394F60
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Metals Expl. is a gold and copper exploration company based in United kingdom.

Metals Expl. develops gold, copper and molybdenum in Philippines.

Its main asset in development is RUNRONO in Philippines and its main exploration properties are CAPAZ, DUPAX, SULONG and WORLDWIDE in Philippines and PURAY in Canada.

Metals Expl. is listed in United Kingdom. Its market capitalisation is GBX 11.4 billions as of today (US$ 13.5 billions, € 12.2 billions).

Its stock quote reached its highest recent level on October 03, 2008 at GBX 9.94, and its lowest recent point on March 08, 2019 at GBX 0.30.

Metals Expl. has 2 071 334 586 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Project news of Metals Exploration Limited
6/22/2011plc to remain AIM quoted and Runruno regional exploration up...
5/18/2011plc - step out drilling and regional exploration activities ...
3/30/2011plc - Operations update on matters relating to its Runruno g...
Corporate news of Metals Exploration Limited
7/26/2016Equity Raising
6/24/2016Results of AGM
6/24/2016Mill update
6/14/2016Runruno Gold Dore Pour
6/2/2016Form of Proxy for AGM
6/2/2016Chairman’s Letter to Shareholders
6/2/2016Annual Results 2015
6/2/2016Notice of Annual General Meeting
4/26/2016Results of the General Meeting
4/25/2016Lifting of Partial Suspension Order
4/25/2016Results of the General Meeting
4/8/2016Notice of General Meeting
4/8/2016Form of proxy for GM
3/22/2016Holding in Company
3/22/2016Partial Suspension Order Update
10/19/2015Results of General Meeting
9/29/2015Open Offer Application Form
9/24/2015Interim results for the six months period ended 30 June 2015
9/24/2015Total voting rights
8/7/2015Commissioning and Funding Update
7/1/2015AGM Company Presentation
7/1/2015AGM Results
4/16/2015Holding in Company – Baker Steel Capital Managers
4/16/2015Holding in the Company – Ruffer LLP
3/18/20152015 AGM Announcement
7/27/2012Outlook on Junior Precious Metals Explorers
5/21/2012PLC - Final Results for the Year Ended 31 December 2011
5/8/2012plc - Operational Update Quarter Ended 31 March 2012
1/26/2012plc - Runruno operations update
12/6/2011Corporate Update
10/24/2011plc - Runruno operational update
5/23/2011plc - Final results for the year ended 31 December 2010.
4/4/2011plc - Completion of Subscription and Shareholders' Agreement
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
LSE (MTL.L)
5.50+6.85%
LSE
GBX 5.50
09/16 17:26 0.350
6.85%
Prev close Open
5.15 5.30
Low High
5.28 5.85
Year l/h YTD var.
2.60 -  5.80 89.66%
52 week l/h 52 week var.
1.83 -  5.80 165.96%
Volume 1 month var.
3,717,148 27.49%
24hGold TrendPower© : 10
Produces
Develops Gold - Molybdenum
Explores for Copper - Gold - Manganese - Molybdenum - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024111.65%6.002.51
2023108.33%3.201.20
2022-13.93%1.660.80
2021-12.12%2.651.18
202043.48%2.000.62
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.05+0.71%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 9.42-0.53%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.64+7.80%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.00-1.96%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 12.48+0.00%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.34+1.49%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.18+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-5.29%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 39.64+0.48%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04-2.38%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.