Lluvia de Oro Mine Update
TSX Venture Exchange - Symbol: COL - Shares Outstanding: 94,970,527
Stacked Material - Slightly more than 100,000 tonnes of crushed ore has now been placed on the second lift of the new heap. The crusher has nearly completed its second 50-meter pass across the transverse dimension of the heap. Six or seven passes will be required to cover the entire length of the heap.
Adjacent Deposits - Exploration work continued on the El Pozo and nearby prospects consisting of trenching and sampling. Some encouraging assay results were received from an outside laboratory, but a backlog of samples is accumulating at the Mine Laboratory. No further ore was trucked to the crusher pending resolution of this matter.
Click here or on the picture above to be linked to the website version with larger photos.
Leaching - Leach pipe has been laid over about 75% of the stacked material. The most recent work covered about 4,000 sq.m. The increased dosage of descalant referred to in an earlier report has been successful in reducing scaling of emitters.
ADR Plant - Operations continued normally including start-up adjustments to the process.
Pregnant solution continues to be applied to the carbon in the columns at approximately 350 USGPM. There have been four caustic/cyanide strips of high-grade pregnant solution from the loaded carbon during August.
SART Copper Recovery Plant - Recent work has concentrated on operator training. A group of contract electricians from Hermosillo has arrived to complete the electrical installations.
Espa�ol
Material Almacenado - Poco m�s de 100,000 toneladas de mineral triturado han sido colocados actualmente en el segundo piso del patio nuevo. La quebradora ha casi terminado su segundo pase de 50 metros a trav�s de la dimensi�n transversal del patio. Se necesitar� seis o siete pases para abarcar el largo completo del patio.
Dep�sitos Adyacentes - Se sigui� con los trabajos de exploraci�n en el prospecto El Pozo y otros cercanos, los que consist�an en excavar trincheras y sacar muestras. Se recibi� algunos resultados de muestreo alentadoras de un laboratorio exterior, pero sigue acumul�ndose gran n�mero de muestras en el Laboratorio de la Mina. No se ha transportado mineral a la quebradora pendiente una resoluci�n del asunto.
Lixiviaci�n - Se ha tendido tubos de lixiviaci�n sobre algo como 75% del mineral almacenado. El trabajo m�s reciente ha cubierto unos 4,000 metros cuadrados. El dosaje mayor de antiincrustante a que se refiri� anteriormente, ha logrado reducir la incrustaci�n de sarro en las emisoras.
Planta ADR - Las operaciones continuaron normalmente, inclusive los ajustes propios al arranque de operaciones. Se continu� la aplicaci�n de la soluci�n pre�ada al carb�n en las columnas a un ritmo de aproximadamente 350 USGPM. Se ha logrado cuatro despojos de soluci�n pre�ada de alta ley del carb�n cargado en el transcurso de agosto.
Planta SART de Recuperaci�n de Cobre - �ltimamente se ha concentrado el trabajo en el entrenamiento de operadores. Ha llegado un grupo de electricistas contratistas de Hermosillo para completar las instalaciones el�ctricas.
Prepared by Vernon Smith, P.Eng., General Manager, Minera Columbia de Mexico, S.A. de C.V.
Please e-mail NWM Mining or telephone us at 416-364-6799 for more information.