VanEck Vectors Global Alternative Energy ETF

Published : April 13th, 2011

Northgate Minerals Provides Update on

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Northgate Minerals Provides Update on Construction and Exploration Activities at Young-Davidson

Project Remains On Schedule and On Budget

VANCOUVER, April 13 /CNW/ - (All figures in US dollars except where noted) Northgate Minerals Corporation (TSX: NGX, NYSE-Amex: NXG) is pleased to provide an update on construction activities for its 100% owned Young-Davidson project located beside the town of Matachewan, Ontario, 60 kilometres ("km") west of Kirkland Lake. Northgate is also pleased to report that follow-up drilling on the YD West zone continues to return positive results.

With current proven and probable gold reserves totalling over 2.8 million ounces(1), the Young-Davidson mine is targeting start-up of production in late Q1 2012. The mine is expected to generate an average of 180,000 ounces of gold annually over an initial 15-year mine life.

Highlights

Construction Activities

    -   The project remains on schedule:
          -   at the end of March 2011, 80% of the contracts have been
              awarded (approximately $170 million), 90% of equipment purchase
              orders have been placed and 66% of the engineering has been
              completed.
    -   The project remains on budget:
          -   at the end of March 2011, Northgate has invested approximately
              $130 million towards construction of the Young-Davidson mine.

Diamond Drill Program

    -   Hole YD10-198B, located approximately 115 metres ("m") below
        discovery hole 198, returned 5.43 grams per tonne ("g/t") gold over
        10.95 m (estimated 6.7 m true thickness).
    -   A total of 5,332 m of surface Diamond drilling has been completed
        within the YD West zone in 2011.

"Since breaking ground in August 2010, we're pleased to report that Young-Davidson has remained on schedule and on budget" commented Ken Stowe, President and CEO. "In particular, we have made great progress on the construction front, having recently completed the raise bore pilot hole for the first leg of the production shaft as well as the concrete foundations for the process plant building. In addition, exploration results continue to prove up the YD West zone, where there is significant potential to add to current reserves. Over the next year, we expect to invest an additional $250 million using existing funds to bring Young-Davidson into production as we move towards our objective of increasing annual production to 350,000 ounces in 2013 and beyond."

Young-Davidson Targeting Production in 2012

Construction activities on surface facilities and underground development are well advanced and are detailed as follows:

Overall Project Activity and Schedule Update (up to the end of March 2011)

    -   Northgate has invested approximately $130 million towards building
        the Young-Davidson mine.
    -   On surface, continued major earthworks in preparation of the project
        site.
    -   Received an amended Certificate of Approval permitting the discharge
        of treated process water, which is the last significant permit
        required for the mine to commence production.
    -   Began dewatering the historic Young-Davidson open pit.
    -   Commenced construction of the 115 kilovolt ("kV") power line to
        energize the site by the beginning of Q4.

Process Plant and Major Equipment

    -   Completed pouring the concrete foundations for the process plant
        building and major equipment.
    -   Currently installing formwork (permanent moulds) and reinforcements
        for the autogenous grinding ("AG") mill foundation.
    -   One of the Kemess South ball mills has been dismantled and is being
        refurbished by the equipment manufacturers in preparation for
        installation at Young-Davidson.
    -   Erection of the mill building is in progress and is expected to be
        completed by June.
    -   Major equipment orders are beginning to arrive on site.

Ramp

    -   The underground development rate is now averaging almost 14 m per
        day.
    -   During the first quarter, the ramp was extended an additional 290 m
        to an approximate length of 4,200 m.
    -   The vertical depth of the ramp is currently 680 m and over the next
        30 months, will be competed to a depth of 1500 m.
    -   An additional 890 m of lateral development was achieved during the
        quarter.

Shaft

    -   Commissioned the new hoist and have commenced sinking operations of
        the existing shaft.
          -   The existing shaft will be extended to a depth of 1,500 m.
    -   Completed the 446 m raise bore pilot hole for the first leg of the
        production shaft.
          -   A total of 220 m has been reamed to 5.5 m in diameter for the
              new production shaft.

Tailings Impoundment Area ("TIA")

    -   Commissioned the dewatering system that will facilitate construction
        of the TIA west dam.
    -   Quarrying of the rock necessary for the construction of the tailings
        dam will be completed within the next two months.
    -   Targeting completion of the first two stages of the TIA construction
        by year-end.
    -   Construction of the haul bridge is scheduled to start in the
        following months.

Development activities over the next 12 months include:

    -   Awarding the electrical/mechanical equipment installation contract in
        April.
    -   Tendering the open pit mining contract in April.
    -   Starting the open pit pre-production development in Q4.
    -   Completing the 115 kV transmission line to energize the site by Q4.
    -   Commissioning activities in Q4.
    -   Targeting our first gold pour late Q1 2012.

The following photos showcase some of the recent construction activities at site. A complete photo gallery and short video clip are available on our website at www.northgateminerals.com.

Process plant concrete foundations

www.northgateminerals.com/Theme/Northgate/files/Releases/2011/ppconcrete.jpg

New hoist commissioned

www.northgateminerals.com/Theme/Northgate/files/Releases/2011/newhoist.jpg

Raise bore setup for new production shaft

www.northgateminerals.com/Theme/Northgate/files/Releases/2011/raisebore.jpg

Headframe modifications:

www.northgateminerals.com/Theme/Northgate/files/Releases/2011/headframe.jpg

Young-Davidson Targeting Production in 2012

Northgate released its final Feasibility Study on Young-Davidson in January 2010 (see press release dated January 25, 2010). Results of the Feasibility Study were based on a gold price of $825 per ounce and an exchange rate of US$/Cdn$0.90. In order to better reflect current market conditions, all figures have been updated in this press release using a gold price of $1,400 per ounce and an exchange rate of US$/Cdn$1.00, unless otherwise noted.

The mining operations will consist of an open pit and underground mine. Access for personnel and materials to the underground mine will be via the ramp and the existing shaft, which will be extended to a depth of 1,500 m. A second production shaft will also be developed to a depth of 1,500 m.

Surface facilities will consist of a modern 6,000 tonne per day ("tpd") process plant utilizing conventional gold processing technology. Unit operating costs are projected to be Cdn$31.63 per metric tonne ("mt") of ore.

Targeting our first gold pour in late Q1 2012, the first leg of production will come from a small open pit targeting production in the range of 84,000 - 90,000 ounces in 2012 and 134,000 - 140,000 ounces in 2013. Once underground development is complete, gold production is expected to ramp up to approximately 175,000 ounces in 2014 and 220,000 ounces in 2015. The approximate life-of-mine cash cost of $400 per ounce is forecast to be well below the current industry average due to the favorable geometry, strong continuity and thickness of the orebody, as well as the very competent nature of the host rock, which allows low cost bulk mining techniques to be employed.

The net cash cost of gold production expressed in US dollars per ounce has increased slightly from the Feasibility Study, solely as a result of the change in base case exchange rate assumption from US$/Cdn$0.90 to US$/Cdn$1.00.

Estimated gold production and cash costs for Young-Davidson are shown below:

Table 1: Young-Davidson Production and Cash Cost Forecast

    -------------------------------------------------------------------------
                                 Source           Production       Cash Cost
                                                    (ounces)      ($/oz) (1)
    -------------------------------------------------------------------------
    2012 (late Q1 start-up)    Open Pit      84,000 - 90,000     $580 - $610
    2013                       Open Pit    134,000 - 140,000     $420 - $440
    2014                       Open Pit
                          & Underground              175,000            $425
    2015                    Underground              220,000            $335
    2016 - 2020 Average     Underground              205,000            $390
    2021 - 2025 Average     Underground              175,000            $425
    2026                      Stockpile               95,000            $630
    -------------------------------------------------------------------------
    Annual average                           ~180,000 ounces      ~$400 / oz
    -------------------------------------------------------------------------
    (1) Assuming exchange rate of US$/Cdn$1.00.

Young-Davidson Capital Costs and Economics

The pre-production capital development costs of the Young-Davidson mine are almost exclusively denominated in Canadian dollars. The current estimate of the total capital cost of the project is Cdn$377.1 million and has not changed from the figure contained in the Feasibility Study. However in US dollars, the pre-production capital cost estimate is now $377.1 million reflecting the increase in the exchange rate assumption from US$/Cdn$0.90 to $1.00.

At a gold price of $1,400 per ounce and an exchange rate of US$/Cdn$1.00, the Young-Davidson mine's existing proven and probable reserves are expected to generate $1.9 billion in pre-tax operating cash flow and on a project basis (i.e. prior to any capital investment), has a pre-tax net present value ("NPV") 5% of $1.0 billion and a pre-tax internal rate of return ("IRR") of 27.6%. The pre-tax and after tax metrics for the Young-Davidson project, at a variety of gold prices, are shown in the following table:

Table 2: Young-Davidson Economics Estimate(1)

    -------------------------------------------------------------------------
                  Cash Flow         NPV 5% Discount        IRR
                    (US$M)               (US$M)
    Gold      ------------------  ------------------  -------------- Payback
    Price     Pre-tax  After tax  Pre-tax  After tax  Pre-tax  After  (years)
    US$/oz                                                       tax
    -------------------------------------------------------------------------
    1,000        $917       $654     $421       $275    15.4%   12.8%    6.1
    1,200      $1,405       $989     $730       $491    21.8%   18.2%    4.8
    1,400      $1,902     $1,331   $1,045       $709    27.6%   23.1%    4.0
    1,600      $2,398     $1,670   $1,358       $926    32.9%   27.7%    3.5
    -------------------------------------------------------------------------
    (1) Feasibility Study press release on January 25, 2010 used a range of
        $825/oz - $1,125/oz of gold and exchange rate assumption of US$/C
        $0.90

Table 3: Summary of Economic Parameters

    -------------------------------------------------------------------------
    Item                                                               Value
    -------------------------------------------------------------------------
    Gold price (US$ per ounce)                                         1,400
    Silver price (US$ per ounce)                                          28
    Foreign exchange rates (US$/Cdn$)                                   1.00
    Tax rates (%)
      Federal Income Tax                                                  15
      Provincial Income Tax                                               10
      Provincial Mining Tax                                               10
    -------------------------------------------------------------------------
    Pre-Production Capital (US$ millions)
      Infrastructure                                                    83.3
      Process plant                                                     90.1
      Mining                                                           106.3
      Indirect costs                                                    62.8
      Contingency                                                       34.6
    -------------------------------------------------------------------------
    Total Pre-Production Capital                                      $377.1
    -------------------------------------------------------------------------
    Sustaining Capital & Mine Closure (US$ millions)
      Completion of Underground Mine Infrastructure                    142.9
      Sustaining Capital & Mine Closure                                119.8
    -------------------------------------------------------------------------
    Total Sustaining Capital & Mine Closure                           $262.7
    -------------------------------------------------------------------------
    Average mining cost (Cdn$ per tonne milled)                     19.03(1)
    Process cost (Cdn$ per tonne milled)                               10.08
    General and administration (Cdn$ per tonne milled)                  2.52
    -------------------------------------------------------------------------
    Total (Cdn$ per tonne milled)                                     $31.63
    -------------------------------------------------------------------------
    Processing Recovery (%)
      Gold                                                              92.4
    -------------------------------------------------------------------------
    (1) Includes open pit mining cost of Cdn$3.46 per tonne mined and
        underground mining cost of Cdn$20.63 per tonne mined.

Infrastructure

The Young-Davidson property is located 3 km west of the town of Matachewan, in the gold-producing Abitibi greenstone belt of northern Ontario. It is readily accessible to, and serviced by, surrounding mining communities such as Kirkland Lake (60 km) and Timmins (165 km) via Highways 566, 66 and 101.

Electric power for the mine site will be supplied by upgrading approximately 47 km of an existing 115 kV power line. We will also be installing 7 km of a new 115 kV line and a mine site transformer station, which is expected for completion in the beginning of the fourth quarter.

The Young-Davidson property sits on the site of two past producing mines, both with track records of successful mining and simple metallurgy, producing approximately one million ounces of gold between the mid 1930's and the mid 1950's. All of the existing underground workings left by the previous owners are in excellent condition.

Human Resources

Work is progressing well at Young-Davidson and has resulted in a significant boost for local and regional employment. Currently, there are approximately 275 contractors and Northgate employees on site, including over 20 First Nations employees. Once production begins in 2012, the mine will provide ongoing direct employment for 275 employees during its 15-year mine-life.

Environment, Permitting and Community Relations

Environmental and permitting activities are ongoing. A recent open house was held to provide an update on blasting information and construction activities. In addition, Young-Davidson provides a community newsletter in order to keep stakeholders up-to-date on site progress. Open houses will continue to be held with the local communities and First Nations, where there is strong community support. On July 2, 2009, Northgate entered into an Impact and Benefits Agreement with the Matachewan First Nation. Since that achievement, the parties have continued to work cooperatively on various aspects of project development.

Exploration Update: YD West Zone

In 2011, a total of 5,332 m of surface Diamond drilling has been completed in the YD West zone with the intent of delineating additional resources. The YD West zone was discovered when hole YD10-198 intersected 3.46 g/t gold over 79.5 m. With the current data, the zone appears to have a minimum strike length of approximately 175 m, measures 150 m along dip and averages 20 m in true thickness.

Hole YD10-198B, located approximately 115 m below the discovery hole YD10-198, returned 5.43 g/t over 10.95 m (estimated 6.7 m true thickness). This hole has been cut by a late post mineral dyke that cut off as much as 45 m of the zone as evidenced by the presence of auriferous material in both the hanging and footwall of the dyke.

The long section below illustrates the location of hole 198B in relation to other intercepts 198,198A and 234 (see press release dated January 11, 2011) in the YD West zone. Drilling now continues in the area with two Diamond drills active. Results are pending for another hole (YD11-234A), which tested an area approximately 50 m east of the discovery hole.

If the 2011 drilling program is successful, it is expected that an initial mineral resource estimate for the YD West zone will be completed by the end of the year.

Table 4: Assay Results YD10-198B

    -------------------------------------------------------------------------
                                                        True
    Hole ID     From (m)    To (m)    Interval (m)    Thickness     Gold Cut
                                                         (m)          20 g/t
    -------------------------------------------------------------------------
    YD10-198B   1353.47    1364.42        10.95          6.7           5.43
    -------------------------------------------------------------------------

Figure 1: Young-Davidson Longitudinal Section (looking north) Assay Results YD10-198B www.northgateminerals.com/Theme/Northgate/files/Releases/2011/YDFig1Apr11.jpg

Underground Delineation Drilling

Underground delineation drilling in support of future underground mining activities began in late 2010 and is currently focusing on a sector of the Upper Boundary Zone. This portion of the program is nearly complete and will be reported upon during the second quarter of 2011 once all the results have been received. It is expected that the results of this program will be incorporated into the annual reserve and resource re-estimate at the end of 2011.

Qualified Persons

John Andrew Cormier, PEng, Project Manager, Northgate Minerals Corporation, is the Qualified Person responsible for reviewing and approving the technical information of this press release.

Carl Edmunds, Exploration Manager, Northgate Minerals Corporation, is the Qualified Person responsible for reviewing and approving the exploration results of this press release.

Northgate Minerals Corporation is a gold and copper producer with mining operations, development projects and exploration properties in Canada and Australia. Our vision is to be the leading intermediate gold producer by identifying, acquiring, developing and operating profitable, long-life mining properties.

Cautionary Note Regarding Forward-Looking Statements and Information:

This Northgate press release contains "forward-looking information", as such term is defined in applicable Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995, concerning Northgate's future financial or operating performance and other statements that express management's expectations or estimates of future developments, circumstances or results. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "expects", "believes", "anticipates", "budget", "scheduled", "estimates", "forecasts", "intends", "plans" and variations of such words and phrases, or by statements that certain actions, events or results "may", "will", "could", "would" or "might", "be taken", "occur" or "be achieved". Forward-looking information is based on a number of assumptions and estimates that, while considered reasonable by management based on the business and markets in which Northgate operates, are inherently subject to significant operational, economic and competitive uncertainties and contingencies. Northgate cautions that forward-looking information involves known and unknown risks, uncertainties and other factors that may cause Northgate's actual results, performance or achievements to be materially different from those expressed or implied by such information, including, but not limited to gold and copper price volatility; fluctuations in foreign exchange rates and interest rates; the impact of any hedging activities; discrepancies between actual and estimated production, between actual and estimated reserves and resources or between actual and estimated metallurgical recoveries; costs of production; capital expenditure requirements; the costs and timing of construction and development of new deposits; and the success of exploration and permitting activities. In addition, the factors described or referred to in the section entitled "Risk Factors" in Northgate's Annual Information Form for the year ended December 31, 2010 or under the heading "Risks and Uncertainties" in Northgate's 2010 Annual Report, both of which are available on the SEDAR website at www.sedar.com, should be reviewed in conjunction with the information found in this press release. Although Northgate has attempted to identify important factors that could cause actual results, performance or achievements to differ materially from those contained in forward-looking information, there can be other factors that cause results, performance or achievements not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate or that management's expectations or estimates of future developments, circumstances or results will materialize. Accordingly, readers should not place undue reliance on forward-looking information. The forward-looking information in this press release is made as of the date of this press release, and Northgate disclaims any intention or obligation to update or revise such information, except as required by applicable law.

Cautionary Note to US Investors Regarding Mineral Reporting Standards:

The Corporation prepares its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101-Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the "SEC") permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. The Corporation uses certain terms, such as, "measured mineral resources", "indicated mineral resources", "inferred mineral resources" and "probable mineral reserves", that the SEC does not recognize (these terms may be used in this press release and are included in the Corporation's public filings which have been filed with securities commissions or similar authorities in Canada).

(1) See press release dated March 8, 2011

For further information: Ms. Keren R. Yun, Director, Investor Relations, Tel: 416-216-2781, Email: ngx@northgateminerals.com, Website: www.northgateminerals.com

.
Data and Statistics for these countries : Australia | Canada | All
Gold and Silver Prices for these countries : Australia | Canada | All

VanEck Vectors Global Alternative Energy ETF

PRODUCER
CODE : NGX.TO
ISIN : CA6664161024.
CUSIP : 666416102
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Northgate Minerals is a gold and copper producing company based in Canada.

Northgate Minerals develops gold, copper and silver in Canada, and holds various exploration projects in Canada.

Its main assets in production are STAWELL MINE and FOSTERVILLE MINE in Australia and KEMESS SOUTH in Canada, its main asset in development is YOUNG - DAVIDSON in Canada and its main exploration properties are BOULEVARD, KEMESS UNDERGROUND, MATACHEWAN MINE and AWAKENING GOLD in Canada.

Northgate Minerals is listed in Canada. Its market capitalisation is 176.0 millions as of today (US$ 173.2 millions, € 122.3 millions).

Its stock quote reached its lowest recent point on January 28, 2000 at 0.60, and its highest recent level on May 12, 2006 at 5.29.

Northgate Minerals has 47 442 200 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of VanEck Vectors Global Alternative Energy ETF
10/26/2011AuRico Gold Completes Acquisition Of Northgate Minerals Corp...
8/14/2006Follow up N° 8
4/29/2006Follow up N° 7
Financings of VanEck Vectors Global Alternative Energy ETF
2/28/2011Sells Auction Rate Securities
9/23/2009Announces C$100 Million Bought Deal Financing
Nominations of VanEck Vectors Global Alternative Energy ETF
7/12/2011Northgate Minerals Corporation Announces the Appointment of ...
7/11/2011Announces the Appointment of Richard Hall as President and
5/10/2011Announces Retirement of President and CEO Ken Stowe
Financials of VanEck Vectors Global Alternative Energy ETF
10/14/2011Reports Strong Third Quarter Production
8/10/2011Primero Reports Second Quarter 2011 Results; Earnings Increa...
5/10/2011Reports First Quarter Results
4/7/2011Northgate Minerals Provides Details for its 2011 First Quart...
4/7/2011Provides Details for its 2011 First Quarter Results and ...
8/10/2010Reports Second Quarter Results
5/11/2010Solid First Quarter Results
4/8/2010Details for Annual General and Special Meeting and 2010 Firs...
8/10/2009Strong Second Quarter Operating Cash Flow of $50 Million
3/4/2009Posts Fourth Quarter Net Earnings of $0.07 per Share
1/14/2009Reports Record Gold Production in the Fourth Quarter 2008
8/1/2008Generates Cash Flow from Operations of $41 million in the Se...
5/2/2008 Reports First Quarter Financial Results; Adjusted Net Earni...
4/8/2008 announces details for annual general meeting and 2008 first...
2/29/2008 posts fourth quarter net income of $32 million
1/28/2008Reports fourth quarter operating results and production fore...
11/30/2007Revises fourth quarter metal production forecast
5/4/2007first quarter gold production on plan; Kemess South mine-lif...
Project news of VanEck Vectors Global Alternative Energy ETF
10/24/2011AuRico Gold's Acquisition of Northgate Minerals Receives Ove...
9/16/2011(Young - Davidson)Announces a 500,000+ Ounce Indicated Resource at YD West
8/25/2011(Young - Davidson)Intersects Two Major Intervals in the YD West Zone at Young-...
8/2/2011(Kemess Underground)Announces Positive Preliminary Assessment for its Kemess Und...
6/24/2011(Young - Davidson)Provides Update on Construction and Exploration Activities a...
6/23/2011(Awakening Gold)Initiates Drill Program at =?ISO-8859-1?Q?=20the=20Awakening...
6/8/2011(Young - Davidson)Intersects 4=2E31 Grams per Tonne Gold Over 79=2E6 Metres at...
5/27/2011(Young - Davidson)Underground Delineation Drilling at NorthgateMinerals' Young...
5/20/2011(Matachewan Mine)Matachewan Consolidated Mines, Limited Announces Sale of Min...
4/13/2011Northgate Minerals Provides Update on Construction and Explo...
4/13/2011(Young - Davidson)' Young-Davidson Project Remains On Schedule and On Budget
2/16/2011(Kemess Underground)Northgate Minerals Announces Updated Resource Estimate for K...
1/12/2011(Young - Davidson)Drilling at Northgate Minerals' Young-Davidson Project Confi...
11/30/2010(Kemess South)Northgate Minerals Successfully Completes 2010 Diamond Drill...
7/2/2010(Young - Davidson)Receives Key Permit for the Development
2/9/2010(Young - Davidson)Receives Board Approval for Development of the Young-Davidso...
1/25/2010(Young - Davidson)Releases Final Feasibility Study for the Young-Davidson Proj...
9/15/2009(Fosterville Mine)Significant Extension of Mineralization Discovered at Northg...
9/10/2009(Young - Davidson)New Gold Zone Discovery at Northgate Minerals' Young-Davidso...
8/6/2009(Stawell Mine)Extends Mine Life at the Stawell Gold Mine
7/15/2009Announces Positive Young-Davidson Pre-Feasibility Study
6/30/2009(Fosterville Mine)Three-Year Collective Agreement Ratified at Northgate's Fost...
12/10/2008(Young - Davidson)Announces Dramatic Increase in Resources at its Young-Davids...
7/18/2008(Young - Davidson) Additional Drill Results for the Young-Davidson Project
4/23/2008reports first quarter production results and updated 2008 pr...
4/16/2008Exploration drilling at Northgate's Stawell mine intersects ...
4/9/2008(Kemess South)New three-year collective agreement ratified at Northgate's ...
3/17/2008(Kemess South)Tentative labour agreement reached at Northgate's Kemess min...
3/8/2008(Kemess South)Federal and Provincial Environmental Ministers announce fina...
3/5/2008(Kemess South)Unionized employees at Northgate's Kemess mine turn down ten...
12/21/2007(Young - Davidson) Announces Additional Young-Davidson Drill Results - Drill H...
5/31/2007(Kemess South)2007 Technical report
5/2/2005(Kemess South)2005 Technical report
Corporate news of VanEck Vectors Global Alternative Energy ETF
10/10/2011Miners Boost Hedging Even as Gold Demand Strengthens
9/14/2011Miners Continue to Underperform in Gold Market
9/13/2011AuRico Gold and Northgate Minerals Provide Update on Special...
8/29/2011Primero Announces Termination of Arrangement Agreement With ...
8/29/2011AuRico Gold to Acquire Northgate Minerals and Create A Leadi...
7/13/2011and Primero to Combine and Create
5/31/2011..lling at Northgate Minerals\342\200\231 Young-Davids...
5/17/2011Recognized for Its Commitment to Sustainability
4/13/2011Northgate Minerals Provides Update on
3/8/2011Northgate Minerals Reports Excellent Cash
2/16/2011Northgate Minerals Announces Updated
1/14/2011Reports 2010 Gold
1/14/2011Reports 2010 Gold
7/2/2010Renews Base Shelf Prospectus
6/11/2010To Renew Universal Base
6/7/2010& Nevada Exploration Sign Formal Option Agreement
3/22/2010Added to S&P/TSX Composite Index
3/9/2010Reports Record Cash Flow from Operations in 2009
1/19/2010Reports Record Gold Production of 362,743 Ounces in 2009
10/14/2009Announces Diamond Drill Results Adjacent to Established Rese...
9/30/2009 Closing of C$100 Million Common Share Offering
7/20/2009Confirms Discussions with Dioro Exploration NL
7/3/2009Matachewan First Nation Signs Impact and Benefits Agreement ...
12/22/2008Comments on Recent Market Activity
9/20/2008Issues Statement on its American Stock Exchange Closing Pric...
9/9/2008 Announces Increase in Gold Reserves at its Stawell Gold Min...
6/25/2008Files Preliminary Assessment Report for the Young-Davidson P...
5/17/2008files preliminary base shelf prospectus
3/26/2008Matachewan First Nation signs Memorandum of Understanding wi...
3/18/2008 reports final audited revenue and net earnings for 2007
2/25/2008's Fosterville Gold Mine to Transition to Owner Mining
2/18/2008Completes Acquisition of Perseverance
2/14/2008Tentative labour agreement reached at Northgate's Kemess min...
2/7/2008Major increase of indicated resources at Northgate's Young-D...
2/1/2008Final court approval received for Northgate's acquisition of...
1/21/2008Perseverance shareholders and warrant holders approve Northg...
12/18/2007Updates progress on Perseverance acquisition
11/5/2007reports strong quarterly production and record low cash cost...
10/28/2007Announces Friendly Proposal to Acquire Perseverance Corporat...
9/20/2007to speak at Denver Gold Forum - Update on Kemess North Proje...
9/18/2007announces further drill results at Young-Davidson analysts' ...
9/18/2007Review Panel submits recommendation report for Northgate's K...
9/10/2007Review panel announces date for the release of recommendatio...
8/2/2007Review panel announces recommendation report for Northgate's...
7/27/2007reports strong quarterly cash flow of $43.7 million - A thir...
12/2/2005Follow Up N° 6
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (NGX.TO)
3.71-0.27%
TORONTO
CA$ 3.71
10/27 15:00 -0.010
-0.27%
Prev close Open
3.72 3.76
Low High
3.65 3.84
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  3.71 -%
Volume 1 month var.
1,270,800 -%
24hGold TrendPower© : 11
Produces Copper - Gold
Develops Gold
Explores for Copper - Gold - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/22/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 6.69-0.15%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.26+2.29%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.61+3.40%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
 2.11+1.44%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.99+0.00%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
 0.30+7.14%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
 0.20+2.56%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 2.20+1.38%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 38.96-0.38%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.10-4.55%Trend Power :
Sun Res.(Oil)SUR.AX
Released ASX Announcement: Quarterly Activities Report
AU$ 0.00+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.