Highlights
 
        Indicated Resource of 66.6 million tonnes at 0.063% molybdenum equivalent
        Inferred Resource of 38.9 million tonnes at 0.065% molybdenum equivalent
 
December 9, 2008 � Toronto, Ontario � Linear Metals Corporation (TSX: LRM) is pleased to report an initial Mineral Resource estimate for the Main Zone at its KM61 Project located near Armstrong, Ontario. This resource consists of a single body of mineralization as detailed in the tables below.  At a cut-off grade of 0.02% molybdenum, the 66.6 million tonne Indicated Resource includes in-situ metal quantities of 127.7 million pounds of copper, 78.2 million pounds of molybdenum, and 5.5 million ounces of silver. In addition, the 38.9 million tonne Inferred Resource includes in-situ metal quantities of 78.0 million pounds of copper, 46.5 million pounds of molybdenum, and 3.4 million ounces of silver.
 
Brian MacEachen, Linear Metals President & CEO, states, �We are encouraged that the first 43-101 compliant resource estimate at KM61 has identified a significant Indicated Resource of 66.6 million tonnes of 0.063% molybdenum equivalent with an additional Inferred Resource of 38.9 million tonnes of 0.065% molybdenum equivalent. This is Linear�s second significant resource estimate in 2008 with our Cobre Grande project, located in Oaxaca Mexico, reporting an initial 43-101 compliant Inferred Resource of 49.8 million tonnes of 0.92% copper equivalent in May 2008. Together, our KM61 and Cobre Grande resources provide Linear and our shareholders with tremendous leverage and exposure to long-term molybdenum and copper prices.� 
 
�We are also very pleased,� adds Brian MacEachen, �to see the majority of the mineral resources at KM61 in the Indicated category, a prerequisite for pre-feasibility studies. This will allow us to advance the project with a minimal amount of additional drilling within the identified Main Zone. KM61 is extremely well located from an infrastructure, environmental and socio-economic perspective and we believe the project has excellent prospects for being mined.�
 
The Mineral Resources encompass the 1.55 kilometre long and up to 275 metres wide Main Zone of the KM61 project where exploration has focused to date. Metallurgical recoveries, from a locked cycle test for KM61, have been reported previously (see press release dated November 24, 2008), and though subject to change as more test work is completed, show mineralization that responds well to conventional flotation.
 
Further study is also planned within the Main Zone Resource to define how much of the higher grade (= 0.10% molybdenum), near-surface mineralization can be modeled into a potential �starter-pit� zone.


Table 1. Indicated Mineral Resources � December 3, 2008
Molybdenum
 (%) cut-off
Tonnes
Molybdenum (%)
Copper (%)
Silver
(g/t)
Molybdenum Equivalent
(%)
 0.10
2,700,000
0.119
0.12
3.3
0.133
0.08
7,800,000
0.099
0.11
3.2
0.111
0.06
21,100,000
0.080
0.10
3.0
0.091
0.04
45,500,000
0.064
0.09
2.8
0.074
0.03
57,900,000
0.057
0.09
2.7
0.068
0.02
66,600,000
0.053
0.09
2.6
0.063
 
Table 2. Inferred Mineral Resource Table � December 3, 2008
 
Molybdenum
 (%) cut-off
Tonnes
Molybdenum (%)
Copper (%)
Silver
(g/t)
Molybdenum Equivalent
(%)
 0.10
1,600,000
0.125
0.09
2.5
0.135
0.08
5,300,000
0.100
0.11
3.5
0.112
0.06
13,500,000
0.081
0.11
3.5
0.094
0.04
25,900,000
0.066
0.10
3.0
0.077
0.03
33,600,000
0.059
0.09
2.8
0.070
0.02
38,900,000
0.054
0.09
2.7
0.065
 
 
Notes:
1.        CIM definitions were followed for Mineral Resources.
2.        The cut-off grade of 0.02% Molybdenum was calculated using long-term prices of US$2.50 per pound copper, US $20.00 per pound molybdenum, and US$13.50 per ounce silver.
3.        Molybdenum equivalent values were calculated using the same long-term prices as above and take into account projected metallurgical recoveries, certain concentrate properties, smelter charges, and payable percentages.
4.        High Molybdenum values were cut to 0.04% prior to compositing to three metres. Similarly, Silver was cut to 30 g/t.
5.        Blocks are 10 metres by 10 metres by 10 metres. Inverse distance squared interpolation was used to estimate block grades. 
 
 
Scott Wilson Roscoe Postle Associates Inc. (Scott Wilson RPA), independent geological and mining consultants, prepared the estimate as at December 3, 2008 in accordance with the guidelines set forth in National Instrument 43-101 (�NI 43-101�).  The estimate was based on a geology model prepared by Geoff Chinn, P.Geo., Linear�s Senior Resource Geologist, on data for drill holes completed through to September 25th, 2008. The resource was estimated through block modeling in Gemcom software. Volumes were constrained using 3D wireframes interpreted from geological logs and assay data, and a preliminary open pit shell modeled in Whittle software.
 
The KM61 drill hole database includes 113 inclined Diamond holes totaling 37,100 metres of core. Most holes within the Mineral Resource area were drilled at -45� to the SE, aligned along NNW-SSE oriented sections spaced 50 to 100 metres apart, resulting in an average drill hole spacing of approximately 50 metres.. The KM61 drill hole data base contains 17,692 copper, molybdenum, and silver laboratory analyses taken over sample lengths generally between one and a half and two metres. Analyses were composited into three metre equal lengths constrained within the wireframes. A total of 4,902 composite intervals were used to estimate block grades within the wireframes. The block tonnage was estimated from volume and generalized densities applied to each rocks type. Generalized densities were determined by statistical analysis of 2,464 core measurements. A generalized density of 2.70 gramsper cubic centimetre was determined for porphyry intrusions and 3.00 gramsper cubic centimetre for mafic volcanic rocks and late mafic dykes.
 
The Mineral Resource was identified from a larger volume of mineralized material through �floating cone analysis�, whereby a preliminary open pit shell, constrained by economic inputs, is generated by Whittle software. The part of the wireframe volume that falls within the preliminary open pit shell is considered to have reasonable prospects of economic extraction; thereby, qualifying as a Mineral Resource. Classification into the Indicated and Inferred categories was guided by the drill hole spacing, interpreted variogram ranges, and the apparent continuity of the mineralized zones.  The estimate is of Mineral Resources only and, because these do not constitute Mineral Reserves, they do not have any demonstrated economic viability.
 
A detailed description of the Mineral Resource estimate and other pertinent information related to the KM61 project will be included in an NI43-101 compliant technical report being prepared for the Company by Scott Wilson RPA, to be filed on SEDAR within 45 days of this press release. 
 
The Whitesand First Nation provided workers and support throughout the field program, and Linear looks forward to the continued advancement of the project under the guidance of an MOU signed in October 2007, between Linear and the Whitesand First Nation.
 
Qualified Persons
 
Dr. Robert Page, PhD, P. Geo., Mr. Matt Rees, M.Sc., P. Geo., and Mr. Geoffrey Chinn M.Sc., P. Geo., have acted as Qualified Persons, as defined in NI 43-101, for this disclosure and have supervised the preparation of the technical information, which formed the basis of the new Mineral Resource disclosed in this press release.
 
Dr. Robert Page, P. Geo., has a PhD in geology and more than 30 years of relevant experience focused on exploring copper, molybdenum, and zinc systems in Mexico and internationally. He is a Professional Geologist registered in the Province of Ontario, Canada. Dr. Page is not independent of Linear Metals as he is an officer and holds common shares and share options.
 
Mr. Matt Rees, P. Geo., has an M.Sc. in geology and 25 years of relevant experience focused on exploring for copper, molybdenum, zinc and nickel systems in Canada and internationally.  He is a Professional Geologist registered in the Province of Ontario, Canada. Mr. Rees is not independent of Linear Metals as he holds common shares and share options.
 
Mr. Geoffrey Chinn, P. Geo., has an Applied M.Sc. in mineral exploration and more than 15 years of relevant experience focused on exploring copper, molybdenum and zinc systems in Canada. He is a Professional Geologist registered in the Province of Ontario, Canada. Mr. Chinn is not independent of Linear Metals as he holds common shares and share options.
  
Mr. David Ross, P. Geo.., a Consulting Geologist employed by Scott Wilson RPA, acted as the Qualified Person, as defined by NI43-101, for the Scott Wilson RPA Mineral Resource estimate. Mr. Ross is independent of Linear Metals.
 
Quality Assurance and Quality Control
 
The Quality Control program at KM61 was set up and supervised on site by Linear Metals� Chief Geologist, Matt Rees, P. Geo., and reviewed for the resource study by Senior Resource Geologist, Geoff Chinn, P.Geo.  Both are Qualified Persons as defined under National Instrument 43-101. Drill core is sawn in half on site and samples collected over one to two metre intervals based on geology. Prior to shipping sealed sample bags are stored in a locked shed on site at the project. Samples are shipped via ground courier to the ALS Chemex sample preparation facility in Thunder Bay, Ontario.  The preparation facility then sends analytical pulps to the ALS Chemex Vancouver, B.C. laboratory � ISO 9001-2000 registered.  All samples are analyzed for molybdenum, copper and silver using a 4 acid digestion Atomic Absorption Spectrometry geochemical method.   The project uses a protocol that includes blanks, standards, and duplicates which make up 15% of each sample shipment. 
 
This press release was prepared under the supervision of Linear Metals� Vice President of Exploration, Dr. Robert Page, P. Geo., who is a Qualified Person as defined under National Instrument 43-101. Dr. Page has reviewed the scientific and technical information in this press release.
For further details on Linear Metals Corporation and its KM61 Project, please visit the Company's website at www.linearmetals.com or contact investor relations at (416) 216-4708 or within North America toll free at [1-866-376-7683].
Signed �Brian MacEachen
Brian MacEachen, President & CEO
 
The TSX Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
  
Forward-Looking Information:
This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address future production, reserve potential, continuity of mineralization, exploration drilling, exploitation activities and events or developments that the Company expects are forward-looking statements. Although the Company believes that the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. The likelihood of future mining at KM61 is subject to a large number of risks and will require achievement of a number of technical, economic and legal objectives, including obtaining necessary mining and construction permits, completion of pre-feasibility and final feasibility studies, preparation of all necessary engineering for pits and processing facilities as well as receipt of significant additional financing to fund these objectives, as well as funding mine construction. Such funding may not be available to the Company on acceptable terms or on any terms at all. There is no known ore at KM61 and there is no assurance that the mineralization at KM61 will ever be classified as ore. For more information on the Company and the risk factors inherent in its business, investors should review the Company's Annual Information Form at www.sedar.com
.
Data and Statistics for these countries : Canada | Mexico | All
Gold and Silver Prices for these countries : Canada | Mexico | All

Linear Metals Corporation

EXPLORATION STAGE
CODE : LRM.TO
ISIN : CA8613081048
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Linear Metals is a silver and gold exploration company based in Canada.

Linear Metals holds various exploration projects in Canada and in Mexico.

Its main exploration properties are LA MORENA and COBRE GRANDE in Mexico and SEYMOUR LAKE and KM61 in Canada.

Linear Metals is listed in Canada and in United States of America. Its market capitalisation is CA$ 3.2 millions as of today (US$ 3.1 millions, € 2.4 millions).

Its stock quote reached its highest recent level on January 18, 2008 at CA$ 1.14, and its lowest recent point on May 22, 2013 at CA$ 0.04.

Linear Metals has 80 331 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Linear Metals Corporation
2/11/2011Announces $1,000,000 Private Placement
8/4/2009Announces Completion of Private Placement
7/22/2009Announces $900,000 Private Placement
Option Grants of Linear Metals Corporation
8/9/2011Retains Alliance Advisors as US Investor Relations Consultan...
Nominations of Linear Metals Corporation
3/26/2008Appoints Dr. James W. Gill as Director
12/11/2007Announces New Appointments
Project news of Linear Metals Corporation
5/10/2011Provides An Update On Its Nyanza Project Exploration Program...
3/31/2011(Seymour Lake)Agrees to Option Agreement on Seymour Lake Project
2/9/2011Signs Option Agreement To Acquire Large Gold And Base Metal ...
1/7/2010Additional High Grade Drill Results
10/7/2009(Seymour Lake)Provides An Update on the Seymouth Lake Lithium Project
9/10/2009(Seymour Lake)Reports Additional Beryllium And Tantalum Results Compiled F...
7/24/2009(Cobre Grande)Provides Update onCobre Grande Purchase Option
12/9/2008(Km61)Reports 43-101 Mineral Resources at KM61 Project
11/24/2008(Km61)Reports Positive Metallurgical Results and Significant Deep ...
9/24/2008(Km61)Deep Holes at Linear Metals KM61 Project Show Molybdenum Min...
9/3/2008(Km61)Encounters Strong Molybdenum Mineralization in Offsets to Hi...
8/20/2008(Cobre Grande)Extends Copper-Molybdenum Mineralization in El Oso Zone at C...
7/23/2008(Km61)Intersects Longest Molybdenum-Copper-Silver Intervals to Dat...
7/2/2008(Km61)Continues to Intersect Long Intervals of Molybdenum-Copper-S...
6/18/2008(Cobre Grande)Intersects High Grade Copper-Silver in Northwest Skarn at Co...
5/15/2008(Km61)Intersects High-Grade Molybdenum in the Main Zone at KM61 Pr...
5/13/2008(Cobre Grande)Announces New Discovery at Cobre Grande Copper-Molybdenum Si...
5/9/2008(Km61)Connects Mineralization Across the Main Zone and Makes a New...
3/5/2008(Km61)Reports Additional Molybdenum-Copper-Silver Mineralization a...
2/12/2008(Km61)Continues to Intersect Wide Intervals of Molybdenum-Copper-S...
2/1/2008(Cobre Grande)Extends Mineralization by 200 Metres and Intersects New Zinc...
10/4/2007Drilling Intersects Significant Mo-Cu-Ag Mineralization
Corporate news of Linear Metals Corporation
4/24/2012Announcement
1/9/2012Reports Gold Mineralization in Kamwango Core Samples-Assays ...
11/28/2011Kenyan Partners of Linear Metals and African Queen Mines Set...
8/22/2011Increases Nyanza Gold and Base Metal Property Portfolio by 6...
7/6/2011Commences Drilling on Its Nyanza Project in Kenya
9/3/2009Additional Results Announced From Linear
8/25/2009Reactivates Seymour Lake Lithium/Tantalum/Beryllium Project
2/9/2008To Begin Trading on the Toronto Stock Exchange And Commences...
1/11/2008Plans Aggressive 2008 Work Programs
12/18/2007ACQUISITION OF SHARES OF LINEAR METALS CORPORATION
11/9/2007Mineralization Extended Over One Kilometre at LinearMetals?C...
8/16/2007Sampling of Historic Core at Linear Metals' KM61 Project Inc...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (LRM.TO)OTHER OTC (LMTCF)
0.040+0.00%0.573+14.37%
TORONTO
CA$ 0.040
05/22 15:28 -
0%
Prev close Open
0.040 0.040
Low High
0.040 0.040
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.040 -%
Volume 1 month var.
130,000 -%
Produces
Develops
Explores for Beryllium - Copper - Gold - Lithium - Silver - Tantalum - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 6.83-1.30%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.18+5.60%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.63-0.63%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
 2.20+2.80%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 14.50+4.39%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
 0.33+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
 0.19+5.56%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 2.05+6.22%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 37.87-4.85%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Sun Res.(Oil)SUR.AX
Released ASX Announcement: Quarterly Activities Report
AU$ 0.00+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.