|
For the detailed Management Discussion
& Analysis and Financial Statements please refer to the Company's website
at www.firsturanium.com.
Summary
- Revenue for the three months ended December
31, 2010 ("Q3 2011") increased by 60% compared
to the three months ended December 31, 2009
("Q3 2010") and by 34% compared to the three months
ended September 30, 2010 ("Q2 2011");
- Gross profit margin improved significantly compared to both Q3
2010 and Q2 2011;
- Operating profit for Q3 2011 indicating an improvement of 129%
and 119% compared to Q3 2010 and Q2 2011, respectively;
- Current cash resources of $29.9 million
may be insufficient to address medium-term working capital needs
following adjustments to Ezulwini's
shaft system; and
- Funding options are being assessed.
All amounts are expressed in US dollars
unless otherwise noted
TORONTO and JOHANNESBURG,
Feb. 2 /CNW/ - First Uranium Corporation (TSX:FIU, JSE:FUM) ("First Uranium" or "the
Company") has announced significantly higher revenues of $51.3 million in Q3 2011, compared to $40.0 million for Q3 2010, which resulted in an
improvement in the consolidated gross profit margin from operations from $1.0 million in Q3 2010 to $7.6
million in Q3 2011.
The significant improvement in the
consolidated gross profit margin from Q3 2010 was the result of the lower
losses from the activities at the Ezulwini Mine,
which more than offset the decreased gross profit margin from Mine Waste
Solutions ("MWS").
The Company generated a consolidated
operating profit of $1.7 million in Q3 2011,
which is a 129% improvement from Q3 2010, primarily due to a higher
consolidated gross margin from operations along with lower expenditures.
The higher consolidated loss in Q3 2011
compared to Q3 2010 was attributable to the foreign exchange loss on
translation in Q3 2011, along with the higher interest and accretion expenses
partially offset by the lower losses generated from mining activities at the
operations compared to the Q3 2010 quarter.
As announced on January
27, 2011, First Uranium's production and financial results for the
third quarter have been negatively impacted primarily because of lost
production time at the Ezulwini Mine resulting from
the fall of ground in November 2010 and the shaft
maintenance program, which is currently underway. Due to the lower than
anticipated production from the Ezulwini Mine the
Corporation's current cash resources ($29.9 million
at December 31, 2010) may be insufficient to
address the medium-term working capital needs. Accordingly, the Corporation
has retained RBC Capital Markets as its financial advisor to review all
funding alternatives available to the Corporation.
Table
1 -
|
Key Consolidated Financial
Results for Q3 2011 and the nine months ended December
31, 2010 ("2011 YTD") compared to its comparative periods
for the 2010 financial year
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Q3 2011
|
|
Q3 2010
|
|
%
Change
|
|
2011 YTD
|
|
2010 YTD
|
|
%
Change
|
Mine
Waste Solutions
|
|
|
|
|
|
|
|
|
|
|
|
|
Ounces of gold sold
|
|
21,040
|
|
21,099
|
|
-
|
|
60,791
|
|
43,514
|
|
40%
|
Average gold selling price
per ounce
|
|
1,179
|
|
1,096
|
|
8%
|
|
1,100
|
|
1,025
|
|
7%
|
Average Cash Cost per ounce
of gold sold (a)
|
|
(482)
|
|
(367)
|
|
31%
|
|
(488)
|
|
(388)
|
|
26%
|
Ezulwini Mine
|
|
|
|
|
|
|
|
|
|
|
|
|
Ounces of gold sold
|
|
19,477
|
|
8,213
|
|
137%
|
|
48,296
|
|
18,639
|
|
159%
|
Average gold selling price
per ounce
|
|
1,360
|
|
1,078
|
|
26%
|
|
1,275
|
|
1,035
|
|
23%
|
Average cash cost per ounce
of gold sold (a)
|
|
(1,576)
|
|
(2,649)
|
|
(41%)
|
|
(1,576)
|
|
(2,826)
|
|
(44%)
|
Revenue
|
|
51,298
|
|
31,979
|
|
60%
|
|
129,274
|
|
63,899
|
|
102%
|
MWS
|
|
24,805
|
|
23,125
|
|
7%
|
|
66,858
|
|
44,610
|
|
50%
|
Ezulwini Mine
|
|
26,493
|
|
8,854
|
|
199%
|
|
62,416
|
|
19,289
|
|
224%
|
Cost of sales (including
amortization)
|
|
(43,652)
|
|
(31,007)
|
|
41%
|
|
(114,767)
|
|
(73,604)
|
|
56%
|
MWS
|
|
(11,786)
|
|
(7,985)
|
|
48%
|
|
(34,134)
|
|
(17,665)
|
|
93%
|
Ezulwini Mine
|
|
(31,866)
|
|
(23,022)
|
|
38%
|
|
(80,633)
|
|
(55,939)
|
|
44%
|
Gross
profit (loss)
|
|
7,646
|
|
972
|
|
687%
|
|
14,507
|
|
(9,705)
|
|
250%
|
MWS
|
|
13,019
|
|
15,140
|
|
(14%)
|
|
32,724
|
|
26,945
|
|
21%
|
Ezulwini Mine
|
|
(5,373)
|
|
(14,168)
|
|
(63%)
|
|
(18,217)
|
|
(36,650)
|
|
(50%)
|
Operating
profit (loss)(b)
|
|
1,704
|
|
(5,939)
|
|
129%
|
|
(10,113)
|
|
(31,196)
|
|
(68%)
|
Loss for the period
|
|
(18,114)
|
|
(14,432)
|
|
26%
|
|
(52,030)
|
|
(66,137)
|
|
(21%)
|
Loss per common share
|
|
(0.10)
|
|
(0.09)
|
|
11%
|
|
(0.29)
|
|
(0.40)
|
|
(27%)
|
Cash flows utilized in
operating activities
|
|
(3,651)
|
|
(1,185)
|
|
208%
|
|
(29,249)
|
|
(48,811)
|
|
(40%)
|
Cash flows utilized in
investing activities
|
|
(33,939)
|
|
(80,182)
|
|
(58%)
|
|
(92,401)
|
|
(198,019)
|
|
(53%)
|
Please refer to the Management's
Discussion & Analysis and Financial Statements for more detailed
information.
Notes:
(a)
|
Total cash costs per ounce is
a non-GAAP measurement and investors are cautioned not to place
undue reliance on it and are advised to read all GAAP accounting
disclosures presented in the Financial Statements.
|
(b)
|
This is a non-GAAP
measurement. Operating profit (loss) is the profit or loss before
investment income, interest and accretion expenses, fair value gain or loss
on derivative liability, foreign exchange gain or loss and income tax
charges.
|
MWS and Ezulwini
Mine
Although the tonnage throughput and
ounces sold by MWS during Q3 2011 were marginally lower than that of Q3 2010,
revenues were 7% higher, primarily as a result of higher gold selling prices
compared to Q3 2010. The 31% increase in costs, in US dollar terms, compared
to Q3 2010 was mainly attributable to the significantly stronger ZAR in Q3
2011 compared to Q3 2010. Costs in ZAR terms increased by 6%. The increase in
ZAR terms was mainly attributable to higher labour
and power costs compared to Q3 2010 due to annual increases set in Q1 2011.
Amortization in Q3 2011 was significantly higher compared to Q3 2010 as MWS
only started amortizing capital costs associated with the second gold plant
module at the start of January 2010.
The increase in costs and amortization
exceeded the increased revenues in Q3 2011 compared to Q3 2010, resulting in
a 14% decrease in the gross profit margin at MWS.
At the Ezulwini
Mine, gold sales for Q3 2011 increased by 137% compared to Q3 2010,
reflecting the increase in production at the mine as well as the improvement
in mining efficiencies over the comparative period. Costs did not increase in
direct correlation to the revenue increase, due to the mine's fixed operating
costs being spread over higher production for the comparative period, which
is also contributed to the decrease in Cash Costs compared to Q3 2010.
Consequently the mine's losses in Q3 2011 decreased by 63% compared to Q3
2010. No uranium was produced or sold during Q3 2011 or Q3 2010.
During Q3 2011, capital expenditures of $26.2 million were incurred at MWS and $6.1 million at the Ezulwini
Mine, respectively. During Q3 2010, capital expenditures of $72.8 million and $7.3 million
were incurred at MWS and the Ezulwini Mine,
respectively. The remaining capital program at MWS is comprised primarily of
the third gold plant module ("Phase
Two") and the new TSF, including adjoining infrastructure. At the
end of Q3 2011, $113 million (ZAR831 million) had
been spent on the completion of the Phase Two expansion program, while $28 million (ZAR216 million) had been spent on the new
TSF capital project. Approximately $35 million
(ZAR228 million) remains to be spent on these two capital projects of which $25 million (ZAR166 million) is planned to be spent
over the next 12 months and $10 million (ZAR62
million) during the first half of FY 2014.
Table 2 - Key Consolidated
Financial Results for the Q3 2011 compared to Q2 2011
|
|
|
|
|
|
|
|
|
|
|
|
|
Q3 2011
|
|
|
Q2 2011
|
|
|
%
Change
|
Mine
Waste Solutions
|
|
|
|
|
|
|
|
|
|
Ounces of gold sold
|
|
|
21,040
|
|
|
18,743
|
|
|
12%
|
Average gold selling price
per ounce
|
|
|
1,179
|
|
|
1,051
|
|
|
12%
|
Average cash cost per ounce
of gold sold (a)
|
|
|
(482)
|
|
|
(537)
|
|
|
(10%)
|
Ezulwini Mine
|
|
|
|
|
|
|
|
|
|
Ounces of gold sold
|
|
|
19,477
|
|
|
15,066
|
|
|
29%
|
Average gold selling price
per ounce
|
|
|
1,360
|
|
|
1,236
|
|
|
10%
|
Average cash cost per ounce
of gold sold (a)
|
|
|
(1,576)
|
|
|
(1,710)
|
|
|
(8%)
|
Revenue
|
|
|
51,298
|
|
|
38,315
|
|
|
34%
|
MWS
|
|
|
24,805
|
|
|
19,696
|
|
|
26%
|
Ezulwini Mine
|
|
|
26,493
|
|
|
18,619
|
|
|
42%
|
Cost of sales (including
amortization)
|
|
|
(43,652)
|
|
|
(38,207)
|
|
|
14%
|
MWS
|
|
|
(11,786)
|
|
|
(11,523)
|
|
|
(2%)
|
Ezulwini Mine
|
|
|
(31,866)
|
|
|
(26,684)
|
|
|
19%
|
Gross
profit
|
|
|
7,646
|
|
|
108
|
|
|
6,980%
|
MWS
|
|
|
13,019
|
|
|
8,173
|
|
|
59%
|
Ezulwini Mine
|
|
|
(5,373)
|
|
|
(8,065)
|
|
|
(33%)
|
Operating
profit (loss)(b)
|
|
|
1,704
|
|
|
(8,995)
|
|
|
119%
|
Loss for the period
|
|
|
(18,114)
|
|
|
(21,891)
|
|
|
(17%)
|
Loss per common share
|
|
|
(0.10)
|
|
|
(0.12)
|
|
|
(17%)
|
Cash flows utilized in
operating activities
|
|
|
(3,651)
|
|
|
(10,249)
|
|
|
(65%)
|
Cash flows utilized in
investing activities
|
|
|
(33,939)
|
|
|
(24,803)
|
|
|
37%
|
Notes: see Notes (a) and (b) in Table 1.
Non-GAAP Measures
The Company believes that in addition to
conventional measures prepared in accordance with Canadian GAAP, the Company
and certain investors and analysts use certain other non-GAAP financial measures
to evaluate the Company's performance including its ability to generate cash
flow and profits from its operations. The Company has included certain
non-GAAP measures throughout this document. Non-GAAP measures do not have any
standardized meaning prescribed under Canadian GAAP, and therefore they may
not be comparable to similar measures employed by other companies.
The data is intended to provide
additional information and should not be considered in isolation or as a
substitute for measures of performance prepared in accordance with Canadian
GAAP.
About First Uranium Corporation
First Uranium Corporation (TSX:FIU, JSE:FUM) is focused on its goal of becoming a
low-cost producer of uranium and gold through the expansion of the
underground development to feed the new uranium and gold plants at the Ezulwini Mine and through the expansion of the plant
capacity of the Mine Waste Solutions (MWS) tailings recovery facility, both
operations situated in South Africa. First Uranium also plans to grow
production by pursuing value-enhancing acquisition and joint venture
opportunities in South Africa and elsewhere.
Cautionary Language Regarding
Forward-Looking Information
This news release contains and refers to
forward-looking information based on current expectations. All other
statements other than statements of historical fact included in this release
including, without limitation, statements regarding the timing and amount of
estimated future production, the processing and development plans, operating
and capital cost estimates, resource estimates, metal prices, exchange rates,
discount rates, the timing and receipt of required permits, the ability to
satisfy the Gold Wheaton Completion Test and future plans and objectives of
First Uranium are forward-looking statements (or forward-looking information)
that involve various estimates, assumptions, risks and
uncertainties. For more details on these estimates, assumptions, risks
and uncertainties, see the Company's most recent Annual Information Form ("AIF")
and Management's Discussion and Analysis ("MD&A") on file with
the Canadian provincial securities regulatory authorities on SEDAR at www.sedar.com.
No assurance can be given that a financing transaction will be concluded.
These forward-looking statements are made as of the date hereof and there can
be no assurance that such statements will prove to be accurate, such
statements are subject to significant risks and uncertainties, and actual
results and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue reliance on
forward-looking statements that are included herein, except in accordance
with applicable securities laws. For details on the Gold Wheaton
Completion Test see the AIF and MD&A.
www. firsturanium.com
|
|