Funding and Technical Programs Update, Ngualla Rare Earth Project
Peak Resources Limited ("Peak" or the "Company"; ASX Code: PEK) is pleased to provide an update on progress in relation to the receipt of funds from strategic partners and technical programs underway.
Peak has previously announced agreements with Appian Natural Resources Fund ("Appian") and the International Finance Corporation ("IFC") to fund the development of the Ngualla Rare Earth Project and Company through Bankable Feasibility Study for a total investment of
~US $25 million (see ASX announcements 'Peak secures BFS funding for Ngualla Rare Earth
Project' of 29 September 2014 and 'Peak attracts IFC as potential cornerstone investor' of 24
October 2014).
HIGHLIGHTS
IFC has completed its mandatory 30 day disclosure period and confirmed formal board approval of the investment in Peak and the Ngualla Rare Earth Project.
All parties (Peak, Appian and IFC) continue to work co-operatively to complete the documentation for the Principal Transaction, which is at an advanced stage and is expected to be finalized prior to the end of January 2015.
• All conditions precedent required for the second tranche of US $2 million of the Bridge Loan Facility have now been met or extended and the funds are expected to be received by Peak this week.
A series of key development programs that have the potential to further improve the
Ngualla Rare Earth Projects attractive economics are now underway.
Strategic Partners
On 29 September 2014 Peak announced details of a ~US $25 million total funding agreement with Jersey based Appian Natural Resources Fund. On completion, the investment is expected to fully fund Peak and the Ngualla Rare Earth Project through the Bankable Feasibility Study (BFS).
Following the introduction by Appian, IFC is proposing to participate with Appian in the ~US
$25million total investment described above, on a 20:80% pro rata basis (IFC 20% ; Appian
80%). IFC's mandatory disclosure period has now been completed and IFC's Board has given
approval to proceed
The first US $1 million (~A$1.1 million) of the Bridge Loan Facility ("BLF) was received in early October (ASX Announcement 'First tranche of funding for Ngualla Rare Earth Project received' of 13 October 2014).
Peak Resources Limited Level 2, 46 Ord Street, West Perth, Western Australia 6005. PO Box 603, West Perth 6872. ASX: PEK ACN
112 546 700
Telephone: +61 8 9200 5360 info@peakresources.com.au www.peakresources.com.au
Non-executive Chairman: Alastair Hunter Managing Director: Darren Townsend Technical Director: Dave Hammond Non-Executive Director: Jonathan Murray Company Secretary: Graeme Scott
All conditions precedent required for the second tranche of US $2 million of the BLF have now been met or extended and the additional funds are expected to be received this week.
All parties (Peak, Appian and IFC) continue to work co-operatively to complete the documentation for the Principal Transaction, which is at an advanced stage and is expected to be finalized prior to the end of January 2015.
About Appian
Appian Natural Resources Fund is a private equity fund which has been established to invest specifically in the metals and mining sector. Appian has a uniquely collaborative investment approach that seeks to partner with local owners, managers and investors to leverage its world-class operational and corporate finance expertise.
With this value-add approach and long-term investment horizon, it aims to generate significant value for the investors and other stakeholders of both the Company and Appian.
About IFC
IFC, a member of the World Bank Group, is the largest global development institution focused exclusively on the private sector. Working with private enterprises in about 100 countries, IFC use their capital, expertise, and influence to help eliminate extreme poverty and boost shared prosperity. In FY14, IFC provided more than $22 billion in financing to improve lives in developing countries and tackle the most urgent challenges of development. For more information, visit www.ifc.org
Technical work programs
The Bridge Loan Facility of US $3million has been agreed to allow Peak to progress key work programs designed to evaluate the potential for further economic upside in the Ngualla Rare Earth Project whilst formal documentation for the Principal Transaction is being completed.
Individual programs now underway include:
Beneficiation breakthrough confirmation work on varied ore samples
Beneficiation Optimisation programs in Australia and China
Leach recovery optimization for the high grade mineral concentrate
Location study for hydrometallurgical section of process plant
The further beneficiation programs will allow Peak to further investigate the 'Beneficiation Breakthrough' test work (see ASX Announcement titled "Ngualla Rare Earth Project Beneficiation Breakthrough" of 7 August 2014).
The beneficiation breakthrough test work produced a 34.4% rare earth oxide mineral concentrate from a typical sample of Ngualla's Bastnaesite Zone mineralisation. This is
double the concentrate grade assumed in the Preliminary Feasibility Study (see ASX
Announcement titled "Peak Resources Delivers Robust PFS for Ngualla" dated 19 March
2014).
The ability to produce a high grade mineral concentrate in the first process stage of beneficiation should lower capital and operating costs due to smaller second stage acid leach recovery plant components and reduced reagent use (Figure 1).
Figure 1: Simplified overview of the 3 stage metallurgical process (PFS version shown). Test work is underway to further optimise the new Beneficiation Breakthrough Process and subsequent Recovery stage for the high grade mineral concentrate produced post PFS.
Additional tests using the 'Beneficiation Breakthrough' flowsheet have been completed at two Perth laboratories on a number of additional samples of Ngualla's mineralisation during November. The work has successfully repeated previous results, thereby increasing confidence in the robustness of the process and the ability to produce a consistent high grade mineral concentrate.
Whilst the beneficiation breakthrough flowsheet is a bespoke flotation only process that has been developed for the Ngualla style of mineralisation, it is yet to be fully optimised. A beneficiation optimization program has commenced in Perth to investigate the potential for further improvements in mineral concentrate REO grades and / or recoveries.
Peak has also commissioned simultaneous beneficiation research programs at two technical institutes in China that have extensive experience in rare earth processing.
Preparation of a high grade mineral concentrate from a 1.3 tonne bulk sample of mineralisation using the 'Beneficiation Breakthrough' flowsheet has also commenced in Perth. The resulting mineral concentrate will be used as feed for additional testwork on further improving and optimising the downstream acid recovery flowsheet.
The results of these beneficiation and leach recovery optimization programs will be used to design pilot plants to provide operating data to assist in upscaling the developed processes to the commercial operation. To this end, a 22 tonne bulk sample of typical mineralisation has been collected by a trenching program on site at Ngualla and is in transit to Australia to
provide feed for the pilot plants. Design and operation of the pilot plants will be completed in 2015 as part of the BFS.
The production of a high grade mineral concentrate may offer the potential to reduce Ngualla's operating costs by locating the subsequent recovery and separation stages of the processing plant close to port and power facilities which should allow Peak to reduce reagent, transport and power costs.
The build out of the Peak team for the development studies has also commenced and we look forward to providing further details on these appointments in due course.
Darren Townsend
Managing Director
The information in this report that relates to Metallurgical Test Work Results based on information compiled and / or reviewed by Gavin Beer who is a Member of The Australasian Institute of Mining and Metallurgy and a Chartered Professional. Gavin Beer is a Consulting Metall urgist with sufficient experience relevant to the activity which he is undertaking to be recognized as competent to compile and report such information. Gavin Beer consents to the inclusion in the report of the matters based on his information in the form and context in which it appe ars.