14 May 2012
Lonmin Plc
2012 Interim Results Announcement
Lonmin Plc, (Lonmin or the Company), the world's third largest Platinum producer, today announces its Interim Results for the half year period ended 31 March 2012.
HIGHLIGHTS
? Solid half year performance in a challenging environment:
o Platinum sales of 318,402 ounces - broadly flat on H1 2011 - impacted by significant disruptions to production
o Revenue basket price down 10% in Dollar terms
o Rand unit cost 10.9% up on H1 2011 - full year guidance maintained
o Net operating profit of $14 million - impacted by weak pricing and higher Rand costs
o Net debt of $356 million and net gearing contained at 11% - tighter working capital management
? Production momentum maintained at Marikana operations:
o Improved safety performance - LTIFR of 4.69 per million man hours worked vs 5.4 in H1 2011
o Tonnes produced at 5.8 million, 1.7% decrease - impacted by Section 54 safety stoppages
o 347,000 Section 54 tonnes lost, up 398%
o Ore reserves at 3.1 million centares, up 10.7% - healthy level being achieved
o Saleable metal in concentrate up 3.8% to 368,175 Platinum ounces
o High Concentrator recovery rates maintained - 85.5%
? Investing in growth for the future:
o Continued investment in our growth shafts to increase our production capacity at Marikana
o Balancing capex spend with return on projects and prudent balance sheet management remains key
? Market outlook:
o Gradual industrial and auto demand recovery
o Supply constraints by South African producers will lead to deficits
o Near term pricing outlook remains unpredictable
o Medium to long term market fundamentals remain positive as demand will outstrip supply
? 2012 guidance on track:
o 750,000 Platinum ounces absent any further abnormal production interruptions from safety stoppages, labour and community unrest
o Guidance maintained for the full year at 8.5% on Rand unit operating costs
o Capex spend maintained at $450 million - but maintain flexibility to moderate consistent with markets and balance sheet prudence
o Number Two Furnace commissioning on schedule for Q3
Ian Farmer, Chief Executive Officer, commented:
"Lonmin performed well in a period where unprecedented high levels of Section 54 safety stoppages, labour and community unrest impacted on our production. The impact was slightly less in Quarter Two however as we saw the benefits of our partnership approach with the DMR in tackling the safety journey start to come through. We expect production to ramp up in the second half as normal, absent any further abnormal disruptions.
The inflationary increases in our costs and what seemingly appears to be an unrelenting depressed pricing environment also impacted our profitability and cash flows. We have been managing our net debt closely and will continue to do so. We remain on track to meet our full year guidance.
Whilst we are continuing to invest in our growth shafts at Marikana to build our production profile and ultimately achieve the optimal cost profile for our operations, we do so with an element of caution in a market where demand is currently soft. In our view the medium to long term PGM market fundamentals however, remain sound and this strategy will benefit our shareholders as the market improves. We are therefore predisposed towards the continuation of our investment programme but we will defer capital to the extent deemed necessary to remain within prudent debt parameters.
I am pleased to report that we have made considerable progress with further improving our safety record and our LTIFR has been trending positively as we continue to focus on the safety initiatives we embarked on last year to drive further improvements."
FINANCIAL HIGHLIGHTS
|
6 months to
31 March 2012 |
|
6 months to
31 March 2011 |
|
|
|
|
Revenue |
$751m |
|
$938m |
Underlying i operating profit |
$14m |
|
$148m |
Operating profit ii |
$14m |
|
$144m |
Underlying i profit before taxation |
$6m |
|
$149m |
Profit before taxation |
$18m |
|
$159m |
Underlying i (loss) / earnings per share |
(6.9)c |
|
45.0c |
(Loss) / earnings per share |
(11.8)c |
|
44.5c |
|
|
|
|
|
|
|
|
Trading cash inflow per share iii |
55.6c |
|
148.4c |
Free cash (outflow) / inflow per share iv |
(41.6)c |
|
54.3c |
|
|
|
|
|
|
|
|
Net debt as defined by the Group v |
$356m |
|
$296m |
|
|
|
|
|
|
|
|
Interest cover (times) vi |
8.4x |
|
11.3x |
Gearing vii |
11% |
|
9% |
|
|
|
|
Notes on Financial Highlights:
i |
Underlying results and earnings per share are based on reported results and earnings per share excluding the effect of special items as disclosed in note 3 to the interim statements. |
ii |
Operating profit is defined as revenue less operating expenses before impairment of available for sale financial assets, finance income and expenses and before share of profit of equity accounted investments. |
iii |
Trading cash flow is defined as cash flow from operating activities. |
iv |
Free cash flow is defined as trading cash flow less capital expenditure on property, plant and equipment and intangibles, proceeds from disposal of assets held for sale and dividends paid to non-controlling interests. |
v |
Net debt as defined by the Group comprises cash and cash equivalents, bank overdrafts repayable on demand and interest bearing loans and borrowings less unamortised bank fees. |
vi |
Interest cover is calculated for the 12 month periods to 31 March 2012 and 31 March 2011 on the underlying operating profit divided by the underlying net bank interest payable excluding exchange. |
vii |
Gearing is calculated as the net debt attributable to the Group divided by the total of the net debt attributable to the Group and equity shareholders' funds. |
ENQUIRIES:
Investors / Analysts:
Tanya Chikanza +44 (0) 207 201 6007
Head of Investor Relations
Ruli Diseko
Investor Relations Manager +44 (0) 207 201 6000
Media:
Cardew Group +44 (0) 207 930 0777
James Clark/Emma Crawshaw
Inzalo Communications +27 (0) 11 646 9992
Gillian Findlay
This press release is available on www.lonmin.com. A live webcast of the Interim Results presentation starting at 09.00hrs (London) on 14 May 2012 can be accessed through the Lonmin website. There will also be a web question facility available during the presentation. An archived version of the presentation, together with the presentation slides, will be available on the Lonmin website.
Chief Executive's Review
1 Introduction
I am pleased to report that we delivered a solid operational performance in the first half of the 2012 financial year in spite of the known and significant disruptions that we experienced during the period. The results reflect the healthy state of our operating assets and a team that is growing in its confidence and ability to deliver in a challenging environment. The key features during this first half are as follows.
Our mining operations produced 5.8 million tonnes in the first half of 2012, a decrease of 1.7 % when compared to the 2011 half year. Productivity was impacted by the uncharacteristically high Section 54 safety stoppages that were seen across the South African PGM mining industry during this period, labour and community unrest as well as management induced safety stoppages. The total impact of these disruptions in the period was a loss of some 464,000 tonnes, compared to 166,000 tonnes lost in 2011 half year.
Metals in Concentrate were up 3.8 % to 368,175 Platinum ounces whilst Platinum sales, at 318,402 were in line with 2011 half year. Revenue was however significantly impacted by lower PGM prices and volumes sold and fell by 20% to $751 million. The weak pricing environment and higher unit costs have significantly impacted our profitability and today we report operating profits for the half year of $14 million compared to $144 million in the prior year period and profit before tax of $18 million compared to profit before tax of $159 million in 2011 first half..
In March 2012, we entered into a pre-paid sale of 70,700 gold ounces and yielded around $107 million in cash flow.. The proceeds from this arrangement have provided flexibility around our debt headroom and at 31 March 2012 we have a moderate net debt level of $356 million, compared to the net debt of $234 million we had at the beginning of the financial year. This represents a relatively low gearing of 11%.
2 Safety performance
The safety of our employees is our first consideration in everything we do. Regrettably we recorded one fatality during the period and we extend our sincere condolences to the family and friends of Mr Albino Moises Cuna who died in December 2011.
We have made considerable progress with improving our safety results. Our Lost Time Injury Frequency Rate (LTIFR) at 4.69 per million man hours worked showed an improvement when compared to the 2011 year rate of 4.71 per million hours and 5.4 for the same period in 2011. During the period, Rowland shaft continued to be an industry leader as it recorded the significant industry achievement of 12.9 million Fall of Ground Fatality Free Shifts over a ten year period. We also recorded a best ever five million Fatality Free Shifts for Lonmin as a whole. We remain diligently focused on improving our safety working in partnership with the Department of Mineral Resources (DMR).
3 Mining Division
Introduction
Our Marikana mining operations have been able to maintain production despite the headwinds of industrial relations, Section 54 safety stoppages and community unrest. I believe this reflects the healthy technical state of the business and the team's competency.
The total impact of the Section 54 Safety shutdowns was 347,000 tonnes in lost production across all operations including the joint venture, compared to 70,000 tonnes in the 2011 half year.. The frequency of stoppages and losses in tonnage was quite marked, particularly in January when around 100,000 tonnes of production were lost. Following some high level dialogue across all levels of the DMR around the end of January, losses have subsequently fallen to lower levels.
We incurred an additional 48,000 and 69,000 tonnes of lost production as a result of management induced safety stoppages, and community and labour unrest at our operations respectively.
Production statistics for the second quarter of the year can be found in a separate announcement published today.
Grade
Underground milled head grade fell to 4.48 grammes per tonne in the first half of 2012 from 4.56 grammes per tonne in the prior year period as a result of an increase in the overall contribution of Merensky ore to the mix. The overall head grade for the same period including open cast however, increased by 1.8% from 4.34 grammes per tonne to 4.42 grammes per tonne as a result of an increase in the opencast grade and a decrease in opencast ore in the mix. The Merensky:UG2 mix is now 27%, up from 23% in the prior year period. Overall we are comfortable, that given our current mining mix, the current grade is in line with expectations.
Development
We continue to make progress in improving our ore reserve position and immediately available ore reserves at Marikana at the end of the first half of the 2012 financial year were 3.1 million centares compared to 2.9 million centares at the end of the 2011 financial year and 2.8 million centares at 31 March 2011. This represents around 19 months of current production and supports Lonmin's capacity growth strategy.
Mine production
Overall production at our operations of 5.8 million tonnes for the period, compared to 5.9 million tonnes for the prior year period has been satisfactory.
Total underground tonnes mined from the Marikana operations were relatively flat at 5.5 million compared to the first half of 2011. The greatest contribution was made by Karee which mined 2.5 million tonnes compared to 2.2 million in the same period last year, despite losing 90,000 tonnes to Section 54 safety stoppages.
Production from our Middelkraal unit, comprising of Hossy and Saffy shafts, mined 965,000 tonnes, an increase of 5% when compared against 919,000 tonnes in the prior year period. Middelkraal had one of the highest frequency of Section 54s, losing 121,000 tonnes during the six months to 31 March 2012. Saffy's ramp up has also been slightly slower than anticipated due to poor ground conditions. We are making progress with our programme of introducing hybrid mining in some upper quadrants at Hossy, to minimise the risks of interruption to production from machine breakdowns and lack of availability of artisans. We are converting the top levels of the shaft to hybrid. The middle sections are remaining on XLP, whilst the bottom levels are being developed conventionally. Production at Hossy has increased by around 23% to 465,000 tonnes when compared to the prior year, supporting the approach taken.
At Easterns, production declined by 10% to 556,000 tonnes, mainly due to community unrest and having lost 10,000 tonnes as a result of Section 54 safety stoppages.
At Westerns, the planned decline in production at Newman shaft, and lost production due to Section 54s of 86,000 tonnes at both Newman and Rowland shafts contributed to production at Westerns falling by 12.6% from the prior year period to 1.5 million tonnes.
We continued to scale back on our production at the Merensky opencast operations as we focused on grade improvement. We produced 196,000 tonnes compared to 336,000 tonnes in the prior year period.
Underground production at Pandora, our joint venture, is increasing at a steady rate and contributed 104,000 attributable tonnes for the first half of 2012, an increase of 25.3% when compared against the prior year period. Lonmin purchases 100% of the ore from the Pandora joint venture and this ore contributed 15,608 saleable Platinum ounces in concentrate and 29,617 saleable PGM ounces in concentrate to our production, representing increases of 40.9% and 40.3% respectively from the prior year period due to higher volumes and better grades.
We expect our production performance in the second half of 2012 to continue to be supported by increased contributions from our major shafts, K3 and Rowland as well as the continued ramping up of Saffy and Hossy shafts.
4 Process Division
Introduction
The performance of our Process Division was impacted by a build up of stocks in the Smelter, as explained below. The overall refining recovery rate which measures recoveries across the processing chain was a satisfactory 81.3 % for the half year, a decrease from the 2011 year end rate of 82.5%.
Concentrators
Total tonnes milled were flat at 6.0 million for the half year to 31 March 2012 when compared to the prior year period whilst total Metals in concentrate production from Marikana increased by 2.3 % to 351,695 saleable ounces of Platinum driven by higher grades as a result of increased underground ore tonnes milled.
Total metals in concentrate produced increased by 3.8% from 354,863 saleable Platinum ounces for the half year 2011 to 368,175 and saleable PGM ounces increased by 2.0% from 667,088 to 680,528 in the same period.
The Easterns tailings treatment plant was successfully commissioned during March 2012. This plant is already showing early signs of contributing to an improvement in concentrator recoveries in the Easterns concentrators.
Smelters and Refineries
Total refined production for the six months to 31 March 2012 was 304,329 ounces of Platinum and 601,540 ounces of PGMs, a decrease of 3.9% and 11.6% respectively on the prior year period. The decrease has arisen as refined production was temporarily affected by a smelting stock build up due to an increase in sulphur in the feed to the smelter. This occurred as a result of a greater percentage of Merensky ore being milled due to the series of Section 54 safety stoppages and internal safety stoppages that predominantly impacted our UG2 production. The PGM percentage decrease is greater due to a disproportionately higher number of Other Precious Metals which were returned by third party toll refiners during the prior year period. The Smelter will operate at normal stock levels by the end of the third quarter.
Plans for the commissioning of the new Number Two Furnace are on schedule for the third quarter. While there is an inherent risk within the commissioning procedure, the Processing team will be working through a comprehensive implementation plan to ensure a safe and successful start up.
5 Cost management
Management continued to focus on operational delivery in an environment that faced severe business disruption. Containing operational costs has consequently been challenging. Our gross Rand operating costs increased by 9.4 % from R5.3 billion to R5.8 billion mainly as a result of inflationary increases. We also incurred high cost ounces at K4 as it commences early stage production. The overall effect of these factors was to increase unit cost by 10.9% to R8,172 per PGM ounce produced when compared to the first six months of 2011. Adjusted for the impact of Section 54 stoppages, labour unrest and deferred stripping costs, the increase would have been 9.2%. Production volumes are traditionally second half weighted benefiting unit costs in the second half of the year.
Managing structural unit cost inflation and arresting the decreasing productivity trend is paramount and is receiving attention through a number of integrated initiatives such as our line of sight management system that tracks and rewards productivity. A new team training system has also been piloted at the 1B/4B shaft at Karee and positive results are in evidence. It will be gradually rolled out to other shafts over the coming months.
6 Progress with transformation objectives and equity ownership
Human Resources Development
Transformation is a fundamental element of our licence to operate and the right thing to do, and we are pursuing a number of initiatives within our Human Resource Development (HRD) plan which enable a holistic approach to our transformation strategy. In April 2012, the Minister of Mineral Resources, Ms Susan Shabangu officially opened the new Lonmin Artisan Training Centre at Marikana. This facility, is an important building block in our HRD strategy and complements the bursary programme, the mining skills training and Adult Basic Education and Training (ABET) to enable us to offer a full spectrum of up-skilling opportunities to people within the local community and nationally whatever their level of current educational advancement. As a result we are well placed to feed Lonmin's future talent requirements over time.
We are making good progress with our equity targets and as at 31 March 2012, 35% of management was Historically Disadvantaged South Africans (HDSA). We are committed to various social projects and raising visibility thereof within the community. We will report progress in this area in more detail at year end.
Equity ownership
A Concept Paper has been submitted to the DMR outlining our proposal for increasing BEE equity ownership to achieve Phase Two compliance by 2014. Good progress has been made in discussions with the DMR in clarifying the different initiatives we are progressing. These include incorporating broad based ownership around employees and our communities via ESOPs and community ownership schemes and migrating HDSA equity and royalty holdings in the various Lonmin entities into Lonmin Plc as well as consolidating future HDSA ownership at this level.
Shanduka, our BEE partner is also undertaking a feasibility study on Limpopo which if positive will result in Shanduka acquiring a direct stake in the Limpopo operations. The feasibility study is expected to be completed in quarter four of this financial year. We will report our progress in this area in more detail at the year end.
7 Market outlook
PGM prices weaker over review period
PGM prices were under downward pressure in the six month period ending 30 March 2012, compared to the same period a year before. Platinum weakened by 10% from an average of $1,745 per ounce in first half of 2011 to $1,566 per ounce in the first half of 2012, while palladium declined 11% from $734 per ounce to $655 per ounce and rhodium lost 36% year on year to $1,524 per ounce. However, the price weakness in Dollar terms was largely offset by a 14% weakening of the Rand against the Dollar, resulting in the overall Rand basket price declining by 0.5% to R9, 600 per ounce over the corresponding period.
Automotive demand encouraging
The recovery in the auto industry, our largest end use market, continues despite the uncertain global economic conditions. Companies such as LMC Automotive are still forecasting unit volume growth of 5% for 2012 and 8% per year in the two years after that.
The growth is however more subdued than previously anticipated and somewhat fragmented. Demand in Europe is declining but is expected to stabilise in 2013 and Euro 6 emission legislation requirements for the 2014 model year will start to provide a boost for platinum in Europe in 2013. Demand from China was flat in the first quarter of 2012 but is expected to accelerate as the year progresses.
However, the US has experienced strong overall demand growth of 13% in the first quarter of calendar 2012. Much of the strength in the US market is coming from pent-up demand, with the average age of their cars at 10.8 years and with fuel prices rising, many buyers are opting to buy more fuel efficient cars. Diesel and hybrid sales for example have increased in Q1 by 35% and 37 % respectively, with diesel vehicles now accounting for around 3% of US sales.
Investment demand remaining steadfast
Platinum ETFs have withstood recent price movements relatively well, with ETF holdings dropping late last year, when prices softened but adding these ounces back in early 2012. We believe that the investment market has matured and will continue to exhibit this "stickiness", particularly once industrial fundamentals become the main price driver. We therefore continue to hold the view that the investment sector will be a net contributor to demand over time.
The palladium investment market has shown a bit more volatility, but that can be expected in a market where the price has increased almost four-fold in the space of two years against a backdrop of uncertain economic conditions. As is the case in platinum, ETF volume movements in recent months appear to be following prices. This will have important implications when we enter the PGM recovery phase as the investment market may not be providing the liquidity needed in a deficit market if investors believe prices are going to rise further.
Supply forecasts
Platinum supply estimates have been progressively revised downwards since 2007, due to supply disruptions and constraints in South Africa. 2012 has already seen disruptions affecting over 200,000 ounces worth of production due to strikes and industry wide safety related stoppages. Some analysts are estimating that 2012 could see supply disruptions of up to 400-500,000 ounces, which would almost certainly lead to supply deficits, despite softer demand.
PGM Supply-Demand estimates
We have changed our view of a marginally oversupplied platinum market in 2012, to one of slight deficit. This is largely due to supply disruptions from South Africa. However industrial users have taken advantage of recent low prices and find themselves well stocked at a time when the rate of global growth is once again unclear. As a result we are likely to see a short term period of price weakness until such time as this situation unwinds. When this occurs we do not expect the supply response to be robust enough to meet a sustained recovery in demand which we now anticipate during 2013. We expect this to lead to deepening market deficits and rising prices in coming years.
Palladium is expected to head for large deficits as Russian exports are drying up and gasoline auto markets such as the US and China are showing stronger growth than the diesel auto market in Europe. Continued substitution of platinum by palladium is also expected to drive demand in the next few years.
The rhodium market is still seen as oversupplied this year, but may also move into a small deficit by 2013 on the back of recovering auto and industrial demand and its low price.
PGM Market Outlook
In summary, short term conditions are likely to be difficult to predict due to high working inventories and investor speculation. However, with the market already moving towards a deficit, conditions will get tighter as supply will not be able to keep up with recovering demand and we expect deeper deficits in the 2013 to 2015 period.
8 Maintaining balance sheet strength whilst investing capital for growth
Marikana
We continue to focus on growing our capacity to achieve target production and sales volumes of 950,000 Platinum ounces. We are in the attractive position of having three new generation shafts; Hossy, Saffy and K4, as well as sub declines at K3 and Rowland in which we are investing to grow our production capacity and ultimately achieve the lower cost and improved profitability profile for our operations.
We have been successful in thrifting our Rand capital expenditure, but given the strength of the Rand, this translated into capital expenditure of $197 million in the first half. Our capital programme guidance for 2012 remains around $450 million funded by operating cash flow and debt.
Other assets
We are making progress with the feasibility study on Pandora which is a proposed extension of the current underground operations from the E3 shaft and a new incline shaft in the Pandora block. The study is expected to complete in the Quarter Three. The pre-feasibility study on the mining and processing at 240,000 tonnes per month at Akanani is also progressing and is expected to complete in Quarter Four.
We are encouraged with the positive prefeasibility study on the potential modest open pit operation on our Vale PGM joint venture in Sudbury and together with our partner are contemplating next steps. Encouraging results from other properties in the joint venture are being followed up in the summer drilling programme.
We have increased our equity in Wallbridge Mining Company back to close to 16% and elected to form a further joint venture on the prospective North Range properties, the second such PGM joint venture with Wallbridge in the Sudbury area.
9 Looking ahead
Safety
Achieving our goal of safe production requires constant vigilance. We will endeavour to continue to foster a partnership approach with the DMR in tackling this journey and in doing so we hope to minimise the frequency of safety interventions by the inspectorate.
Labour
Successfully managing labour relations represents the biggest challenge to the effective operation of our mines and indeed the industry as a whole. Labour dynamics are going through a sea change, with the emergence of an alternative trade union in the PGM mining industry, in the form of the Association of Mineworkers and Construction Union (AMCU), to rival the dominance of NUM. The rivalry for membership between the unions could be a feature for the foreseeable future with a corresponding increase in the risk of escalation of costs and disruptions to production.
AMCU now has a presence at our Karee mining division where a third of the employees have become members. We have agreed limited organisational rights with AMCU to reflect this position.
Overall we continue to professionally manage the relationship with the individual unions as stakeholders and representatives of our employees, constructively engaging with representatives on a regular basis to mitigate the risk adverse labour relations may pose to the business.
We will also continue to adopt a zero tolerance approach to those that practice intimidation and violence and the South African law enforcement agencies have been fully supportive of this approach.
Community unrest and resource nationalism
As a result of high unemployment and poverty, social and community unrest is an increasing risk. We experienced business disruption as a result of this several times during the first half of 2012. We are aware of this issue and constantly engage with relevant community stakeholders.
The ground swell of support for the Nationalisation of the mining industry appears to have finally been discounted. However, the debate surrounding Resource Nationalism and the Mining sector's ability to contribute to the country's development continues apace and we can expect this to persist throughout this year as the ANC prepares for its policy conference in June and its leadership elections in December.
10 Keysha
In January 2012, the Director General of the DMR rejected Lonmin's appeal against the granting to Keysha Investments 220 (Pty) Limited of a prospecting right for associated minerals and metals that are found as part our PGM ore body on part of our mining right area. We have appealed to the Minister as is required by the process laid down by the MPRDA. We remain confident of our legal position and given our view that this decision is procedurally and substantively incorrect, are taking the necessary measures to protect Lonmin's rights. This will include taking the matter to Court for review if necessary.
11 Outlook
We have delivered a solid operational performance despite the headwinds of a difficult operating environment. Whilst the period has been challenging, it has given us the opportunity to demonstrate that our assets are technically healthy and the team is well capable of tackling the challenges effectively.
Guidance
We expect momentum to build up in the second half and we are maintaining our guidance, absent any abnormal disruptions, of safely and profitably producing around 750,000 Platinum ounces for the full 2012 with a unit cost increase per PGM ounce of around 8.5% - in line with wage settlements.
We expect our production performance in the second half of 2012 to continue to be supported by the following:
? Improved production performance and consistency at K3 shaft as it benefits from improved ore reserves. Successful management of labour relations at Karee however will be important given the split of employees between non-unionised employees, members of NUM and AMCU;
? Continuing momentum at Rowland which will offset the ongoing planned decline of Newman;
? Continued ramping up of production at Middelkraal's Hossy and Saffy. We expect the poor ground conditions that have been seen at Saffy to remain a feature for the rest of the year;
? Positive contribution from Easterns supported by healthy ore reserves whilst closely monitoring the area to mitigate the risk of community unrest; and
? Sustained concentrator recoveries at the levels achieved in the first half.
Our guidance for 2012 capex spend remains at $450 million, the bulk of which is either committed or has been spent. The objectives of the capex programme are to reduce costs at Marikana, in particular at our three growth shafts, and to work towards our target capacity of 950,000 profitable Platinum ounces. Our expectations for the medium term price environment for PGMs support our predisposition towards the continuation of the investment programme. However, we are not immune to the effect on cash flow from short term prices, the outlook for which remains uncertain. Given our stated intent to manage the balance sheet prudently and produce profitable ounces, we will defer this capital investment to the extent deemed necessary. We are watching the situation carefully and as we have demonstrated in the past, we will react if we deem it prudent to do so.
12 Employee contribution
Finally, I would like to express my sincere gratitude to all our employees, contractors and community members for their support and commitment to delivering a solid performance in the first half of 2012.
Ian Farmer
Chief Executive Officer
11 May 2012
Financial Review
Overview
The 2012 interim period has been characterised by declining profitability driven mainly by reduced revenues. Automotive and industrial demand for PGMs has remained subdued which has had an adverse impact on the pricing environment. The volume of PGMs sold has also declined from the 2011 interim period. This is due to anticipated production increases not materialising as a result of production losses due to heightened Section 54 stoppages as well as management induced safety stoppages and community unrest disruptions.
On the cost side, wage and electricity tariff increases continued at above inflation rates putting further strain on profitability. However, the resultant increase in costs was mitigated by favourable exchange movements and positive metal stock movements. Unit costs remain under pressure as cost escalations have not been offset by the expected increase in production as mentioned above. The C1 unit cost per ounce produced for the 2012 interim period was 10.9% higher than the comparative 2011 period.
We continue to invest in capital expenditure as we build our production base. Not only will this allow us to meet our objective of moving down the industry cost curve, but it will also enable us to increase production from our Marikana infrastructure at a time when we believe that the market will require the additional production. While this has had the consequence of increasing our net debt to $356 million at 31 March 2012, our gearing at 11% remains relatively low. We continue to demonstrate balance sheet capacity afforded us by existing debt facilities and other funding measures we are able to execute in the short term. One such funding measure was the prepaid sale of gold undertaken in March which yielded $107 million in cash flow.
We will constantly monitor and balance the need to invest for future production and the requirement to maintain a strong balance sheet, with the overriding objective to provide an optimal return for our shareholders.
Income Statement
The $134 million movement between the underlying operating profit of $14 million for the six months ended 31 March 2012 and that of $148 million for the six months ended 31 March 2011 is analysed below.
|
|
$m |
|
Period to 31 March 2011 reported operating profit |
144 |
|
Period to 31 March 2011 special items |
4 |
|
Period to 31 March 2011 underlying operating profit
|
148 |
|
PGM price
PGM volume
PGM mix
Base metals |
(119)
(92)
37
(13) |
|
Revenue changes |
(187) |
|
Cost changes (including foreign exchange impact of $60m) |
53 |
|
Period to 31 March 2012 underlying operating profit |
14 |
|
Period to 31 March 2012 special items |
- |
|
Period to 31 March 2012 reported operating profit |
14 |
Revenue
Total revenue decreased by $187 million from the six months ended 31 March 2011 to $751 million for the six months ended 31 March 2012.
As noted in the overview the PGM pricing environment during the period deteriorated over the prior period and the impact on the average prices achieved on the key metals sold is shown below:
|
Six months ended
31.03.12 |
Six months ended
31.03.11 |
|
$/oz |
$/oz |
Platinum |
1,568 |
1,777 |
Palladium |
660 |
755 |
Rhodium |
1,462 |
2,345 |
PGM basket (excluding by-product revenue) |
1,155 |
1,290 |
PGM basket (including by-product revenue) |
1,231 |
1,382 |
The US Dollar PGM basket price (excluding by-products) decreased by 10% contributing $119 million to the overall decline in revenue.
While Platinum sales volume was in line with that achieved in the 2011 comparative period, PGM sales volume for the six months to 31 March 2012 at 608,579 ounces was down 10% on the six months to 31 March 2011.The decline in PGM volumes had a negative effect of $92 million. Overall production was significantly impacted by increased production losses associated with Section 54 and management induced safety stoppages as well as community unrest. However, the mix of metals sold resulted in a positive impact of $37 million mainly due to the higher proportion of Platinum arising from metal-in-process inventory timing differences. Base metal revenue was down $13 million due to a combination of volume and price movements.
Operating costs
Total underlying costs in US Dollar terms decreased by $53 million with the impact of cost escalations being offset by a combination of reduced production (from opencast and toll refining), positive foreign exchange movements and a build up of stock in process. A track of these changes is shown in the table below:
|
$m |
Six months ended 31 March 2011 - underlying costs |
790 |
Increase / (decrease):
|
|
Marikana underground mining
Marikana opencast mining
Limpopo mining
Concentrating and processing
Overheads |
56
(10)
3
5
17 |
Operating costs |
71 |
Pandora and W1 ore purchases
Metal stock movement
Foreign exchange
Depreciation and amortisation |
3
(68)
(60)
1 |
Cost changes (including foreign exchange impact) |
(53) |
Six months ended 31 March 2012 - underlying costs |
737 |
Marikana underground mining costs increased in the period by $56 million or 12%, mainly due to wages and electricity costs escalating at rates above average CPI. There was also a marginal increase in underground production. Marikana opencast mining costs decreased by $10 million or 40% largely driven by a reduction in production reflecting the continued slowdown in opencast production that commenced in the first quarter as we focus on grade improvement.
Concentrator and processing costs increased by $5 million or 3%, on the prior year period, as cost escalation effects were diluted by a decrease in toll refined metal production.
Ore purchases increased by $3 million or 10% on the back of increased volumes of ore purchased.
Overheads increased by $17 million or 30% largely due to cost escalation effects. Additional spend was also made on exploration and in the sustainability and transformation areas (e.g. bursaries, training and community projects), in line with our commitment to meeting our Mining Charter targets.
The six months under review saw a build up of stock in process as ore mix challenges affected smelter efficiency. This has resulted in a $68 million positive impact on operating profit, excluding exchange impacts, arising from metal stock movements.
The Rand weakened considerably against the US Dollar during the period under review averaging ZAR7.91 to USD1 compared to an average of ZAR6.93 to USD1 in the 2011 period resulting in a $60 million positive impact on operating costs.
Cost per PGM ounce
The C1 cost per PGM ounce produced for the six months to 31 March 2012 was R8,172. This was an increase of 10.9% compared to the same period in 2011. This increase was largely driven by higher than inflation increases in the wage bill (8.5%) and electricity tariffs (24%). These escalations were not mitigated by the expected increase in production due to the increased Section 54 and management induced safety stoppages as well as community unrest disruptions during the period.
Further details of unit costs analysis can be found in the Operating Statistics.
Special operating costs
There were no special operating costs incurred for the six months ended 31 March 2012.
Impairment of available for sale financial assets
The $6 million impairment of available for sale financial assets represents the loss in value of our share in Platmin Limited following the company's delisting in December 2011.
Net finance income
|
6 months to 31 March |
|
2012
$m |
|
2011
$m |
Net bank interest and fees |
(11) |
|
(20) |
Capitalised interest payable and fees |
10 |
|
20 |
Exchange |
(2) |
|
2 |
Other |
(6) |
|
(4) |
Underlying net finance costs |
(9) |
|
(2) |
HDSA receivable |
18 |
|
14 |
Net finance income |
9 |
|
12 |
The total net finance income of $9 million for the six months ended 31 March 2012 represents a $3 million adverse movement compared to the total net finance income of $12 million for the six months ended 31 March 2011.
Net bank interest and fees decreased from $20 million to $11 million for the six months ended 31 March 2012 largely as a result of a lower average net debt during the period and substantially better interest rates on debt funding. Interest totalling $10 million was capitalised to assets (2011 - $20 million).
The Historically Disadvantaged South Africans (HDSA) receivable, being the Sterling loan to Shanduka Resources (Proprietary) Limited (Shanduka), increased by $18 million during the period to 31 March 2012 representing exchange movements and accrued interest.
Taxation
Reported tax for the current six month period was a charge of $52 million which exceeds the recorded profit before tax of $18 million. This was largely driven by foreign exchange impacts arising from the fact that overseas tax charges are predominantly calculated in Rand as required by the local authorities while the functional currency of these subsidiaries is US Dollar. These exchange impacts have added $39 million to the reported tax charge split between exchange impacts on the translation of Rand denominated current and deferred tax balances ($26 million) and exchange impacts on Rand taxable profits ($13 million). A detailed tax rate reconciliation is included in note 5 to the financial statements.
Cash generation and net debt
The following table summarises the main components of the cash flow during the year:
|
|
|
Six months ended 31 March |
|
|
|
2012 |
|
2011 |
|
|
|
$m |
|
$m |
Operating profit |
|
|
14 |
|
144 |
Depreciation, amortisation and impairment |
|
|
61 |
|
62 |
Changes in working capital |
|
|
40 |
|
109 |
Other |
|
|
15 |
|
12 |
Cash flow generated from operations |
|
|
130 |
|
327 |
Interest and finance costs |
|
|
(12) |
|
(19) |
Tax |
|
|
(8) |
|
(7) |
Trading cash inflow |
|
|
110 |
|
301 |
Capital expenditure |
|
|
(197) |
|
(191) |
Investment expenditure |
|
|
(4) |
|
(1) |
Free cash (outflow) / inflow |
|
|
(91) |
|
109 |
Dividends paid to equity shareholders |
|
|
(31) |
|
(30) |
Cash (outflow) /inflow |
|
|
(122) |
|
79 |
Opening net debt |
|
|
(234) |
|
(375) |
Foreign exchange |
|
|
1 |
|
- |
Unamortised fees |
|
|
(1) |
|
- |
Closing net debt |
|
|
(356) |
|
(296) |
|
|
|
|
|
|
Trading cash inflow (cents per share) |
|
|
55.6c |
|
148.4c |
Free cash (outflow) / inflow (cents per share) |
|
|
(41.6)c |
|
54.3c |
Cash flow generated from operations in the six months ended 31 March 2012 at $130 million reflects a $197 million decrease from the same period in 2011. This was largely as a result of subdued profitability on the back of lower revenues mainly driven by adverse price and volume movements. Cash flow generated from operations for the six months ended 31 March 2012 includes deferred revenue received on the forward sale of gold of $107 million as well as the benefit of improved payment terms negotiated with one of our large customers.
Trading cash inflow for the six months to 31 March 2012 amounted to $110 million (2011 - $301 million). The cash flow on interest and finance costs decreased by $7 million. Tax payments remained flat and represent provisional corporate tax payments. The trading cash inflow per share was 55.6 cents for the six months ended 31 March 2012 against 148.4 cents for 2011.
Capital expenditure cash flow at $197 million was $6 million above the prior period. In Mining the expenditure incurred was focused on operating developments at Hossy and Saffy shafts, equipping and development at K4 and investment in sub-declines at K3. In the Process Division spend largely comprised additional furnace capacity.
The proposed dividend of 15 cents per share for the financial year ended 30 September 2011 was paid during the period under review resulting in a cash outflow of $31 million.
Net debt at $356 million has increased by $122 million since 30 September 2011. Pressure on net debt as a result of subdued profitability and the continued capital programme was mitigated by the deferred revenue proceeds mentioned above.
As a result gearing, calculated on net borrowings attributable to the Group divided by those attributable net borrowings and the equity interests outstanding at the balance sheet date, was 11% at 31 March 2012 (31 March 2011 - 9%). We continue to closely monitor our liquidity risk as discussed in more detail under the financial risk management section below.
Principal risks and uncertainties
The Group faces many risks in the operation of its business. The Group's strategy takes into account known risks, but risks will exist of which we are currently unaware. There is an extensive discussion of the principal risks and uncertainties facing the Company on pages 37 to 40 of the 2011 Annual Report, available from the Company's website, www.lonmin.com. This financial review focuses on financial risk management.
Financial risk management
The main financial risks faced by the Group relate to the availability of funds to meet business needs (liquidity risk), the risk of default by counterparties to financial transactions (credit risk), fluctuations in interest and foreign exchange rates and commodity prices.
These are the critical factors to consider when addressing the issue of whether the Group is a Going Concern. As is clear from the following paragraphs, the Group is in a strong position regarding financial risk. There are, however, factors which are outside the control of management, specifically, volatility in the Rand / US Dollar exchange rate and PGM commodity prices, which can have a significant impact on the business.
Liquidity risk
The policy on liquidity is to ensure that the Group has sufficient funds to facilitate all ongoing operations. The Group funds its operations through a mixture of equity funding and borrowings. The Group's philosophy is to maintain an appropriately low level of financial gearing given the exposure of the business to fluctuations in PGM commodity prices and the Rand / US Dollar exchange rate. This is supplemented with additional risk mitigation strategies such as those described below in respect of foreign currency and commodity price risk.
As part of the annual budgeting and long term planning process, the Group's cash flow forecast is reviewed and approved by the Board. The cash flow forecast is amended for any material changes identified during the year, for example material acquisitions and disposals. Where funding requirements are identified from the cash flow forecast, appropriate measures are taken to ensure these requirements can be satisfied. Factors taken into consideration are:
? the size and nature of the requirement;
? preferred sources of finance applying key criteria of cost, commitment, availability, security / covenant conditions;
? recommended counterparties, fees and market conditions; and
? covenants, guarantees and other financial commitments.
During the course of 2011 Lonmin's bank debt facilities were reorganised into new facilities totalling approximately $945 million. These facilities have been operating smoothly and are adequate for the Group's current liquidity requirements.
As at 31 March 2012, Lonmin had net debt of $356 million, comprising $515 million of drawn facilities net of $157 million of cash and equivalents and $7 million of unamortised bank fees as well as a further $5 million of external debt incurred to fund the construction of a chrome treatment plant with an outside partner.
The effective cost of debt funding for the first half of the 2012 financial year was circa 4.6%.
Credit risk
Banking counterparties
Banking counterparty credit risk is managed by spreading financial transactions across an approved list of counterparties of high credit quality. Banking counterparties are approved by the Board and consist of the ten banks that participate in Lonmin's bank debt facilities. These counter-parties comprise: BNP Paribas S.A., Citigroup Global Markets Limited, FirstRand Bank Limited, HSBC Bank Plc, Investec Bank Limited, J.P. Morgan Limited, Lloyds TSB Bank Plc, The Royal Bank of Scotland N.V., The Standard Bank of South Africa Limited and Standard Chartered Bank.
Trade receivables
The Group is exposed to significant trade receivable credit risk through the sale of PGMs to a limited group of customers.
This risk is managed as follows:
? aged analysis is performed on trade receivable balances and reviewed on a monthly basis;
? credit ratings are obtained on any new customers and the credit ratings of existing customers are monitored on an ongoing basis;
? credit limits are set for customers; and
? trigger points and escalation procedures are clearly defined.
It should be noted that a significant portion of Lonmin's revenue is from two key customers. However, both of these customers have strong investment grade ratings and their payments terms are very short, thereby reducing trade receivable credit risk significantly..
HDSA receivables
HDSA receivables are secured on the HDSA's shareholding in Incwala.
Interest rate risk
Currently, the bulk of Lonmin's outstanding borrowings are in US Dollars. Of the USD borrowings, the base rate in respect of the $300 million term facility has been fixed through an interest rate swap for the term of the facility which runs until May 2016. In respect of the remaining USD borrowings and the ZAR borrowings these are at floating rates of interest linked to LIBOR and JIBAR respectively. The interest position is kept under constant review in conjunction with the liquidity policy outlined above and the future funding requirements of the business.
Foreign currency risk
The Group's operations are predominantly based in South Africa and the majority of the revenue stream is in US Dollars. However, the bulk of the Group's operating costs and taxes are paid in Rand. Most of the cash received in South Africa is in US Dollars. Most of the Group's funding sources are in US Dollars.
The Group's reporting currency is the US Dollar and the share capital of the Company is based in US Dollars.
Because of the current depressed level of our revenue basket when expressed in Rands and the sensitivity of this price to a strengthening Rand, a decision has been taken to use hedging instruments in respect of the Rand / US Dollar currency exposure for a portion of revenues in the second half of the 2012 financial year when the opportunity arises.
The approximate effects on the Group's results of a 10% movement in the Rand to US Dollar based on the year-to-date 2012 average exchange rate would be as follows:
|
EBIT |
+/- $67m |
|
Profit for the year |
+/- $39m |
|
EPS (cents) |
+/- 19.5c |
These sensitivities are based on year-to-date 2012 prices, costs and volumes and assume all other variables remain constant. Current hedges have not been taken into account in the calculations. They are estimated calculations only.
Commodity price risk
Our policy is not to hedge commodity price exposure on PGMs, excluding gold, and therefore any change in prices will have a direct effect on the Group's trading results.
For base metals and gold, hedging is undertaken where the Board determines that it is in the Group's interest to hedge a proportion of future cash flows. The policy is to hedge up to a maximum of 75% of the future cash flows from the sale of these products. The Group did not undertake any hedging of base metals under this authority in the financial period and no forward contracts were in place in respect of base metals at the end of the period.
In respect of gold, Lonmin entered into a pre-paid sale of 75% of its current gold production for the next 54 months in March 2012. In terms of this contract Lonmin will deliver 70,700 ounces of gold over the period with delivery on a quarterly basis and in return received an upfront payment of $107 million. This will be used to help fund the capital expenditure programme. The upfront receipt has been accounted for as deferred revenue on our balance sheet and will be released to profit and loss as deliveries take place at an average price of $1,510/oz delivered.
The approximate effects on the Group's results of a 10% movement in the year-to-date 2012 average metal prices achieved for Platinum (Pt) ($1,568 per ounce), Palladium (Pd) ($660 per ounce) and Rhodium (Rh) ($1,462 per ounce) would be as follows:
|
|
Pt |
Pd |
Rh |
|
EBIT |
+/- $50m |
+/- $9m |
+/- $7m |
|
Profit for the year |
+/- $29m |
+/- $5m |
+/- $4m |
|
EPS (cents) |
+/- 14.5c |
+/- 2.6c |
+/- 2.1c |
These sensitivities are based on year-to-date 2012 costs and volumes and assume all other variables remain constant. They are estimated calculations only.
Contingent liabilities
The Group provided third party guarantees to the Department of Minerals and Energy in connection with environmental and rehabilitation obligations which the Group has to fund in order to restore the environment once all mining operations have ceased. At 31 March 2012 these guarantees amounted to $54 million (2011 - $50 million).
Simon Scott
Chief Financial Officer
11 May 2012
Operating Statistics
|
|
|
Units |
6 months to
31 March
2012 |
6 months to
31 March
2011 |
Tonnes mined |
Marikana |
Karee 1 |
kt |
2,459 |
2,214 |
|
Westerns 1 |
kt |
1,508 |
1,725 |
|
Middelkraal 1 |
kt |
965 |
919 |
|
Easterns 1 |
kt |
556 |
615 |
|
Underground |
kt |
5,489 |
5,473 |
|
Opencast |
kt |
196 |
336 |
Pandora attributable 2 |
Underground |
kt |
104 |
83 |
Lonmin Platinum |
Underground |
kt |
5,593 |
5,556 |
Opencast |
kt |
196 |
336 |
|
Total |
kt |
5,789 |
5,891 |
|
% tonnes mined from the UG2 reef |
|
% |
71.0 |
72.4 |
Tonnes milled 3 |
Marikana |
Underground |
kt |
5,533 |
5,275 |
|
|
Opencast |
kt |
239 |
550 |
|
Pandora 4 |
Underground |
kt |
226 |
175 |
|
Lonmin Platinum |
Underground |
kt |
5,759 |
5,451 |
|
|
Opencast |
kt |
239 |
550 |
|
|
Total |
kt |
5,998 |
6,000 |
Milled head |
Lonmin Platinum |
Underground |
g/t |
4.48 |
4.56 |
grade 5 |
|
Opencast |
g/t |
2.89 |
2.20 |
|
|
Total |
g/t |
4.42 |
4.34 |
Concentrator |
Lonmin Platinum |
Underground |
% |
85.5 |
85.6 |
recovery rate 6 |
|
Opencast |
% |
85.0 |
81.8 |
|
|
Total |
% |
85.5 |
85.4 |
Metals in |
Marikana |
Platinum |
oz |
351,695 |
343,789 |
concentrate 7 |
|
Palladium |
oz |
159,805 |
161,419 |
|
|
Gold |
oz |
9,582 |
9,133 |
|
|
Rhodium |
oz |
44,338 |
44,982 |
|
|
Ruthenium |
oz |
69,023 |
71,091 |
|
|
Iridium |
oz |
15,009 |
15,564 |
|
|
Total PGMs |
oz |
649,452 |
645,978 |
|
Pandora 4 |
Platinum |
oz |
15,608 |
11,074 |
|
|
Palladium |
oz |
7,232 |
5,179 |
|
|
Gold |
oz |
118 |
77 |
|
|
Rhodium |
oz |
2,389 |
1,689 |
|
|
Ruthenium |
oz |
3,655 |
2,654 |
|
|
Iridium |
oz |
615 |
438 |
|
|
Total PGMs |
oz |
29,617 |
21,112 |
|
Concentrate purchases |
Platinum |
oz |
872 |
- |
|
|
Palladium |
oz |
310 |
- |
|
|
Gold |
oz |
3 |
- |
|
|
Rhodium |
oz |
104 |
- |
|
|
Ruthenium |
oz |
127 |
- |
|
|
Iridium |
oz |
43 |
- |
|
|
Total PGMs |
oz |
1,458 |
- |
|
Lonmin Platinum |
Platinum |
oz |
368,175 |
354,863 |
|
|
Palladium |
oz |
167,346 |
166,597 |
|
|
Gold |
oz |
9,703 |
9,210 |
|
|
Rhodium |
oz |
46,831 |
46,671 |
|
|
Ruthenium |
oz |
72,805 |
73,745 |
|
|
Iridium |
oz |
15,667 |
16,002 |
|
|
Total PGMs |
oz |
680,528 |
667,089 |
|
|
|
Units |
6 months to
31 March
2012 |
6 months to
31 March
2011 |
Metals in |
Lonmin Platinum |
Nickel 8 |
MT |
1,963 |
1,823 |
concentrate 7 |
|
Copper 8 |
MT |
1,258 |
1,157 |
Refined |
Lonmin refined metal production |
Platinum |
oz |
284,309 |
280,980 |
production |
|
Palladium |
oz |
136,502 |
138,386 |
|
|
Gold |
oz |
8,536 |
6,664 |
|
|
Rhodium |
oz |
51,760 |
38,524 |
|
|
Ruthenium |
oz |
72,969 |
72,407 |
|
|
Iridium |
oz |
16,705 |
13,411 |
|
|
Total PGMs |
oz |
570,782 |
550,372 |
|
Toll refined metal production |
Platinum |
oz |
20,019 |
35,854 |
|
|
Palladium |
oz |
4,189 |
48,635 |
|
|
Gold |
oz |
200 |
2,866 |
|
|
Rhodium |
oz |
1,662 |
13,892 |
|
|
Ruthenium |
oz |
3,682 |
23,999 |
|
|
Iridium |
oz |
1,006 |
5,091 |
|
|
Total PGMs |
oz |
30,759 |
130,337 |
|
Total refined PGMs |
Platinum |
oz |
304,329 |
316,834 |
|
|
Palladium |
oz |
140,691 |
187,021 |
|
|
Gold |
oz |
8,736 |
9,530 |
|
|
Rhodium |
oz |
53,421 |
52,416 |
|
|
Ruthenium |
oz |
76,651 |
96,406 |
|
|
Iridium |
oz |
17,711 |
18,502 |
|
|
Total PGMs |
oz |
601,540 |
680,709 |
|
Base metals |
Nickel 9 |
MT |
1,645 |
2,113 |
|
|
Copper 9 |
MT |
899 |
1,214 |
Sales |
Lonmin Platinum |
Platinum |
oz |
318,402 |
318,306 |
|
|
Palladium |
oz |
135,554 |
189,531 |
|
|
Gold |
oz |
9,333 |
8,638 |
|
|
Rhodium |
oz |
49,020 |
54,807 |
|
|
Ruthenium |
oz |
77,911 |
91,773 |
|
|
Iridium |
oz |
18,359 |
16,503 |
|
|
Total PGMs |
oz |
608,579 |
679,557 |
|
|
Nickel 9 |
MT |
1,793 |
2,110 |
|
|
Copper 9 |
MT |
870 |
1,077 |
|
|
Chrome 9 |
MT |
596,032 |
241,746 |
Average prices |
|
Platinum |
$/oz |
1,568 |
1,777 |
|
|
Palladium |
$/oz |
660 |
755 |
|
|
Gold |
$/oz |
1,673 |
1,125 |
|
|
Rhodium |
$/oz |
1,462 |
2,345 |
|
|
Ruthenium |
$/oz |
103 |
170 |
|
|
Iridium |
$/oz |
1,041 |
840 |
|
|
Basket price of PGMs 10 |
$/oz |
1,155 |
1,290 |
|
|
Basket price of PGMs 10 |
R/oz |
9,070 |
8,990 |
|
|
Basket price of PGMs 11 |
R/oz |
9,638 |
9,619 |
|
|
Nickel 9 |
$/MT |
16,087 |
22,241 |
|
|
Copper 9 |
$/MT |
7,321 |
8,720 |
|
|
Chrome 9 |
$/MT |
18 |
26 |
Footnotes:
1 |
Karee includes the shafts K3, 1B and 4B and will also include K4 once production commences. Westerns comprises Rowland, Newman and ore purchases from W1. Middelkraal represents Hossy and Saffy. Easterns includes E1, E2 and E3. |
2 |
Pandora attributable tonnes mined represents Lonmin's share (42.5%) of the total tonnes mined on the Pandora joint venture. |
3 |
Tonnes milled excludes slag milling. |
4 |
Lonmin purchases 100% of the ore produced by the Pandora joint venture for onward processing which is included in downstream operating statistics. |
5 |
Head grade is the grammes per tonne (5PGE + Au) value contained in the tonnes milled and fed into the concentrator from the mines (excludes slag milled). |
6 |
Recovery rate in the concentrators is the total content produced divided by the total content milled (excluding slag). |
7 |
Metals in concentrate includes slag and has been calculated using industry standard downstream processing losses. |
8 |
Corresponds to contained base metals in concentrate. |
9 |
Nickel is produced and sold as nickel sulphate crystals or solution and the volumes shown correspond to contained metal. Copper is produced as refined product but typically at LME grade C. Chrome is produced in the form of chromite concentrate and volumes shown are in the form of chromite. |
10 |
Basket price of PGMs is based on the revenue generated in Rand and Dollar from the actual PGMs (5PGE + Au) sold in the period based on the appropriate Rand/Dollar exchange rate applicable for each sales transaction. |
11 |
As per note 10 but including revenue from base metals. |
|
Units |
|
6 months to
31 March
2012 |
6 months to
31 March
2011 |
Capital Expenditure 1 |
Rm |
|
1,552 |
1,069 |
|
$m |
|
197 |
154 |
Group cost per PGM ounce sold 2 |
|
|
|
|
Mining - Marikana |
R/oz |
|
5,698 |
5,111 |
Concentrating - Marikana |
R/oz |
|
973 |
922 |
Process division |
R/oz |
|
961 |
920 |
Shared business services |
R/oz |
|
540 |
420 |
C1 cost per PGM ounce produced |
R/oz |
|
8,172 |
7,372 |
Stock movement |
R/oz |
|
(413) |
(337) |
C1 cost per PGM ounce sold before base metal credits |
R/oz |
|
7,759 |
7,036 |
Base metal credits |
R/oz |
|
(568) |
(629) |
C1 costs per PGM ounce sold after base metal credits |
R/oz |
|
7,190 |
6,407 |
Amortisation |
R/oz |
|
780 |
600 |
C2 costs per PGM ounce sold |
R/oz |
|
7,970 |
7,007 |
Pandora mining cost: |
|
|
|
|
C1 Pandora mining cost (in joint venture) |
R/oz |
|
5,326 |
5,340 |
Pandora JV cost/ounce produced to Lonmin (adjusting Lonmin share of profit) |
R/oz |
|
8,079 |
8,251 |
Exchange rates Average rate for period 3 |
R/$ |
|
7.91 |
6.93 |
Closing rate |
R/$ |
|
7.65 |
6.77 |
Footnotes:
1 |
Capital expenditure is the aggregate of the purchase of property, plant and equipment and intangible assets (includes capital accruals and excludes capitalised interest). |
2 |
Exchange rates are calculated using the market average daily closing rate over the course of the period. |
Responsibility statement of the directors in respect of the interim financial report
We confirm that to the best of our knowledge:
? the condensed set of financial statements has been prepared in accordance with IAS 34 Interim Financial Reporting as adopted by the EU; and
? the interim management report includes a fair review of the information required by:
(a) DTR 4.2.7R of the Disclosure and Transparency Rules, being an indication of important events that have occurred during the first six months of the financial year and their impact on the condensed set of financial statements; and a description of the principal risks and uncertainties for the remaining six months of the year; and
(b) DTR 4.2.8R of the Disclosure and Transparency Rules, being related party transactions that have taken place in the first six months of the current financial year and that have materially affected the financial position or performance of the entity during that period; and any changes in the related party transactions described in the last annual report that could do so.
For and on behalf of the Board
Roger Phillimore Simon Scott
Chairman Chief Financial Officer
11 May 2012
INDEPENDENT REVIEW REPORT TO LONMIN PLC
Introduction
We have been engaged by the company to review the condensed set of financial statements in the half-yearly financial report for the six months ended 31 March 2012 which comprises the consolidated income statement, consolidated statement of comprehensive income, consolidated statement of financial position, consolidated statement of changes in equity, consolidated statement of cash flows and the related explanatory notes. We have read the other information contained in the half-yearly financial report and considered whether it contains any apparent misstatements or material inconsistencies with the information in the condensed set of financial statements.
This report is made solely to the company in accordance with the terms of our engagement to assist the company in meeting the requirements of the Disclosure and Transparency Rules ("the DTR") of the UK's Financial Services Authority ("the UK FSA"). Our review has been undertaken so that we might state to the company those matters we are required to state to it in this report and for no other purpose. To the fullest extent permitted by law, we do not accept or assume responsibility to anyone other than the company for our review work, for this report, or for the conclusions we have reached.
Directors' responsibilities
The half-yearly financial report is the responsibility of, and has been approved by, the directors. The directors are responsible for preparing the half-yearly financial report in accordance with the DTR of the UK FSA.
As disclosed in note 1, the annual financial statements of the group are prepared in accordance with IFRSs as adopted by the EU. The condensed set of financial statements included in this half-yearly financial report has been prepared in accordance with IAS 34Interim Financial Reporting as adopted by the EU.
Our responsibility
Our responsibility is to express to the company a conclusion on the condensed set of financial statements in the half-yearly financial report based on our review.
Scope of review
We conducted our review in accordance with International Standard on Review Engagements (UK and Ireland) 2410 Review of Interim Financial Information Performed by the Independent Auditor of the Entity issued by the Auditing Practices Board for use in the UK. A review of interim financial information consists of making enquiries, primarily of persons responsible for financial and accounting matters, and applying analytical and other review procedures. A review is substantially less in scope than an audit conducted in accordance with International Standards on Auditing (UK and Ireland) and consequently does not enable us to obtain assurance that we would become aware of all significant matters that might be identified in an audit. Accordingly, we do not express an audit opinion.
Conclusion
Based on our review, nothing has come to our attention that causes us to believe that the condensed set of financial statements in the half-yearly financial report for the six months ended 31 March 2012 is not prepared, in all material respects, in accordance with IAS 34 as adopted by the EU and the DTR of the UK FSA.
Robert M. Seale
for and on behalf of KPMG Audit Plc
Chartered Accountants
15 Canada Square
London E14 5GL
11 May 2012
To unsubscribe from alerts, please visit Lonmin PLC's website.