17 March 2014
LENDERS UPDATE
Discovery Metals Limited (ASX/BSE: DML) (Discovery Metals, or the Company) provides a further update in regards to its Boseto Project Finance Facility (PF Facility) and its Single Currency Revolving Facility Agreement (SCRFA).
Discovery Metals has previously announced to the market various changes to the repayment schedule for the PF Facility (Repayment Schedule) in the form of formal waivers from its lenders.
On 17 February 2014, Discovery Metals advised the market that its lenders had granted a waiver such that the scheduled repayment date for the principal repayment of $17.5 million was deferred until 31
March 2014. Further, on 28 February 2014, Discovery Metals advised the market that all interest owing up until 28 February 2014 on the PF Facility and SCRFA had been deferred until 15 March 2014.
Discovery Metals today advises the market that the Company's lenders have agreed to a further waiver to the Repayment Schedule such that the scheduled principal repayment amount of $37.5m due on 31
March 2014 and all interest owing up until 15 March 2014 on the PF Facility and the SCRFA has been deferred until 30 April 2014.
The Company thanks the lenders for their support while discussions between Discovery Metals and various external parties to a large-scale recapitalisation of the Company continue.
Table 1 - Revised Principal Repayment Schedule for the PF Facility and the SCRFA
Principal Due
|
PF Facility
US$
|
SCRFA US$
|
Total Debt
US$
|
30-Apr-14
|
|
37,500,000
|
25,000,000
|
62,500,000
|
30-Jun-14
|
|
20,000,000
|
-
|
20,000,000
|
31-Sep-14
|
|
16,000,000
|
-
|
16,000,000
|
31-Dec-14
|
|
18,000,000
|
-
|
18,000,000
|
31-Mar-15
|
|
37,360,000
|
-
|
37,360,000
|
|
Total
|
128,860,000
|
25,000,000
|
153,860,000
|
FORWARD LOOKING STATEMENTS
17 March 2014
This release includes certain statements that may be deemed "forward-looking statements". All statements in this discussion, other than statements of historical facts, that address future activities and events or developments that Discovery Metals expects, are forward-looking statements. Although Discovery Metals believes the expectations expressed in such forward- looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, continued availability of capital and financing, and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and that actual results or developments may differ materially from those projected in forward-looking statements.
DISCOVERY METALS BACKGROUND
Discovery Metals is an ASX/BSE listed copper exploration and production company focused on the emerging Kalahari
Copperbelt in north-west Botswana. The Company is a copper producer at its 100% owned Boseto Copper Project.
The Kalahari Copperbelt sediment-hosted mineralisation of the Boseto Copper Project is similar in style to the well-known and large deposits of the Central African Copperbelt of Zambia and the Democratic Republic of the Congo.
Discovery Metals has prospecting licences covering approximately 26,150 km2 in Botswana.
Further information on the Company including Mineral Resources and Ore Reserves is available on our website:
www.discoverymetals.com
For further information on this release and Discovery Metals Limited, please contact:
Bob Fulker - CEO
Phone: +61 7 3218 0222 / Email: [email protected]
Paul Frederiks - CFO and Company Secretary
Phone: +61 7 3218 0222 / Email: [email protected]