Lluvia de Oro Mine Update
TSX Venture Exchange - Symbol: COL - Shares Outstanding: 94,970,527
Crushing - Crushing operations continued normally on the heap. Newly crushed material deposited since on-heap placement began on April 24 has now passed a quarter-million tonnes, estimated to contain approximately 3,000 ounces of gold. The supplier's representative visited the property on Sept. 25th to review crushing operations and discuss spare parts procurement, also future plans for multi-stage crushing when Pit operations are re-started.
Click here or on the picture above to be linked to the website version with larger photos.
Leaching - Approximately 330,000 tonnes have now been placed under leach containing an estimated 3,700 ounces of gold and covering an area of 18,000 sq.m. Calcium carbonate scaling in the leach pipes and emitters is being combatted with the addition of descalant.
ADR Plant - Pregnant solution is being passed through the carbon columns at about 650 USGPM, near design capacity. Adsorption, stripping and electrolysis are proceeding normally. A similar volume of barren solution is being returned to the heap. The water in the Open Pit is being pumped to the solution ponds as necessary for make-up.
Dor� Production - On Sept. 30th, three dor� buttons having a total weight of 26.92 kg were poured and shipped by armored truck to Nogales, Sonora to await transshipment to Brinks facility in Nogales, Arizona on October 1st. Bullion grade is estimated provisionally as 50% gold, 40% silver, but will be determined more precisely later in the week.
SART Plant - Several members of the construction crew have now left the property as the construction phase approaches completion.
Open Pit - Company geological staff continue to examine and sample the different benches in the Open Pit, preparatory to a planned resumption of operations there. A local contractor is working on renovating the Explosives Magazines, work necessary to obtain an Explosives Permit.
Road Work - A program of road widening is underway along the main Access Road which is too narrow for safe traffic in places. Several days' grader work have made some four km of secondary ranch roads accessible immediately West of the Lluvia de Oro area. This will provide partial access into the La Jojoba mining area.
Espa�ol
Trituraci�n - Las operaciones de trituraci�n en los patios procedieron normalmente. El material nuevamente triturado depositado en los patios de lixiviaci�n desde que se comenz� la colocaci�n el 24 de abril, ya ha rebasado un cuarto de mill�n de toneladas, las cuales se estima contienen 3,000 onzas de oro. El representante del proveedor visit� el Proyecto el 25 de septiembre para revisar las operaciones de trituraci�n y tratar sobre la adquisici�n de refacciones, como tambi�n los planes futuros para trituraci�n multi-etapa cuando se arranca las operaciones del Tajo.
Lixiviaci�n - Se ha colocado en situaci�n de lixiviaci�n alrededor de 330,000 tonnes con un contenido de aproximadamente 3,700 onzas de oro y que cubren una �rea de 18,000 metros cuadrados. Se est� combatiendo la incrustaci�n de carbonato de calcio en los tubos y los emisores de lixiviaci�n mediante adiciones de anti-incrustante.
Planta ADR - La soluci�n pre�ada pasa actualmente por las columnas de carb�n a un ritmo de flujo de aproximadamente 650 galones americanos por minuto (USGPM), cerca a su capacidad de dise�o. La adsorci�n, despojo y electr�lisis est�n desempe��ndose de manera normal. Un volumen semejante de soluci�n pobre est� siendo retornado a los patios. El agua que se ha acumulada en el Tajo Abierto est� siendo bombeada para fines de compensaci�n seg�n la necesida.
Producci�n de Dor� - La soluci�n pre�ada pasa actualmente por las columnas de carb�n a un ritmo de flujo de aproximadamente 650 galones americanos por minuto (USGPM), cerca a su capacidad de dise�o. La adsorci�n, despojo y electr�lisis est�n desempe��ndose de manera normal. Un volumen semejante de soluci�n pobre est� siendo retornado a los patios. El agua que se ha acumulada en el Tajo Abierto est� siendo bombeada para fines de compensaci�n seg�n la necesida.
Planta SART - Varios miembros del equipo de construcci�n ya salieron del lugar ya que la fase de construcci�n acerca su final.
Tajo Abierto - Personal geol�gico de la Compa��a continuaron la examinaci�n y muestreo de los distintos bancos del Tajo Abierto, previo al arranque de operaciones en ese lugar. Un contratista local se dedica a la renovaci�n de los Polvorines, trabajo necesario para poder conseguir un permiso para usar explosivos.
Trabajo en los Caminos - Se ha emprendido un programa de ensanchamiento de caminos a lo largo del Camino Principal de Acceso que en algunos lugares ha quedado demasiado angosto para soportar el tr�fico de manera segura. Unos cuantos d�as de trabajo con el motoconformadora ha hecho accesible cuatro kil�metros de caminos rancheros secundarios en el �rea inmediatamente al Oeste del �rea de Lluvia de Oro. Dicho camino permitir� un acceso parcial al �rea minera de La Jojoba.
Prepared by Vernon Smith, P.Eng., General Manager, Minera Columbia de Mexico, S.A. de C.V.
Please e-mail NWM Mining or telephone us at 416-364-6799 for more information.
The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
This News Release is not intended for distribution in the United States. |