TORONTO, ONTARIO--(Marketwired - Oct. 8, 2015) - Richmont Mines Inc. (TSX:RIC)(NYSE MKT:RIC) ('Richmont' or the 'Corporation'), delivered another strong quarter with a year-to-date production of 75,651 ounces that is in-line with planned levels and positions the Corporation to achieve the higher-end of the increased annual production guidance of between 87,000 and 95,000 ounces that was announced on August 6. (All amounts are in Canadian dollars unless otherwise indicated.)
Highlights for the third quarter include:
-- During the third quarter the Corporation produced 23,478 ounces of gold
(22,962 ounces sold) and reported total revenues of $34.1 million.
-- Production for the third quarter was underpinned by another strong
quarter from the Island Gold Mine, which reported production of 15,076
ounces of gold (14,233 ounces sold), in-line with planned levels and on
track to meet the higher-end of annual production guidance.
-- For the nine-month period, production was 75,651 ounces (75,319 ounces
sold), with total revenues of $111.9 million.
-- The Corporation ended the quarter with a strong cash balance of
approximately $76.5 million to maintain a solid balance sheet that will
support the Corporation's growth profile going forward.
-- A 23,000 metre directional drilling program was announced at the highly
prospective Island Gold property to test the down plunge extension of
the deposit where the Corporation previously reported an intercept of
19.87 g/t over 3.93 metres at a depth of 1,200 metres.
-- Effective September 18, 2015 the Corporation was added to the S&P/TSX
SmallCap Index.
Operational Highlights
----------------------------------------------------------------------------
Nine months
ended 2015
Q4 14 Q1 15 Q2 15 Q3 15 Sept. 30/15 Guidance
----------------------------------------------------------------------------
Gold Produced (oz)
Island Gold Mine 8,974 10,764 14,997 15,076 40,837 45,000-50,000
Beaufor Mine 6,633 7,963 7,082 5,714 20,759 42,000-45,000(1)
Monique Mine 7,324 7,132 4,235 2,688 14,055
----------------------------------------------------------------------------
Total Produced(oz) 22,931 25,859 26,314 23,478 75,651 87,000-95,000
----------------------------------------------------------------------------
(1) Production guidance for combined Quebec operations: Beaufor and Monique
Mines.
----------------------------------------------------------------------------
Nine-months
ended
Q4 14 Q1 15 Q2 15 Q3 15 Sept. 30/15
----------------------------------------------------------------------------
Island Gold Mine
----------------------------------------------------------------------------
Underground tpd 399 552 759 669 660
Mill tonnes 46,651 43,785 71,584 66,416 181,785
Mill tpd 507 487 787 722 666
Head grade (g/t) 6.28 7.87 6.73 7.27 7.20
Recoveries (%) 95.3 97.2 96.8 97.1 97.0
----------------------------------------------------------------------------
Beaufor Mine
----------------------------------------------------------------------------
Underground tpd 327 367 360 338 355
Mill tonnes 30,247 29,751 36,914 30,437 97,102
Head grade (g/t) 6.96 8.44 6.05 5.93 6.74
Recoveries (%) 98.1 98.6 98.6 98.6 98.6
----------------------------------------------------------------------------
Monique Mine
----------------------------------------------------------------------------
Mill tonnes 85,447 63,938 61,826 52,987 178,751
Head grade (g/t) 2.80 3.57 2.22 1.64 2.53
Recoveries (%) 95.3 97.2 96.2 96.2 96.7
----------------------------------------------------------------------------
'We are pleased to deliver another solid quarter of production, particularly from our cornerstone Island Gold operation. Our focus in 2015 has been to leverage the significant growth potential we see at Island Gold. This includes the completion of a milling and mining study, which is expected to be released in the latter part of October and was designed to evaluate additional opportunities to increase operating capacity throughout the operation. Also during the quarter, we have advanced our strategic drilling program that targets both increasing our mineral reserves and resources as well as identifying new mineralization both laterally and at depth.' commented Renaud Adams, President and CEO. 'We begin the fourth quarter well positioned with a quality asset base in Canada, and additional
exploration potential yet to be realized, all of which is underpinned by a solid balance sheet that will support our strategic growth plans.'
Island Gold Highlights
-- Production for the quarter was 15,076 ounces, in-line with the prior
quarter. For the nine month period the Island Gold Mine produced 40,837
ounces, well in-line to meet the higher-end of annual guidance
production levels.
-- Underground productivity for the quarter averaged 669 tonnes per day at
higher than planned head grades of 7.27 g/t as mining activities
continued in the higher-grade Goudreau Zone.
-- The mill averaged 722 tpd during the quarter, with recoveries of 97.1%.
Mill productivity was slightly lower than the prior quarter as mining
activities were transitioning to new resources below the 500 metre
level. Long-hole mining from this first mining horizon (above the 635
metre level) will begin in the fourth quarter. The Corporation continues
to test the mill at higher throughput levels of 900 tonnes per day and
in September achieved 24 days with productivity exceeding 900 tonnes per
day, including one day where throughput reached 1,000 tonnes.
-- A planned 3 week shutdown of the underground mine and a corresponding 2
week mill shutdown in October will accommodate a power upgrade, which
will impact production in the fourth quarter. This scheduled upgrade of
existing infrastructure will support ongoing development plans,
productivity enhancement and drilling requirements and has been
incorporated into the 2015 production guidance. At the completion of the
shutdown and related upgrade, the capacity of the mill facility will be
increased to 900 tonnes per day.
-- Development of the main access ramp progressed during the quarter to
reach 725 vertical metres, with a target of 750 vertical metres by the
end of the year.
-- A 23,000 metre deep directional drilling program was announced during
the quarter, which was designed to further expand resources at depth,
below the current one million ounce global gold resource.
-- A milling and mining study that is evaluating several optimized mining
scenarios is nearing completion and a preliminary version is expected to
be released in latter part of October.
Beaufor Highlights
-- Production for the quarter was 5,714 ounces (5,919 ounces sold) and
20,759 ounces (21,638 ounces sold) for the nine-month period.
-- Underground productivity at the Beaufor Mine averaged 338 tonnes per day
at a head grade of 5.93 g/t for the quarter, in-line with planned
levels.
-- Development of the Q Zone advanced during the quarter with a target of
reaching the mineralized structure by the end of 2015 or early 2016.
Monique Highlights
-- Production for the quarter was 2,688 ounces (2,810 ounces sold)
decreased over the prior quarter as the operation began processing the
lower-grade stockpile ore during the quarter.
-- The processing of the lower grade stockpile will be completed by the
latter part of the fourth quarter as planned.
Upcoming News Flow
-- Release of Island Gold milling and mining preliminary study (latter part
of October).
-- Q3 Financial Results (Nov. 5 pre-market).
-- Exploration results (mid-December).
About Richmont Mines Inc.
Richmont Mines has produced over 1.5 million ounces of gold from its operations in Quebec, Ontario and Newfoundland since beginning production. The Corporation currently produces gold from the Island Gold Mine in Ontario, and the Beaufor Mine in Quebec. The Corporation is also advancing development of the significant high-grade resource extension at depth of the Island Gold Mine in Ontario. With 25 years of experience in gold production,
exploration and development, and prudent financial management, the Corporation is well-positioned to cost-effectively build its Canadian reserve base and to successfully enter its next phase of growth. Richmont routinely posts news and other important information on its website (www.richmont-mines.com).
Forward-Looking Statements
This news release contains forward-looking statements that include risks and uncertainties. When used in this news release, the words 'estimate', 'project', 'anticipate', 'expect', 'intend', 'believe', 'hope', 'may' and similar expressions, as well as 'will', 'shall' and other indications of future tense, are intended to identify forward-looking statements. The forward-looking statements are based on current expectations and apply only as of the date on which they were made. Except as may be required by law, the Corporation undertakes no obligation and disclaims any responsibility to publicly update or revise any forward-looking statements or information, whether as a result of new information, future events or otherwise.
The factors that could cause actual results to differ materially from those indicated in such forward-looking statements include changes in the prevailing price of gold, the Canadian-United States exchange rate, grade of ore mined and unforeseen difficulties in mining operations that could affect revenue and production costs. Other factors such as uncertainties regarding government regulations could also affect the results. Other risks may be set out in Richmont Mines' Annual Information Form, Annual Reports and periodic reports. The forward-looking information contained herein is made as of the date of this news release.
Cautionary note to US investors concerning resource estimates
Information in this press release is intended to comply with the requirements of the Toronto Stock Exchange and applicable Canadian securities legislation, which differ in certain respects with the rules and regulations promulgated under the United States Securities Exchange Act of 1934, as amended ('Exchange Act'), as promulgated by the SEC. The Reserve and Resource estimates in this press release were prepared in accordance with Regulation 43-101 adopted by the Canadian Securities Administrators. The requirements of Regulation 43-101 differ significantly from the requirements of the United States Securities and Exchange Commission (the 'SEC').
U.S. Investors are urged to consider the disclosure in our annual report on Form 20-F, File No. 001-14598, as filed with the SEC under the Exchange Act, which may be obtained from us (without cost) or from the SEC's web site: http://sec.gov/edgar.shtml.
Regulation 43-101
The geological data in this news release has been reviewed by Mr. Daniel Adam, Geo., Ph.D., Vice-President, Exploration, an employee of Richmont Mines Inc., and a qualified person as defined by Regulation 43-101.
Web Site: www.richmont-mines.com
Visit our Facebook page
FOR FURTHER INFORMATION PLEASE CONTACT:
Richmont Mines Inc.Renaud Adams
President and CEO
416 368-0291 ext. 101
Richmont Mines Inc.Anne Day
Vice-President, Investor Relations
416 368-0291 ext. 105
www.richmont-mines.com
Source: Richmont Mines Inc.
News Provided by Acquire Media