Fermer X Les cookies sont necessaires au bon fonctionnement de 24hGold.com. En poursuivant votre navigation sur notre site, vous acceptez leur utilisation.
Pour en savoir plus sur les cookies...
Cours Or & Argent

CuDeco Limited

Publié le 16 mai 2016

Rocklands Commissioning Update

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Cobalt | Copper | Diesel |

Rocklands Commissioning Update

0a53b6ad-9364-4767-8dfb-ac0117d87cad.pdf

ACN. 000 317 251 (ASX:CDU)

MARKET RELEASE 16th May 2016

ROCKLANDS GROUP COPPER PROJECT - 100% OWNED BY CUDECO

COMMISSIONING STATUS UPDATE

CuDeco Limited (CuDeco) provides the following market update on commissioning activities at the Company's flagship Rocklands Group Copper Project in Cloncurry, NW Queensland.

The CuDeco Board will hold its next scheduled meeting at Rocklands this week, taking the opportunity to view first-hand, current progress at Rocklands.

Commissioning activity is currently focused on copper production only, incorporating the jigs (coarse native copper), gravity (fine native copper) and flotation (sulphide copper) circuits, with ore feed planned at the latest Monday 30th May. Whilst this is four weeks after our target date, it will result in being behind in only two weeks of planned production due to changes in ramp-up rates. First shipment of product is still expected prior to the end of June, with first receipts thereafter according to the terms of the offtake agreement.

Once the copper circuits reach steady-state, the pyrite/cobalt and DMS magnetite circuits will be commissioned and these streams also brought online. Copper Installation construction verification (C0) is effectively complete, dry commissioning (C1) is nearing completion and the status of wet commissioning (C2) is detailed in table1 below.

Table 1: Status Report (C2) Monday 16th May 2016:

COMMISSIONING AREA

PCM DESCRIPTION

% Complete

C2 Certificate Status

Ore Ready

FINE ORE STOCKPILE AND RECLAIM

Stockpile

90%

No water commissioning required. Some additional civils work almost complete.

Reclaim

95%

A few instruments to be adjusted otherwise ready to run ore.

CRUSHING CIRCUIT

95%

Cone crusher installation complete, screen and sizing optimisation awaiting first ore feed

GRINDING CIRCUIT

HPGR Feed System

40%

Weightometer to be calibrated, but will not prevent ore feed.

HPGR

15%

Dust collection system complete. I/O checks started. PLC software received from Polysius, awaiting vendor engineer arrival.

Scrubber (Deagglomerator)

67%

Scrubber is running and about to undergo water commissioning.

Grinding

36%

Cyclone Feed Pumps are ready to run on water. Ball Mill I/O checks are well under way and live commissioning to commence early this week.

GRAVITY

Classifying

79%

Trippers are almost complete but the rest of the system is ready to take ore.

Fine Jigging

95%

A few instruments to adjust and wedges to be installed on screens, otherwise ready for ore

Intermediate Jigging

95%

A few instruments to adjust and wedges to be installed on screens, otherwise ready for ore

Coarse Jigging

95%

A few instruments to adjust and wedges to be installed on screens, otherwise ready for ore

Primary Spirals

80%

Some instrumentation commissioning outstanding on cyclone packs otherwise ready for ore

Secondary Spirals

95%

Minor adjustment otherwise ready for ore

Unit 33, Brickworks Annex,19 Brolga Avenue, SOUTHPORT 4215

Phone: +617 5503 1955 Facsimile: +617 5503 0288 Email: adm in@ cud e co.com .au

COMMISSIONING AREA

PCM DESCRIPTION

% Complete

C2 Certificate Status

Ore Ready

Primary Tables

85%

Minor adjustment otherwise ready for ore

Secondary Tables

90%

Minor adjustment otherwise ready for ore

Gravity Thickener

94%

Minor adjustment otherwise ready for ore

FLOTATION

Copper Flotation Regrinding

95%

A few instruments to fix then ready for ore

Copper and Pyrite Flotation

95%

1 drive & paperwork outstanding

Magnetic Separation

95%

all drives for Cu complete - paperwork outstanding

TAILINGS

Tailings Thickener

88%

A few instruments to fix. Thickener recirculation line to be re-routed prior to ore

CONCENTRATE DEWATERING & STORAGE

Belt Filters - Fine Native Copper

38%

Filter cloths to be installed and belt to be tracked

Coarse Native Copper

50%

Currently replacing conveyor 16 belt section; once complete it is ready to receive ore

Copper Concentrate Thickener

86%

A few instruments to fix. Thickener recirculation line to be re-routed prior to ore

Copper Concentrate Dewatering & Storage

67%

Filter press vendor is on site and currently undergoing water commissioning on the filter press system; once complete, ready for ore.

REAGENTS

Activator (NaHS)

95%

Ready to mix reagents

Frother (MIBC)

10%

Awaiting pumping system to be installed. An alternate system in place for ore commissioning

Promoter (A3894)

95%

Ready to mix reagents

Spare Reagent

95%

Ready to mix reagents

Hydrated Lime Mixing & Distribution

80%

Almost ready to mix reagents

Cu & Pyrite Conc. Flocculant

95%

Minor instrument recalibrations then ready for mixing reagents

Gravity & Tailings Flocculant

67%

Water commissioning in progress

Coagulant

20%

Water commissioning is currently underway

WATER SERVICES

Raw Water

95%

Minor instrument recalibrations then ready for mixing reagents

Gland Water

95%

Minor instrument recalibrations then ready for mixing reagents

Process Water

50%

Process water system is operational. Other pumps are ready for commissioning

Cooling Water

95%

A few instruments to adjust and water softener is not yet cabled, otherwise the system is fully operational.

AIR SERVICES

Instrument Air

95%

Minor adjustment otherwise ready for ore

Plant Air

90%

Minor adjustment otherwise ready for ore

Blower Air

33%

Undergoing commissioning currently

POWER STATION

Diesel Fuel Farm

100%

Fuel farm is operational

Power Station

95%

Supplying power to whole of process. Full load testing to be completed.

For and on behalf of the Board.

- ends -

Page 2

Lire la suite de l'article sur www.publicnow.com

CuDeco Limited

EXPLORATEUR
CODE : CDU.AX
ISIN : AU000000CDU1
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

CuDeco est une société de production minière de cuivre basée en Australie.

CuDeco détient divers projets d'exploration en Australie.

Ses principaux projets en exploration sont LAS MINERALE et ROCKLANDS en Australie.

CuDeco est cotée en Australie. Sa capitalisation boursière aujourd'hui est 90,7 millions AU$ (62,0 millions US$, 55,9 millions €).

La valeur de son action a atteint son plus haut niveau récent le 13 août 2010 à 4,38 AU$, et son plus bas niveau récent le 09 février 2018 à 0,20 AU$.

CuDeco possède 394 280 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Communiqués de Presse de CuDeco Limited
02/08/2016Update on Concentrate Production
29/07/2016Shipment of Native Copper
11/07/2016Update on Commissioning
30/06/2016Update on Commissioning
21/06/2016CuDECO Welcomes Resources Minister
21/06/2016Terms Sheet Sign for Offtake
02/06/2016Letter to Shareholders from Managing Director
01/06/2016Update on Commissioning of Plant
30/05/2016Update on Rights Issue
26/05/2016Terms of Employment for Managing Director
24/05/2016Rights Issue Update and Appendix 3B
20/05/2016Management Changes
16/05/2016Rocklands Commissioning Update
13/05/2016CuDECO Research Report
11/05/2016Rights Issue Update
11/05/2016Market Update
06/05/2016Update Rights Issue and Website
05/05/2016Updated Timetable for Rights Issue
05/05/2016Rights Issue
05/05/2016Prospectus for Rights Issue
05/05/2016High Voltage Energisation of Process Plant Commences
30/01/201629/01/2016: Appointment of Non-Executive Chairman
30/01/201620/01/2016: Resignation of Director and Final Interest Notic...
26/12/201521/12/2015: Letter Sent to Option Holders
18/12/201517/12/2015: Update on Rights Issue
15/12/201515/12/2015: Director Appointment
14/12/201514/12/2015: Chairman's Address to AGM
14/12/201514/12/2015: Results of Meeting
14/12/201509/12/2015: Revised Rights Issue Timetable
14/12/201511/12/2015: Maiden Ore Reserve Estimate
30/11/201530/11/2015: Update on Annual General Meeting
30/11/201530/11/2015: Investor Presentation for Rights Issue
25/11/201525/11/2015: Non-Renounceable Revised Rights Issue
25/11/201525/11/2015: Initial Substantial Shareholder Notice
20/11/201520/11/2015: 2015 Annual Report
19/11/201518/11/2015: 2015 Financial Statement
02/11/201502/11/2015: Logistics Update
02/11/201502/11/2015: September Quarterly Activity Report
02/11/201502/11/2015: Update on AGM and Annual Report
29/10/201529/10/2015: Funding Update
01/10/201501/10/2015: Rights Issue Correction
01/10/201501/10/2015: Update on Financial Statement to 30 June
18/09/201518/09/2015: Director Resignation
17/09/201518/09/2015: Native Cu Processing and Company Funding
17/09/201517/09/2015: Rights Issue
14/09/201508/09/2015: Appointment of Alternate Director
14/09/201504/09/2015: Update on Voluntary Suspension
21/08/201520/08/2015: Update on Voluntary Suspension
03/08/201531/07/2015: June Quarterly Activity Report
30/07/201530/07/2015: Rocklands Project Moving Forward
28/07/201528/07/2015: Company Update
28/07/201524/07/2015: Update on Funding
28/07/201524/07/2015: Update on Changes to Board of Directors
23/07/201523/07/2015: Rocklands Copper Metal Casting Plant Commissione...
30/06/201530/06/2015: Results of EGM
29/06/201529/06/2015: Rocklands Pictorial Update
26/06/201526/06/2015: Increase in Copper Grade During Mining
25/06/201525/06/2015: Native Copper Supply Agreement
12/06/201512/06/2015: Focus Sun FIRB Approval
23/03/201523/03/2015: Market Update on Progress at Rocklands
17/03/201502/03/2015: Half Yearly Report & Accounts
02/03/201502/03/2015: Company Update
05/01/201505/01/2015: Hong Kong Dual Listing
22/12/201422/12/2014: Capital Raisings & MOU
04/12/201404/12/2014: Assays for Bulk Ore Processing Trial
03/12/201403/12/2014: Binding MOU with Sinosteel
28/11/201428/11/2014: Native Copper Shipment
23/10/201423/10/2014: Response to AFR Article
17/10/201417/10/2014: Crusher rectification and first ore shipment
18/03/201418/03/2014: Rockland's Copper Project Update
17/03/201415/03/2014: Half Year Accounts
25/02/201425/02/2014: Direct Shipping Ore Crushing Underway
17/02/201417/02/2014: Mining reaches upto 56% Cu in massive sulphides
03/02/201403/02/2014: Multi User Rail Load Facility update
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (CDU.AX)
0,2300.00%
AUSTRALIA
Cours préc. Ouverture
Bas haut
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  - -100,00%
Volume var. 1 mois
-100,00%
Produit
Développe
Recherche Copper
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
20200,00%0,240,24
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
6,92 AU$-0,65%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 +100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
10,92 US$+7,80%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,59 GBX-1,50%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,25 +4,17%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 +0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
14,47 +2,26%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,30 +3,45%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,22 +0,93%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
2,47 +2,49%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
40,66 US$+0,20%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,06 AU$+10,00%Trend Power :
Sun Res.(Oil)SUR.AX
Released ASX Announcement: Quarterly Activities Report
0,00 AU$+0,00%Trend Power :
Profitez de la hausse des actions aurifères
  • Inscrivez-vous à notre market briefing minier
    hebdomadaire
  • Recevez nos rapports sur les sociétés qui nous semblent
    présenter les meilleurs potentiels
  • Abonnement GRATUIT, aucune sollicitation
  • Offre limitée, inscrivez-vous maintenant !
Accédez directement au site.