MARKET RELEASE 16th May 2016
ROCKLANDS GROUP COPPER PROJECT - 100% OWNED BY CUDECO
COMMISSIONING STATUS UPDATE
CuDeco Limited (CuDeco) provides the following market update on commissioning activities at the Company's flagship Rocklands Group Copper Project in Cloncurry, NW Queensland.
The CuDeco Board will hold its next scheduled meeting at Rocklands this week, taking the opportunity to view first-hand, current progress at Rocklands.
Commissioning activity is currently focused on copper production only, incorporating the jigs (coarse native copper), gravity (fine native copper) and flotation (sulphide copper) circuits, with ore feed planned at the latest Monday 30th May. Whilst this is four weeks after our target date, it will result in being behind in only two weeks of planned production due to changes in ramp-up rates. First shipment of product is still expected prior to the end of June, with first receipts thereafter according to the terms of the offtake agreement.
Once the copper circuits reach steady-state, the pyrite/cobalt and DMS magnetite circuits will be commissioned and these streams also brought online. Copper Installation construction verification (C0) is effectively complete, dry commissioning (C1) is nearing completion and the status of wet commissioning (C2) is detailed in table1 below.
Table 1: Status Report (C2) Monday 16th May 2016:
COMMISSIONING AREA
|
PCM DESCRIPTION
|
% Complete
|
C2 Certificate Status
|
Ore Ready
|
FINE ORE STOCKPILE AND RECLAIM
|
Stockpile
|
90%
|
No water commissioning required. Some additional civils work almost complete.
|
Reclaim
|
95%
|
A few instruments to be adjusted otherwise ready to run ore.
|
CRUSHING CIRCUIT
|
95%
|
Cone crusher installation complete, screen and sizing optimisation awaiting first ore feed
|
GRINDING CIRCUIT
|
HPGR Feed System
|
40%
|
Weightometer to be calibrated, but will not prevent ore feed.
|
HPGR
|
15%
|
Dust collection system complete. I/O checks started. PLC software received from Polysius, awaiting vendor engineer arrival.
|
Scrubber (Deagglomerator)
|
67%
|
Scrubber is running and about to undergo water commissioning.
|
Grinding
|
36%
|
Cyclone Feed Pumps are ready to run on water. Ball Mill I/O checks are well under way and live commissioning to commence early this week.
|
GRAVITY
|
Classifying
|
79%
|
Trippers are almost complete but the rest of the system is ready to take ore.
|
Fine Jigging
|
95%
|
A few instruments to adjust and wedges to be installed on screens, otherwise ready for ore
|
Intermediate Jigging
|
95%
|
A few instruments to adjust and wedges to be installed on screens, otherwise ready for ore
|
Coarse Jigging
|
95%
|
A few instruments to adjust and wedges to be installed on screens, otherwise ready for ore
|
Primary Spirals
|
80%
|
Some instrumentation commissioning outstanding on cyclone packs otherwise ready for ore
|
Secondary Spirals
|
95%
|
Minor adjustment otherwise ready for ore
|
Unit 33, Brickworks Annex,19 Brolga Avenue, SOUTHPORT 4215
Phone: +617 5503 1955 Facsimile: +617 5503 0288 Email: adm in@ cud e co.com .au
COMMISSIONING AREA
|
PCM DESCRIPTION
|
% Complete
|
C2 Certificate Status
|
Ore Ready
|
Primary Tables
|
85%
|
Minor adjustment otherwise ready for ore
|
Secondary Tables
|
90%
|
Minor adjustment otherwise ready for ore
|
Gravity Thickener
|
94%
|
Minor adjustment otherwise ready for ore
|
FLOTATION
|
Copper Flotation Regrinding
|
95%
|
A few instruments to fix then ready for ore
|
Copper and Pyrite Flotation
|
95%
|
1 drive & paperwork outstanding
|
Magnetic Separation
|
95%
|
all drives for Cu complete - paperwork outstanding
|
TAILINGS
|
Tailings Thickener
|
88%
|
A few instruments to fix. Thickener recirculation line to be re-routed prior to ore
|
CONCENTRATE DEWATERING & STORAGE
|
Belt Filters - Fine Native Copper
|
38%
|
Filter cloths to be installed and belt to be tracked
|
Coarse Native Copper
|
50%
|
Currently replacing conveyor 16 belt section; once complete it is ready to receive ore
|
Copper Concentrate Thickener
|
86%
|
A few instruments to fix. Thickener recirculation line to be re-routed prior to ore
|
Copper Concentrate Dewatering & Storage
|
67%
|
Filter press vendor is on site and currently undergoing water commissioning on the filter press system; once complete, ready for ore.
|
REAGENTS
|
Activator (NaHS)
|
95%
|
Ready to mix reagents
|
Frother (MIBC)
|
10%
|
Awaiting pumping system to be installed. An alternate system in place for ore commissioning
|
Promoter (A3894)
|
95%
|
Ready to mix reagents
|
Spare Reagent
|
95%
|
Ready to mix reagents
|
Hydrated Lime Mixing & Distribution
|
80%
|
Almost ready to mix reagents
|
Cu & Pyrite Conc. Flocculant
|
95%
|
Minor instrument recalibrations then ready for mixing reagents
|
Gravity & Tailings Flocculant
|
67%
|
Water commissioning in progress
|
Coagulant
|
20%
|
Water commissioning is currently underway
|
WATER SERVICES
|
Raw Water
|
95%
|
Minor instrument recalibrations then ready for mixing reagents
|
Gland Water
|
95%
|
Minor instrument recalibrations then ready for mixing reagents
|
Process Water
|
50%
|
Process water system is operational. Other pumps are ready for commissioning
|
Cooling Water
|
95%
|
A few instruments to adjust and water softener is not yet cabled, otherwise the system is fully operational.
|
AIR SERVICES
|
Instrument Air
|
95%
|
Minor adjustment otherwise ready for ore
|
Plant Air
|
90%
|
Minor adjustment otherwise ready for ore
|
Blower Air
|
33%
|
Undergoing commissioning currently
|
POWER STATION
|
Diesel Fuel Farm
|
100%
|
Fuel farm is operational
|
Power Station
|
95%
|
Supplying power to whole of process. Full load testing to be completed.
|
For and on behalf of the Board.
- ends -