bf4a3542-0368-4f54-bf82-16f262da4d26.pdf
ACN. 000 317 251 (ASX:CDU)
MARKET RELEASE 6th May 2016
ROCKLANDS GROUP COPPER PROJECT - 100% OWNED BY CUDECO
RIGHTS ISSUE TO CLOSE END OF TODAY
PAYMENT ACCEPTED UNTIL 7:00PM AEST TONIGHT (5:00PM PERTH)
CuDeco is pleased to remind shareholders that the Rights Issue offer period closes tonight.
Direct deposit into CuDeco account with form to Southport office in person, by fax or email (see details bottom of page), will be accepted until 7:00pm Australian Eastern Standard Time today (5:00pm Perth time).
Remaining timetable for Rights Issue:
Closing Date of Offer (5:00pm Perth time) Advise ASX of any Shortfall
Trading Halt lifted - Ordinary shares recommence trading Allotment of New Shares
Commencement of trading of New Shares on ASX
Expected date of despatch of holding statements for New Shares
Final date for placement of any Shortfall (3 months following Closing Date)
|
Friday 6 May 2016
Wednesday 11 May 2016
Wednesday 11 May 2016
Friday 13 May 2016
Monday 16 May 2016
Tuesday 17 May 2016
Monday 8 August 2016
|
Account details for EFT deposits:
BSB: 084 917
Account Name: CuDeco Ltd Account No: 54 471 4589.
National Australia Bank, Scarborough Street, Southpor
|
t Q 4215
|
WEB SITE UPDATED
CuDeco is pleased to direct shareholders to its recently updated web page:
ww w .c udec o.c om.a u
PROCESS PLANT UPDATE
Energisation of the high voltage circuits and testing and commissioning of the low voltage circuits has been completed, and now wet commissioning of the high-voltage circuits is underway.
Unit 33, Brickworks Annex,19 Brolga Avenue, SOUTHPORT 4215
Phone: +617 5503 1955 Facsimile: +617 5503 0288 Email: admi n@ cudeco. com. au
Figure 1: Water from wet commissioning activity is returned to the process ponds - stockpiles of high-grade crushed native copper ore in background will be the first ore to be processed.
Key activities at the Process Plant:
-
Whole of process plant is now fed from permanent power.
-
Verti-mill has been energised and currently charging with grinding media.
-
Electrical Commissioning checks completed on the Scrubber and will be bump tested today.
-
HPGR High Voltage drives will also be run today.
-
Pre-load electrical commissioning tests of the Ball Mill will be completed within the next few days.
-
Energised and commissioned all low-voltage circuit on water.
-
High-voltage commissioning on water in progress.
For and on behalf of the board
- ends -
Figure 2: E-house being prepared for bump- testing of the Verti-mill.