TORONTO
SU.TO
52,46 CA$
23,58%
Total says not ready to accept cost increases in Fort Hills project
Publié le 27 juillet 2017
PARIS, July 27 (Reuters) - French oil and gas company Total said on Thursday that it was not ready to accept substantial cost increases in the Fort Hills oils sands project in Canada, which has led to a commercial dispute with Suncor .
Total's Chief Financial Officer Patrick de la Chevardiere told analysts in a call following the company's second quarter earnings that it was in discussion with Suncor to reduce costs.
Suncor said separately that it was in the early stages of a commercial dispute with Fort Hills project partner Total over project funding. (Reporting by Bate Felix; Editing by Ingrid Melander)
Les autres articles de la compagnie