Deflector_project_update_jan_2016
ASX Announcement
20 January 2016
DEFLECTOR PROJECT PROGRESSING ON SCHEDULE - OPEN PIT MINING CONTRACTOR MOBILISED
The Deflector Gold Project is a high-grade/low-cost gold-copper deposit with an initial mine life of six years and significant exploration potential. Doray is utilising its recent experience from the Andy Well Gold Project to optimise the construction, development and operation of Deflector.
Following construction and commissioning of Deflector in mid-2016, Doray is forecasting combined production from Andy Well and Deflector of 140,000 ounces1 per annum (plus copper and silver) and is targeting an average all-in sustaining cost (AISC) of less than A$1,000/oz (after by-product credits).
Open pit mining contractor mobilised to site
As previously advised, Doray recently provided MACA Ltd (ASX:MLD, "MACA") with a letter of intent to award them the open pit mining contract at Deflector.
MACA have recently mobilised to Deflector and have commenced refurbishment of the existing tailings storage facility at Gullewa, which will be used for the Deflector Project, and have begun preparing for commencement of open pit mining in February.
Processing plant construction on schedule and on budget
Construction activities are continuing at the processing plant and site admin areas.
The fine ore bin is complete and erection of structural steel is well advanced within the crushing, conveyor, mill and flotation areas. Piping and electrical works are in progress to the crushing area and workshop stores.
1The Company will provide production guidance in terms of actual gold ounces produced. Depending on prevailing copper and
silver prices, gold equivalent ounces (Au Eq) are expected to range between 150,000 ‐160,000 ounces as per previous guidance.
Installation of various site buildings is advanced, including the admin office, mill office, crib room, on-site laboratory, workshop, reagent and general stores buildings.
A number of major items of plant including the new ball mill shell have been delivered to site. Remaining items, including the flotation cells and concentrate filter press are expected to be delivered to site during January and February respectively.
The new 134 person village near to the Deflector site was effectively completed during December and is now operational.
Project development is slightly ahead of schedule to start commissioning of the crushing circuit from April 2016 with full commissioning during May 2016.
Costs incurred to the end of December were $44.3M and are lower than budgeted relative to progress on site to date. Remaining costs to be incurred prior to the commencement of production are anticipated to be within budget.
Figure 1. Primary crusher, ROM bin and apron feeder installed.
Figure 2. Crushing tower with secondary and tertiary crushers installed.
Figure 3. Crushing circuit screen installed.
ASX:DRM
Figure 4. Mill plinth with gravity circuit tower and mill control room installed.
Figure 5. New ball mill shell delivered to site.
ASX:DRM