ASX/Media Announcement 26 September 2016
ALLAMBER FOLLOW-UP DRILLING UNDERWAY
Thundelarra is pleased to report that a multi-purpose drill rig with both reverse circulation and diamond drilling capability has mobilised to Allamber in the Northern Territory. Drilling is underway to test follow-up targets at the Ox-Eyed Herring and Tarpon prospects. It is anticipated that a number of holes will be drilled with RC pre-collars and diamond tails.
Figure 1. Allamber Project location and local infrastructure. Copperfield was relinquished.
The main objective of the programme is to follow up mineralisation intersected in previous exploration and reported in announcements dated 03 February and 24 September 2015:
Hole No
|
From
|
To
|
Interval
|
Cu (%)
|
Ag (ppm)
|
TAL136RC
|
112m
|
120m
|
8m
|
2.71
|
TAL140RC
|
182m
|
188m
|
6m
|
1.58
|
20
|
TAL141RC
|
148m
|
149m
|
1m
|
3.96
|
15
|
TAL145RC
|
127m
|
129m
|
2m
|
1.21
|
5
|
Table 2. Significant drill intercepts from previous programmes.
For Further Information Contact: THUNDELARRA LIMITED
Mr Tony Lofthouse - Chief Executive Officer Issued Shares: 423.5M
Thundelarra Limited | ABN: 74 950 465 654 | Level 1, 186 Hampden Rd, Nedlands WA 6009 | PO Box 7363, Cloisters Square, WA, 6850
www.thundelarra.com.au | [email protected] | Tel: +61 8 9389 6927 | Fax: +61 8 9389 5593