ASX ANNOUNCEMENT 19 December 2016

Aurora Tank Gold Drilling Update

Marmota Limited (ASX: MEU) ("Marmota")

Marmota is pleased to advise that 31 RC holes at Aurora Tank have now been completed.

KEY POINTS

  • Phase 2 drilling at Aurora Tank commenced on 30 November 2016 [see ASX:MEU 1 Dec 2016]

  • Drilling has stopped for the on-set of the holiday period.

    Program

  • 31 of 53 angled RC (reverse circulation) drill holes have now been completed

  • Target depths: 90 m (approximate)

  • Total drilling to date: 2,604m (approximately 150m per day)

  • Phase 2 program is shown in Figure 1. Completed holes to date is shown in Figure 2.

    New assays coming

  • Assay results from drilling samples are anticipated at around the end of January.

    Figure 1: Phase 2 RC drill grid (with previous drilling locations / results)

    Page 3 Figure 2: Phase 2 RC drill holes now completed

    Background

    • Aurora Tank (EL 5589) is situated about 50km NE of the Challenger Gold Mine [ see Fig. 3 ]

    • Aurora Tank is 100% owned by Marmota [see ASX:MEU 4 July 2016]

    • Gold was identified at the Goshawk prospect by drilling historical calcrete sampling anomalies.

      Phase 1

    • In September 2016, Marmota conducted an aircore drilling program to test the Goshawk Gold

      Prospect at Aurora Tank with the intention of fully defining gold geochemical dispersion in the near-surface zone to 40 metres vertical depth [see ASX:MEU 5 Sept 2016]

    • During Phase 1: 98 angled aircore holes totaling 4,385m were drilled

      Phase 1 Results

      Phase 1 (September drilling) has already yielded excellent results [ see ASX:MEU 25 Oct 2016 and 29 Nov 2016 ] with 31 intersections greater than 1 g/t gold, all close to surface, including:

      11.3 g/t

      gold

      from 22m

      - Hole 16AT019

      ( incl

      1m @ 23 g/t

      gold from 22m)

      9.0 g/t

      gold

      from 25m

      - Hole 16AT043

      ( incl

      1m @ 34 g/t

      gold from 27m)

      3.7 g/t

      gold

      from 24m

      - Hole 16AT044

      ( and

      1m @ 11 g/t

      gold from 20m)

      6.2 g/t

      gold

      from 35m

      - Hole 16AT061

      ( incl

      1m @ 23 g/t

      gold from 35m)

      3.9 g/t

      gold

      from 20m

      - Hole 16AT062

      3.3 g/t

      gold

      from 36m

      - Hole 16AT028

      • 3m at

      • 4m at

      • 4m at

      • 4m at

      • 4m at

      • 4m at

      • Significant gold mineralization intersected over 750m strike length

      • Mineralization consistently close to surface

    • Phase 2 RC drilling program commenced on 30 Nov 2016.

Page 4

Les autres articles de la compagnie
Marmota Energy Limited (ASX:MEU) New High Grade Copper Inter
Dans la même rubrique
Shuttered Gold Mine Shows Investors Risks of Thai Power Grab
18/12/16 21:00
CANADA STOCKS-TSX rises as energy, gold miners gain
16/12/16 22:10
Should You Avoid Intermediate Gold Miners with High Leverage
16/12/16 20:05
Should You Avoid Intermediate Gold Miners with High Leverage
16/12/16 20:05
Senior Gold Miners That Could Outperform after the Rate Hike
16/12/16 20:05
Senior Gold Miners That Could Outperform after the Rate Hike
16/12/16 20:05
Articles en illimité et contenus premium Je m'abonne
Editoriaux
et Nouvelles
Actions
Minières
Or et
Argent
Marchés La Cote
search 6479
search