Aurora Tank Gold - Drilling Update

Publié le 19 décembre 2016

ASX ANNOUNCEMENT 19 December 2016

Aurora Tank Gold Drilling Update

Marmota Limited (ASX: MEU) ("Marmota")

Marmota is pleased to advise that 31 RC holes at Aurora Tank have now been completed.

KEY POINTS

  • Phase 2 drilling at Aurora Tank commenced on 30 November 2016 [see ASX:MEU 1 Dec 2016]

  • Drilling has stopped for the on-set of the holiday period.

    Program

  • 31 of 53 angled RC (reverse circulation) drill holes have now been completed

  • Target depths: 90 m (approximate)

  • Total drilling to date: 2,604m (approximately 150m per day)

  • Phase 2 program is shown in Figure 1. Completed holes to date is shown in Figure 2.

    New assays coming

  • Assay results from drilling samples are anticipated at around the end of January.

    Figure 1: Phase 2 RC drill grid (with previous drilling locations / results)

    Page 3 Figure 2: Phase 2 RC drill holes now completed

    Background

    • Aurora Tank (EL 5589) is situated about 50km NE of the Challenger Gold Mine [ see Fig. 3 ]

    • Aurora Tank is 100% owned by Marmota [see ASX:MEU 4 July 2016]

    • Gold was identified at the Goshawk prospect by drilling historical calcrete sampling anomalies.

      Phase 1

    • In September 2016, Marmota conducted an aircore drilling program to test the Goshawk Gold

      Prospect at Aurora Tank with the intention of fully defining gold geochemical dispersion in the near-surface zone to 40 metres vertical depth [see ASX:MEU 5 Sept 2016]

    • During Phase 1: 98 angled aircore holes totaling 4,385m were drilled

      Phase 1 Results

      Phase 1 (September drilling) has already yielded excellent results [ see ASX:MEU 25 Oct 2016 and 29 Nov 2016 ] with 31 intersections greater than 1 g/t gold, all close to surface, including:

      11.3 g/t

      gold

      from 22m

      - Hole 16AT019

      ( incl

      1m @ 23 g/t

      gold from 22m)

      9.0 g/t

      gold

      from 25m

      - Hole 16AT043

      ( incl

      1m @ 34 g/t

      gold from 27m)

      3.7 g/t

      gold

      from 24m

      - Hole 16AT044

      ( and

      1m @ 11 g/t

      gold from 20m)

      6.2 g/t

      gold

      from 35m

      - Hole 16AT061

      ( incl

      1m @ 23 g/t

      gold from 35m)

      3.9 g/t

      gold

      from 20m

      - Hole 16AT062

      3.3 g/t

      gold

      from 36m

      - Hole 16AT028

      • 3m at

      • 4m at

      • 4m at

      • 4m at

      • 4m at

      • 4m at

      • Significant gold mineralization intersected over 750m strike length

      • Mineralization consistently close to surface

    • Phase 2 RC drilling program commenced on 30 Nov 2016.

Page 4

Les autres articles de la compagnie
Marmota Energy Limited (ASX:MEU) New High Grade Copper Inter
Dans la même rubrique
Shuttered Gold Mine Shows Investors Risks of Thai Power Grab
18/12/16 21:00
CANADA STOCKS-TSX rises as energy, gold miners gain
16/12/16 22:10
Should You Avoid Intermediate Gold Miners with High Leverage
16/12/16 20:05
Should You Avoid Intermediate Gold Miners with High Leverage
16/12/16 20:05
Senior Gold Miners That Could Outperform after the Rate Hike
16/12/16 20:05
Senior Gold Miners That Could Outperform after the Rate Hike
16/12/16 20:05
Articles en illimité et contenus premium Je m'abonne
Editoriaux
et Nouvelles
Actions
Minières
Or et
Argent
Marchés La Cote
search 9781
search
Vous avez atteint le quota de 3 articles pour une période de 30 jours. Si vous souhaitez en découvrir d'avantage, devenez Membre Gratuit en cliquant sur le bouton "Créer un compte".
Créer un compte
Si vous avez déjà un compte,
veuillez vous identifier
×