Crowflight Mineral Inc.

Published : October 01st, 2008

Announces Mill Commissioning Underway at Bucko; Intersects 8.10 Metres of 9.01% Nickel

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Canada | Copper | Diamond | Nickel | Storage |
=======================================================================
Re:   News Release - Wednesday, October 01, 2008
      Crowflight Announces Mill Commissioning Underway at Bucko;
      Intersects 8.10 Metres of 9.01% Nickel
=======================================================================

CROWFLIGHT MINERALS INC. (Crowflight, the Company) (TSX Venture
Exchange: CML) is pleased to provide a project update and underground
Diamond drilling results from its wholly-owned Bucko Lake Nickel Mine
(Bucko) located in the Thompson Nickel Belt near Wabowden, Manitoba.

Bucko Project Update

Construction is close to complete at Crowflight's Bucko Lake Mine.
Expectations are to ramp up production during the remainder of 2008 to
declare full commercial production in early 2009. Construction status
is as follows:

..  Mill commissioning has been underway since early September.

..  Ore is currently being mined and stockpiled in preparation for mill
start-up.

..  The crushing plant commissioning is essentially complete and
crushing of ore has commenced.

..  Significant progress has been made on piping in the mill. Remaining
piping should be complete in the next few weeks.

..  The main electrical cables have been pulled in the mill and there
are still some automation control cables to pull. Cable terminations
and energizing of equipment should be complete in the next few weeks.

..  The interim tailings storage facility (ITSF) should be complete by
mid-October.

..  To update on the status of the federal permitting process for the
storage of tailings in Bucko Lake, the screening level assessment
report (the federal government's technical review of the project) was
supposed to be released on September 8, 2008 for public comment but due
to the federal election, this has now been deferred to October 15,
immediately after the federal election. Federal authorities have
indicated to Crowflight that upon completion of the public review,
inclusion of comments from the review, and assuming that no revisions
are required, then the letter of recommendation from federal
authorities to the Governor in Council (Cabinet) recommending that
Cabinet amend Schedule 2 of the Metal Mining Effluent Regulations to
add Bucko Lake as a Tailings Impoundment Area will be sent by early
January 2008. The Schedule 2 amendment process will take eight to 12
months after the letter of recommendation has been received.  The ITSF
will be used until federal approval for the use of Bucko Lake is
received.

..  The dry and wet commissioning of the mill will continue through
October. Assuming commissioning goes as planned, Crowflight anticipates
feeding ore through the plant and producing concentrate in the third or
fourth week of October.
 
Bucko Delineation Drilling Update

Underground delineation drilling at Bucko between sections 517N and
521N has returned encouraging assay results. Hole BUD-39 intersected
8.10 metres grading 9.01% nickel including 4.11 meters of 14.07%
nickel, approximately 30 metres above the main 1,000 foot level. This
mineralization occurs approximately 25 metres south of hole BUD-44
which intersected a 30.17 metre wide interval grading 1.36% nickel
including 6.4 metres grading 2.35% nickel. Both holes, which are
associated with the second planned mining area on the 1,000 foot level
that is expected to be reached in late November, confirm higher grade
nickel mineralization than currently modelled. A number of the drill
holes hit multiple zones of mineralization.

Highlight assays from the most recent delineation program results
include:

..  Hole BUD-12 intersected 18.06 metres grading 1.43% nickel

..  Hole BUD-14 intersected 8.23 metres grading 3.08% nickel

..  Hole BUD-18 intersected 5.21 metres grading 2.12% nickel

..  Hole BUD-19 intersected 13.92 metres grading 2.65% nickel

..  Hole BUD-21 intersected 15.37metres grading 3.01% nickel

..  Hole BUD-29 intersected 11.12 metres grading 1.56% nickel

..  Hole BUD-30 intersected 9.44 metres grading 1.64% nickel

..  Hole BUD-31 intersected 9.77 metres grading 1.76% nickel

..  Hole BUD-34 intersected 9.88 metres grading 2.19% nickel

..  Hole BUD-39 intersected 8.10 metres grading 9.01% nickel

..  Hole BUD-44 intersected 6.40 metres grading 2.35% nickel and 4.37
metres grading 3.54% nickel

..  Hole BUD-50 intersected 4.79 metres grading 3.02% nickel and 3.35%
metres grading 4.09% nickel

..  Hole BUD-64 intersected 9.69 metres grading 2.15% nickel

..  Hole BUD-66 intersected 8.90 metres grading 1.50% nickel

Mike Hoffman, President and CEO of Crowflight, commented "The
Crowflight operating team and the various contractors on site have been
working very hard to complete construction at the Bucko Mine. This will
be a first class facility once complete and we are looking forward to
producing concentrate shortly. The underground drill results at Bucko
are very encouraging as they are confirming, or in some cases
exceeding, our expectations."

Table 1 provides a complete summary of highlight assay intervals from
the 61 assayed holes received to date. Figure 1 depicts a plan view of
the 1,000 foot mining level illustrating the location of current and
planned mining and the location of highlighted drill results.

One underground Diamond drill operated by Boart Longyear is stationed
on the 1,000 foot level. To date, 71 holes totalling 12,017 metres of
drilling have been completed.


Table 1. Assay Results from 1,000 Foot Level Delineation Program
-----------------------------------------------------------------
-----------------------------------------------------------------
                                    Core        Core
-----------------------------------------------------------------
Drill
 Hole         From        To      Length       Length        Ni%
-----------------------------------------------------------------
                (m)       (m)         (m)       (feet)         %
-----------------------------------------------------------------
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-1     64.42     70.00        5.58        18.31       0.98
-----------------------------------------------------------------
(i)BUD-1     77.43     84.85        7.42        24.34       1.07
-----------------------------------------------------------------
(i)BUD-1     92.81     99.20        6.39        20.96       1.14
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-2     58.82     66.50        7.68        25.20       1.08
-----------------------------------------------------------------
(i)BUD-2     71.41     75.60        4.19        13.75       1.08
-----------------------------------------------------------------
(i)BUD-2     80.30     83.30        3.00         9.84       0.89
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-3     61.68     65.72        4.04        13.25       0.90
-----------------------------------------------------------------
(i)BUD-3     73.95     78.50        4.55        14.93       1.06
-----------------------------------------------------------------
(i)BUD-3     73.95     82.64        8.69        28.51       0.91
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-4     53.31     66.50       13.19        43.27       0.83
-----------------------------------------------------------------
(i)BUD-4     78.50     86.00        7.50        24.61       0.87
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-5     55.69     58.00        2.31         7.58       1.14
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-6     78.00     79.35        1.35         4.43       1.03
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-7     87.20     90.29        3.09        10.14       1.06
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-8    166.88    170.33        3.45        11.32       2.17
-----------------------------------------------------------------
(i)BUD-8    193.00    202.27        9.27        30.41       2.82
-----------------------------------------------------------------
(i)BUD-8    204.50    207.48        2.98         9.78       0.82
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-9    135.71    147.84       12.13        39.80       1.44
-----------------------------------------------------------------
(i)BUD-9    172.82    177.80        4.98        16.34       1.97
-----------------------------------------------------------------
(i)BUD-9    182.80    186.00        3.20        10.50       1.37
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-10   134.80    141.00        6.20        20.34       1.55
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-11   109.49    115.75        6.26        20.54       1.13
-----------------------------------------------------------------
(i)BUD-11   126.50    133.09        6.59        21.62       1.36
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-12       96.89    101.57        4.68        15.35       2.56
-----------------------------------------------------------------
BUD-12       96.89    114.95       18.06        59.25       1.43
-----------------------------------------------------------------
BUD-12      122.54    130.62        8.08        26.51       1.34
-----------------------------------------------------------------
BUD-12      146.73    152.41        5.68        18.64       1.18
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-13       99.84    127.50       27.66        90.75       1.64
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-14       80.27     88.50        8.23        27.00       3.08
-----------------------------------------------------------------
BUD-14      100.36    112.00       11.64        38.19       1.48
-----------------------------------------------------------------
BUD-14      116.50    122.48        5.98        19.62       1.51
-----------------------------------------------------------------
BUD-14      135.90    139.08        3.18        10.43       1.90
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-15       81.57     88.39        6.82        22.38       0.66
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-16       82.31     87.00        4.69        15.39       0.93
-----------------------------------------------------------------
BUD-16      111.18    114.83        3.65        11.98       1.66
-----------------------------------------------------------------
BUD-16      120.00    123.26        3.26        10.70       1.22
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-17       79.61     85.28        5.67        18.60       1.26
-----------------------------------------------------------------
BUD-17       90.50    100.00        9.50        31.17       0.99
-----------------------------------------------------------------
BUD-17      120.52    124.73        4.21        13.81       1.86
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-18       84.50     88.05        3.55        11.65       1.07
-----------------------------------------------------------------
BUD-18       98.50    102.00        3.50        11.48       1.14
-----------------------------------------------------------------
BUD-18      122.56    127.77        5.21        17.09       2.12
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-19       94.54    110.20       15.66        51.38       1.14
-----------------------------------------------------------------
BUD-19      124.56    138.48       13.92        45.67       2.65
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-20      101.27    118.77       17.50        57.41       1.25
-----------------------------------------------------------------
BUD-20      133.29    138.05        4.76        15.62       1.76
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-21      112.61    121.44        8.83        28.97       0.87
-----------------------------------------------------------------
BUD-21      162.22    177.59       15.37        50.43       3.01
-----------------------------------------------------------------
BUD-21      186.66    198.90       12.24        40.16       1.10
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-22      113.74    117.43        3.69        12.11       0.76
-----------------------------------------------------------------
BUD-22      153.11    156.84        3.73        12.24       0.71
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-23      150.00    157.91        7.91        25.95       1.11
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-24       82.05     87.00        4.95        16.24       0.83
-----------------------------------------------------------------
BUD-24      113.00    118.00        5.00        16.40       1.05
-----------------------------------------------------------------
BUD-24      139.00    143.50        4.50        14.76       1.15
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-25      111.71    115.56        3.85        12.63       1.13
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-26       91.00     94.04        3.04         9.97       1.43
-----------------------------------------------------------------
BUD-26       96.07    105.92        9.85        32.32       0.83
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-27       83.86    101.09       17.23        56.53       0.79
-----------------------------------------------------------------
BUD-27      111.20    118.57        7.37        24.18       1.27
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-28      110.00    113.00        3.00         9.84       0.85
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-29       91.06     98.30        7.24        23.75       1.21
-----------------------------------------------------------------
BUD-29      105.45    116.57       11.12        36.48       1.56
-----------------------------------------------------------------
BUD-29      123.92    128.67        4.75        15.58       0.97
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-30       71.76     75.00        3.24        10.63       1.28
-----------------------------------------------------------------
BUD-30       92.34    107.00       14.66        48.10       1.20
-----------------------------------------------------------------
BUD-30      110.19    119.63        9.44        30.97       1.64
-----------------------------------------------------------------
BUD-30      132.87    136.50        3.63        11.91       1.58
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-31       73.95     76.98        3.03         9.94       1.36
-----------------------------------------------------------------
BUD-31       89.24     93.35        4.11        13.48       1.48
-----------------------------------------------------------------
BUD-31      110.85    115.18        4.33        14.21       1.32
-----------------------------------------------------------------
BUD-31      149.81    153.48        3.67        12.04       1.29
-----------------------------------------------------------------
incl.       135.61    145.38        9.77        32.05       1.76
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-32      136.65    140.62        3.97        13.02       2.40
-----------------------------------------------------------------
BUD-32      160.00    164.80        4.80        15.75       1.11
-----------------------------------------------------------------
BUD-32      170.00    178.36        8.36        27.43       1.47
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-33      106.15    110.18        4.03        13.22       0.89
-----------------------------------------------------------------
BUD-33      128.03    131.33        3.30        10.83       1.15
-----------------------------------------------------------------
BUD-33      138.93    146.50        7.57        24.84       1.17
-----------------------------------------------------------------
BUD-33      152.58    157.71        5.13        16.83       1.75
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-34      140.23    150.11        9.88        32.41       2.19
-----------------------------------------------------------------
BUD-34      153.74    158.75        5.01        16.44       1.17
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-35      110.04    117.80        7.76        25.46       1.01
-----------------------------------------------------------------
BUD-35      135.00    146.95       11.95        39.21       1.84
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-36       85.56     88.87        3.31        10.86       1.01
-----------------------------------------------------------------
BUD-36      104.24    108.30        4.06        13.32       0.90
-----------------------------------------------------------------
BUD-36      133.50    137.20        3.70        12.14       1.12
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-37       80.46     84.65        4.19        13.75       0.90
-----------------------------------------------------------------
BUD-37      102.32    108.29        5.97        19.59       1.47
-----------------------------------------------------------------
BUD-37      123.05    129.68        6.63        21.75       0.97
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-39      108.30    116.40        8.10        26.57       9.01
-----------------------------------------------------------------
Incl.       109.56    113.67        4.11        13.48      14.07
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-44      100.47    130.64       30.17        98.98       1.36
-----------------------------------------------------------------
incl.       124.24    130.64        6.40        21.00       2.35
-----------------------------------------------------------------
BUD-44      142.00    145.47        3.47        11.38       0.98
-----------------------------------------------------------------
BUD-44      159.26    163.63        4.37        14.34       3.54
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-46      122.22    125.35        3.13        10.27       2.44
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)BUD-47   101.51    108.11        6.60        21.65       2.08
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-48       89.56     93.00        3.44        11.29       2.16
-----------------------------------------------------------------
BUD-48       96.73    101.43        4.70        15.42       1.24
-----------------------------------------------------------------
BUD-48      123.07    126.10        3.03         9.94       4.88
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-49       82.28     85.32        3.04         9.97       2.22
-----------------------------------------------------------------
BUD-49      102.00    105.33        3.33        10.93       1.47
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-50       73.00     76.35        3.35        10.99       4.09
-----------------------------------------------------------------
BUD-50       79.00     82.50        3.50        11.48       1.09
-----------------------------------------------------------------
BUD-50      100.21    105.00        4.79        15.72       3.02
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-51       67.74     74.06        6.32        20.73       0.97
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-52       64.00     70.32        6.32        20.73       1.35
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-53       63.32     76.14       12.82        42.06       1.43
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-54       67.38     75.00        7.62        25.00       1.11
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-55      141.00    144.69        3.69        12.11       0.73
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-56      131.51    139.13        7.62        25.00       0.98
-----------------------------------------------------------------
BUD-56      155.00    158.44        3.44        11.29       1.25
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-57      115.39    120.63        5.24        17.19       1.20
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-58      127.50    130.90        3.40        11.15       1.01
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-59       97.53    101.38        3.85        12.63       1.87
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-60       81.00     84.04        3.04         9.97       0.73
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-61       73.44     76.74        3.30        10.83       1.14
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-62       69.64     74.83        5.19        17.03       0.73
-----------------------------------------------------------------
BUD-62       99.04    104.00        4.96        16.27       0.76
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-63       67.87     71.52        3.65        11.98       1.97
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-64       63.77     73.46        9.69        31.79       2.15
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-65       66.27     70.74        4.47        14.67       1.06
-----------------------------------------------------------------
-----------------------------------------------------------------
BUD-66       71.51     80.41        8.90        29.20       1.50
-----------------------------------------------------------------
-----------------------------------------------------------------
(i)  Previously announced results-see previous release dated
     June 25, 2008 for further information.
    
     Intersection intervals reported are core lengths; actual true
     widths range between 80% and 100% of core length.

Qualified Person/Quality Control Procedures

This press release has been prepared and reviewed by Mr. Greg Collins,
P.Geo (APGO/APEGM) and VP Exploration of Crowflight and Mr. Paul
Keller, P. Eng. and COO of Crowflight, both of whom are Qualified
Persons under the National Instrument 43-101 guidelines. All assays
were performed at the ALS-Chemex laboratory in Vancouver and undergo an
ICP-AES finish and Sodium Peroxide Fusion. Standards and blanks are
submitted with each sample batch.

Crowflight Minerals - Canada's Next Nickel Producer

Crowflight Minerals Inc. (TSX-V: CML) is a Canadian junior mining
company that is developing the Bucko Lake Nickel Mine near Wabowden,
Manitoba. Full commercial production is expected to be achieved at
Bucko in early 2009. The Company is also focused on nickel, copper and
Platinum Group Mineral (PGM) projects in the Thompson Nickel Belt and
Sudbury Basin.

Cautionary Note on Forward-Looking Information

Except for statements of historical fact contained herein, the
information in this press release constitutes "forward-looking
information" within the meaning of Canadian securities law. Such
forward-looking information may be identified by words such as "plans",
"proposes", "estimates", "intends", "expects", "believes", "may",
"will" and include without limitation, statements regarding estimated
capital and operating costs, expected production timeline, benefits of
updated development plans, foreign exchange assumptions and regulatory
approvals. There can be no assurance that such statements will prove to
be accurate; actual results and future events could differ materially
from such statements. Factors that could cause actual results to differ
materially include, among others, metal prices, competition, risks
inherent in the mining industry, and regulatory risks. Most of these
factors are outside the control of the Company. Investors are cautioned
not to put undue reliance on forward-looking information. Except as
otherwise required by applicable securities statutes or regulation, the
Company expressly disclaims any intent or obligation to update publicly
forward-looking information, whether as a result of new information,
future events or otherwise.

The TSX Venture Exchange does not accept responsibility for the
adequacy or accuracy of this release.
 
Further information is available on the Company's website at
www.crowflight.com or contact:

Mike Hoffman
President and CEO
Crowflight Minerals
Tel: (416) 861-2964

Heather Colpitts
Manager, Investor and Public Relations
Crowflight Minerals
Tel: (416) 861-5803
info@crowflight.com

View Map:
http://www.crowflight.com/i/maps/2008-10-01_NRM.jpg

View News Release in PDF Format:
http://www.crowflight.com/i/pdf/2008-10-01_NR.pdf

=======================================================================
Copyright (c) 2008 CROWFLIGHT MINERALS INC. (CML)  All rights reserved.
 For more information visit our website at http://www.crowflight.com/
or send mailto:info@crowflight.com
Message sent on Wed Oct 1, 2008 at 7:27:24 AM Pacific Time
=======================================================================
.
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Crowflight Mineral Inc.

PRODUCER
CODE : CML.TO
ISIN : CA13758Y2015
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Crowflight Mineral is a nickel producing company based in Canada.

Crowflight Mineral produces nickel, copper in Canada, and holds various exploration projects in Canada.

Its main asset in production is BUCKO LAKE in Canada and its main exploration properties are AER/KIDD, PETER'S ROOST and TNB NORTH in Canada.

Crowflight Mineral is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 938 000 as of today (US$ 682 583, € 609 615).

Its stock quote reached its highest recent level on November 01, 1996 at CA$ 96.02, and its lowest recent point on February 04, 2016 at CA$ 0.03.

Crowflight Mineral has 37 520 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Crowflight Mineral Inc.
9/21/2006Ascenta Capital Partners Crowflight Report.pdf
Annual reports of Crowflight Mineral Inc.
Annual Report 2006
Financings of Crowflight Mineral Inc.
1/27/2011Announces $30 Million Private Placement
1/28/2010Provides Further Details on Non-Binding Expression of Intere...
9/22/2009Announces Private Placement Financing
7/28/2009Announces Closing of Previously-Announced Private Placement ...
7/8/2009Announces Private Placement Financing and Provides Bucko Upd...
12/31/2008Amends Terms of Warrants in Connection with Debt Facility Re...
12/17/2008Closes Underwritten Flow-Through Private Placement Financing...
12/2/2008Announces Underwritten Flow-Through Private Placement Financ...
4/30/2008 Closes Bought Deal Private Placement Financing of $11 Milli...
4/16/2008 Announces Bought Private Placement Financing of $11 Million
Nominations of Crowflight Mineral Inc.
3/23/2010Appoints Stephen Davies as Chief Operating Officer
8/21/2009Appoints Mark Trevisiol as President and CEO
5/27/2009Appoints Mike Kelly as President & CEO and Mike Hoffman as C...
5/26/2008Appoints Anna Ladd as CFO
9/10/2007Appoints Bruce Humphrey as Chairman and Mike Hoffman as Pres...
Financials of Crowflight Mineral Inc.
7/26/2011CaNickel Announces Second Quarter 2011 Financial Results and...
5/18/2010Announces First Quarter 2010 Financial Results
11/17/2009Announces Third Quarter 2009 Financial Results
8/13/2009Announces Second Quarter 2009 Financial Results
3/9/2009Announces Fourth Quarter and Year-End 2008 Financial Results
11/19/2008Reports Q3 2008 Financial Results
Project news of Crowflight Mineral Inc.
4/25/2011(Bucko Lake)Announces Restart of Bucko Lake Mine Operation
3/22/2010(Bucko Lake)Resumes Nickel Concentrate Shipments from Bucko Mine
3/4/2010(M11a)Reports Final Results From Drilling At M11A North Deposit
8/5/2009(Bucko Lake)Provides Bucko Mine Update
7/13/2009Intersects High Grade Nickel Off Surface Ramp at the Bucko M...
6/1/2009(Bucko Lake)Reports Results From Underground Drilling At The Bucko Mine
2/13/2009(Bucko Lake)Ships First Concentrate from Bucko Lake Nickel Mine to Becom...
1/23/2009(Bucko Lake)Intersects 9.56 Metres Of 7.87% Nickel; Commences Phase 2 De...
11/20/2008(Bucko Lake)Provides Bucko Lake Nickel Mine Update
10/1/2008Announces Mill Commissioning Underway at Bucko; Intersects 8...
6/25/2008(Bucko Lake)Provides Update on Underground Drilling at Bucko
5/20/2008(Bucko Lake)Final Results From Winter Exploration Drilling Further Indic...
5/9/2008(Bucko Lake)Provides Bucko Lake Nickel Project Update
4/23/2008(Bucko Lake)Discovers New Zone Of Mineralization At M11A North; Intersec...
3/28/2008(Bucko Lake) Commence Production at Bucko Lake Nickel Project
2/29/2008(Halfway Lake) Drilling at Halfway Lake Intersects 13 Metres Grading 1.6% ...
2/20/2008(Aer Kidd) Options AER Kidd Property in Sudbury; Provides Additional D...
1/23/2008(Bucko Lake) Finalizes $55 Million Debt Facility to Complete Bucko Lake ...
1/10/2008(Bucko Lake) Secures $55 Million Debt Facility to Complete Bucko Lake Ni...
9/17/2007(Bucko Lake)Reports New Inferred Nickel Resources for Deposits Near Buck...
Corporate news of Crowflight Mineral Inc.
9/23/2013CaNickel Announces Results of 2013 Winter Drill Program-Inte...
7/12/2013(Bowden Lake)CaNickel to Release Drilling Results at Bowden Lake Property
6/28/2013CaNickel Reports of Voting Results of Annual Meeting
10/29/2012(Bucko Lake)CaNickel Announces Updated Mineral Reserves and Resources fo...
9/14/2012CaNickel Announce Share Consolidation
9/7/2012CaNickel to Release 2012 Winter Drilling Results
7/5/2012CaNickel to Provide Business Updates
6/11/2012CaNickel Annual General Meeting Update
5/16/2012CaNickel to Suspend Blasting and Mill Operations
5/11/2012CaNickel Achieved Positive EBITDA
4/17/2012CaNickel Achieved Record Mill Recovery Rate
3/5/2012CaNickel Intercepts 7.3 Metres of 2.59% Nickel
2/6/2012CaNickel Files Preliminary Short Form Base Shelf Prospectus
12/29/2011CaNickel to Reduce Operations
9/30/2011CaNickel Granted Revised Environment Act Licence
8/22/2011CaNickel Announce New CEO and Change to the Board
6/29/2011CaNickel Intercepts 9.98 Metres of 2.35% Nickel
6/22/2011Announces Name Changed and Provides Business Updates
5/30/2011Arranged Debt Facility
4/14/2011Proposes Name Change and Share Consolidation
3/28/2011to Settle $11.3 Milion Debt for 258.8 Million Shares
3/16/2011Provides Legal Update
3/7/2011Receives $30 Million Financing Proceeds
2/22/2011 King Place Transferred 103.5 Million Shares
2/22/2011s Inc.: King Place Transferred 103.5 Million Shares
3/16/2010Provides Update on TSX Delisting Review
3/10/2010Resumes Milling Operations at Bucko
2/24/2010Provides 2010 Outlook
1/28/2010Announces Strategic Review And Private Placement Financing
2/26/2009Now Debt Free After Closing Out Hedge
1/13/2009Implements Additional Metal and Foreign Exchange Price Prote...
12/2/2008to Commence Trading on Toronto Stock Exchange
11/21/2008Obtains Conditional Approval to Trade on Toronto Stock Excha...
9/10/2008Discovers Two New Zones Of Mineralization Near Past-Producin...
7/30/2008Finalizes Metals Price Protection Requirements for Debt Faci...
1/21/2008 Accepts $55 Million Debt Facility Offer; Commences 2008 Exp...
1/21/2008Announces Changes To Board of Directors
11/15/2007 Partners with Pure Nickel to Explore Past Producing Manibri...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (CML.TO)FRANKFURT (CMI.F)
0.025+0.00%
TORONTO
CA$ 0.025
02/04 15:54 -
0%
Prev close Open
0.030 0.025
Low High
0.025 0.025
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.025 -16.67%
Volume 1 month var.
66 -16.67%
24hGold TrendPower© : -11
Produces Nickel
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 3/31/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 6.88+0.00%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.34-1.65%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59+1.37%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.02-1.46%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 11.44-0.82%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.31+1.64%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.18+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.56+1.30%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.67-1.76%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.