NWM Mining Report - July 2, 2008
formerly the Columbia Metals Report

Lluvia de Oro Mine Update
TSX Venture Exchange - Symbol: COL - Shares Outstanding: 94,970,527 
 
Material Added to Leach Pad - Construction of the new Heap continued and has now reached about 103,000 tonnes,  30,000 tonnes of ore was taken from the final blast in the Open Pit, abandoned in 2000, 10,000 tonnes came from the recently developed El Pozo prospect, SE of the Pit, while the remainder was taken from the uncrushed Heap proper.  
 
Construction of the new Heap continues to be oriented towards rapid development of as large a surface area as possible. The top dimension is now approximately 200 m x 32 m and is approaching one complete transverse slice through the former (uncrushed) Heap.
 
The Company has recently replaced the Cat 980 G Front-end Wheel Loader with a Cat 988 B unit having a larger bucket which has accelerated the feed rate to the crusher by some 34%. Delivery of a Cat D9R dozer is expected this week which will further increase the efficiency of ore movement to the crusher and the opening up of leachable areas.
 
Click here or on the picture above to be linked to the website version with larger photos.
 
Crusher Operations - The Nordberg NW 1415 Impact Crusher operated normally during the reporting period with an increase in output in the last few days due to the introduction of larger loading equipment as described above.  A manufacturer's representative is expected on site this week to make further adjustments to the unit and its associated equipment, conveyor belts, etc. in order to increase output.
 
Accessing More Mineable Material - Assay results were received for the most recent work at El Pozo. Geological analysis indicates a further 4,000 tonnes that could be ripped and deposited on the new Heap. While awaiting the El Pozo assay results,  samples were taken from the El Cobre trenches which, when assayed,  led to an estimate of 9,000 tonnes of mineable material. Further assay results from El Cobre remain pending. The El Este prospect continues to be a future priority.
 
Leaching- Approximately 90% of the new Heap is currently under leach.  Pregnant solution is being accumulated in the Pregnant Pond, transferred to the Barren Pond and returned to the new Heap at a cyanide concentration of 500 ppm and a flow rate of approximately 200 USGPM.  (increasing).   The emergency pond is being kept at a low level for cleaning and to guard against any difficulties arising from sudden and/or heavy rainfall.  There have been some recent storms.  Following receipt of lamps for copper and silver, the Assay Laboratory is essentially operative for Atomic Absorption (AA) work.  Some final reagents are expected this week.   Fire assay furnaces are still awaited.
 
Fresh carbon is being processed by attrition to remove fines, prior to column loading.
 
SART Copper Recovery Plant - Large diameter process piping, field instrumentation and the installation of the diesel fuel tank for the generators have been completed. Cable tray installation is near completion in readiness for field wiring and terminations to commence. Small diameter piping is also underway. Pre-operational testing of the main water tank and SART lime silo has also been completed.
 

Espa�ol

 
Material agregado a los Patios de Lixiviaci�n - Continuaba la construcci�n del nuevo Patio de Lixiviaci�n que ahora almacena unas 103,000 toneladas de mineral de las cuales 30,000 toneladas fueron producto del �ltimo disparo en el Tajo Abierto, abandonado en el a�o 2000,  10,000 toneladas fueron extra�das del prospecto El Pozo, descubierto �ltimamente al sureste del Tajo, mientras el resto proven�an del Patio antiguo que se est� procesando.
 
La construcci�n del Patio nuevo sigue siendo orientada hacia el desarrollo r�pido de una �rea superficial tan amplia que posible.   En la actualidad, su dimensi�n superior aproxima 200 m de largo por 32 m de ancho y casi se ha completado la trituraci�n de un paso transversal completo por el Patio anterior (que no fue triturado).
 
�ltimamente, la empresa ha reemplazado el cargador frontal a ruedas Cat modelo 980 G por otro del modelo 988 B que cuenta con una cuchara m�s grande, lo que ha permitido acelerar el ritmo de alimentaci�n a la quebradora en un 34%.   Se espera la llegada de un tractor Cat D9R esta semana con lo cual aumentar� la eficiencia del movimiento de mineral a la quebradora y la abertura de �reas lixiviables.
 
Operaciones de Trituraci�n - La quebradora de impacto Nordberg NW 1415 funcionaba normalmente durante el per�odo que se examine con un incremento de su producto debido a la introducci�n del equipo mayor mencionado arriba.  Se espera la llegada hoy del representante de la empresa fabricante con el fin de hacer m�s ajustes a la unidad y su equipo asociado, bandas transportadoras, etc. para incrementar a�n m�s su producci�n..
 
Acceso a m�s material econ�mico - Se ha recibido los resultados de los ensayes de las muestras de los trabajos m�s recientes en el prospecto El Pozo. Un an�lisis geol�gico indica la existencia de unos 4,000 toneladas m�s que podr�an ser arrancadas y depositadas en el Patio nuevo. Mientras se esperaba los resultados de los ensayes de El Pozo,  se tom� muestras de las trincheras del prospecto El Cobre, las cuales, al ser ensayadas, dieron una estimaci�n de 9,000 toneladas de mineral rentable. Hay m�s resultados todav�a pendientes de El Cobre. El prospecto El Este sigue como una prioridad futura.
 
Lixiviaci�n - Aproximadamente 90% del Patio nuevo est� actualmente siendo lixiviado. La soluci�n pre�ada se acumula en la Pileta de Soluci�n Rica, y se lo transfiere a la Pileta de Soluci�n Pobre para ser bombeada de vuelta al Patio nuevo a una concentraci�n de cianuro de sodio de 500 ppm y un ritmo de flujo de 200 USGPM (cifra que va en aumento). Se est� manteniendo la pileta de emergencia a un nivel bajo, tanto para limpiarlo como para protegerlo contra cualquier lluvia repentina y/o fuerte.  Han ocurrido unas tormentas �ltimamente. Luego de haber recibido las l�mparas para cobre y plata, el Laboratorio Anal�tico queda efectivamente en condiciones operativas para realizar an�lisis mediante absorpci�n at�mica (AA). Se espera la llegada de algunos �ltimos reactivos esta semana. Las fundiciones para ensayes a fuego est�n todav�a pendientes. Carbono fresco est� siendo procesado mediante rozadura para quitar la fracci�n fina, antes de cargarlo a las columnas.
 
Planta SART de Recuperaci�n de Cobre - Se ha terminado la tuber�a de proceso de mayor di�metro, la instrumentaci�n en el campo y la instalaci�n del tanque de diesel para las generadoras. Las bandejas para cableado est�n casi terminadas, listas para el comienzo del alambrado y las terminaciones en el campo. Instalaci�n de tuber�a de menor di�metro est� tambi�n avanzando.   Adem�s se ha concluido las pruebas previas a la operaci�n del tanque principal de agua y el silo de cal de la planta SARTque ver con tuber�a de gran di�metro, bandejas de cableado y la instalaci�n de un tanque de combustible para las generadoras.

Prepared by Vernon Smith, P.Eng., General Manager, Minera Columbia de Mexico, S.A. de C.V.
 
Please e-mail NWM Mining or telephone us at 416-364-6799 for more information.

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

This News Release is not intended for distribution in the United States. To unsubscribe to this newsletter

 
402 � 121 Richmond Street West, Toronto ON, M5H 2K1, Canada
Phone: (416) 364-6799    Fax: (416) 364-2595
 
.
Data and Statistics for these countries : Mexico | All
Gold and Silver Prices for these countries : Mexico | All

NWM Mining Corp.

PRODUCER
CODE : COL.V
ISIN : CA62946X1042
CUSIP : 197801103
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

MWN Mining is a gold development stage company based in Canada.

MWN Mining holds various exploration projects in Mexico.

Its main asset in production is LLUVIA DE ORO in Mexico and its main exploration properties are NORTH SONORA, CAMPAMENTO MEXICO and LLUVIA JOJOBA in Mexico.

MWN Mining is listed in Canada and in United States of America. Its market capitalisation is CA$ 1.5 millions as of today (US$ 1.2 millions, € 973 367).

Its stock quote reached its highest recent level on July 07, 2006 at CA$ 0.41, and its lowest recent point on April 01, 2020 at CA$ 0.01.

MWN Mining has 30 110 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of NWM Mining Corp.
Annual Report 2007
Financings of NWM Mining Corp.
3/19/2015Copper North Completes Private Placement
11/4/2013Copper North Extends Expiry Date of Warrants
10/30/2009NWM Mining Corporation Announces Closing of the Previously A...
10/1/2009Initial Closing and an Increase and Extension in Size of Pri...
9/4/2009Finalizes Terms for Non-Brokered Private Placement
7/28/2009NWM Press Release - NWM Mining Announces Non-Brokered Privat...
1/28/2009Announces Non-Brokered Private Placement
12/11/2008NWM Mining Press Release - NWM Announces First Draw on New C...
4/9/2008Announces Non-Brokered Private Placement
Option Grants of NWM Mining Corp.
10/2/2009NWM Mining Corporation Grants Stock Options
Nominations of NWM Mining Corp.
5/22/2013NWM Appoints Darren Koningen, P.Eng as President & COO
6/29/2012Mark Selby Joins NWM Board of Directors
5/13/2011NWM announces John Van De Beuken as COO
Project news of NWM Mining Corp.
1/31/2013NWM Reports 2012 Production Highlights
9/27/2012NWM Drills 1.03 g/t Au over 23.0 Metres from surface at Gold...
6/6/2012NWM Reports High Grade Results on Drilling at Gold Ridge
8/3/2011NWM Provides Lluvia-Jojoba Mine Update For July
7/7/2011NWM Provides Lluvia-Jojoba Mine Update & Announces New CFO
6/1/2011(Lluvia De Oro)NWM Provides Update on Gold Ridge Zone Exploration
5/26/2011(Lluvia Jojoba)Bi-weekly Update for Lluvia-Jojoba Project May 25, 2011
5/13/2011(La Jojoba)Lluvia de Oro / La Jojoba Project Up-date
4/28/2011(Lluvia De Oro)NWM provides Gold production and Lluvia de Oro mine update
4/27/2011(Lluvia De Oro)NWM provides update on new Gold Ridge discovery zone at Lluv...
4/8/2011(Lluvia Jojoba)NWM identifies another exploration target with high gold-cop...
3/31/2011(La Jojoba)NWM reports high-grade gold intercepts (3m of 11.15 g/t Au) ...
3/29/2011(La Jojoba)Bi-weekly Update for Lluvia-Jojoba Mine : 29, March, 2011
2/9/2011(Campamento Mexico)NWM Commences Exploration at Campamento
12/1/2010(Lluvia De Oro)NWM Drills 15 Meters of 1.082 g/t Au, 18.88 g/t Ag and 0.401...
7/21/2010(La Jojoba) Files Pre-Feasibility with Increase in Reserves
7/20/2010(Lluvia De Oro)Drills 2.155 g/t Au over 25.9 Meters at Lluvia de Oro (R10-0...
5/19/2010(La Jojoba)Lluvia de Oro & La Jojoba Mineral Resources and Reserves
9/17/2009(Lluvia De Oro)Lluvia de Oro Mine Update
8/8/2009(Lluvia De Oro)Lluvia de Oro Mine Update
7/24/2009(Lluvia De Oro)Lluvia de Oro Mine Update
3/5/2009(Lluvia De Oro)Assumes Financial and Operational Obligations at Lluvia-Jojo...
2/19/2009NI 43-101 Compliant Report for Sierra Pinta Gold Mine
11/14/2008(Lluvia De Oro)Lluvia de Oro Mine Update
6/4/2008(Lluvia De Oro)Lluvia de Oro Mine Update
5/7/2008(Lluvia De Oro)Lluvia de Oro Mine Update
2/26/2008(Lluvia De Oro)Lluvia-Jojoba Gold and Copper Mine Project Update
12/21/2007(Pii (pescarado Ii )) Files NI 43-101 Technical Report For PII, 2005-2007
10/2/2007(Lluvia De Oro)Columbia Metals Report - Lluvia de Oro Site - Bi-Weekly Upd...
Corporate news of NWM Mining Corp.
1/11/2016Copper North Announces Results of Phase 2 Drilling at Carmac...
10/26/2015Copper North Resumes Drilling of Carmacks Copper Mineralizat...
10/22/2015Copper North Clarifies Technical Disclosure
9/23/2015Copper North Expands Copper-Gold Mineralization at Carmacks ...
9/8/2015Copper North Announces Results From Drilling at Carmacks Pro...
8/4/2015Copper North Drilling Expands Copper Mineralization at Carma...
7/20/2015Copper North Commences Drilling at Carmacks Project, Yukon
7/2/2015Copper North Updates Improved Processing Plan for Carmacks P...
1/26/2015Expectations on Stimulus Fuel Hope for Copper Demand
1/21/2015Copper North Mining Corp.: Agitated Leach Process Provides O...
1/8/2015Copper North Grants Stock Options
1/5/2015Copper North Mining Corp.: Carmacks 2014 Exploration Project...
12/8/2014Copper North Clarifies Disclosure
11/25/2014Copper North Completes Warrant Incentive Program
11/17/2014Copper North Appoints Joseph Ringwald as Project Manager for...
10/14/2014Copper North Announces Joint Canada-China Feasibility Study ...
10/1/2014Copper North Commences Geophysical Survey on Thor Property i...
9/2/2014Copper North Progress at Carmacks Project, Yukon
8/27/2014Copper North Grants Stock Options
8/21/2014Copper North Exploration Success on Carmacks Project, Yukon
7/14/2014Copper North Files Carmacks Preliminary Economic Assessment
7/11/2014Copper North Completes Acquisition of Thor Property
7/2/2014Copper North Announces Agreement to Acquire Thor Property in...
6/23/2014Copper North Issues Shares to Repay Debt
6/17/2014Copper North Announces Loan Conversion
5/30/2014Copper North Announces Results of Preliminary Economic Asses...
4/25/2014Copper North Announces Closing of Private Placement
9/30/2013Copper North Executes Share Exchange Agreement
8/29/2013TORONTO =E2?? NWM Announces Start of Mining
6/28/2013NWM Announces Issuance of Bonus Shares
6/15/2013NWM Announces Debt Extension and Embarks on New Direction un...
5/8/2013Copper North Announces Loan Agreement and Deferred Salary Ag...
5/1/2013NWM reports a net income of $3,393,813 for 2012
4/4/2013(Lluvia De Oro)NWM Announces Drill Program to Increase Resources/Reserves a...
2/19/2013NWM Engages U.S. Business Development and Investor Relations...
2/19/2013Copper North Announces Results of 2012 Exploration Program, ...
1/17/2013Corporate Update January 17, 2013
10/16/2012Corporate Update October 17, 2012
9/21/2012NWM Successfully Negotiates Extension of Debt Facility to Ju...
8/31/2012NWM Loan Facility Update
8/23/2012NWM reports a profit of $1.8 million for Q2 2012
6/26/2012NWM and BioteQ Settle Lawsuit
6/19/2012NWM Signs Agreement to Purchase SART Plant Equipment
5/31/2012NWM reports a profit of $2.1 million for Q1 2012
4/26/2012NWM and BioteQ Settle Lawsuit
4/11/2012NWM produces 4,761 oz. Au in Q1.2012
2/7/2012NWM January Operational Update and Private Placement
1/17/2012NWM Provides Q4 2011 Update
11/30/2011Corporate Update November 18, 2011
9/30/2011Corporate Update September 23, 2011
9/12/2011Corporate Update September 9, 2011
8/29/2011NWM Q2 2011 Results and Lluvia-Jojoba Project Update
8/26/2011Corporate Update August 26, 2011
6/28/2011Greg McCoach Provides NWM Update
8/20/2010NWM Begins Mining at Lluvia de Oro & Draws on Standby Facili...
4/23/2010Receives Permits for Mining
1/5/2010NWM Mining Corporation Announces Share Issuance
12/15/2009First Phase Drill Program to Commence at Lluvia de Oro / La ...
12/8/2009NWM Settles Outstanding Tara Gold Resources Interest in Lluv...
8/10/2009New NWM Mining Corporation Presentation
6/24/2009Announces New Trading Symbol
3/10/2009Announces Share Issue
2/10/2009New Mining and Oil & Gas Research Website - StockResearchPor...
1/27/2009NWM Announces Convertible Debenture Restructuring
10/1/2008Lluvia de Oro Mine Update
9/17/2008Lluvia de Oro Mine Update
9/4/2008Lluvia de Oro Mine Update
8/20/2008Lluvia de Oro Mine Update
8/1/2008Press Release - NWM Pours First Gold at Lluvia-Jojoba Projec...
7/31/2008Lluvia de Oro Mine Update
7/25/2008Acorns to Mighty Oaks Initial Review - Published on Stockhou...
7/16/2008Lluvia de Oro Mine Update
7/2/2008Lluvia de Oro Mine Update
6/27/2008Columbia Announces Name Change
6/18/2008Lluvia de Oro Mine Update
6/5/2008 Profiled in The Market Traders' Commodity Supercycle Report
5/9/2008Hinde Gold Fund April 2008 Investor Letter
4/8/2008 Reports Option Payment at Lluvia de Oro
4/7/2008 Announces CDN $3M Financing Facility for Lluvia-Jojoba Gold
4/3/2008 Lluvia de Oro Mine Update
3/26/2008 Announces Addition To The Board of Directors
2/24/2008Lluvia de Oro Mine Update
1/16/2008Lluvia de Oro Mine Update
12/14/2007Lluvia de Oro Site - Bi-Weekly Update
12/12/2007Reports Option Payment at Lluvia de Oro
10/31/2007Lluvia de Oro Site - Bi-Weekly
10/30/2007Purchases Heavy Equipment for Lluvia de Oro Gold Mine
10/4/2007 Announces Transfer of Environmental & Mining Permits
9/18/2007Lluvia de Oro Site - Bi-Weekly Update - RESEND
9/1/2007(angl) Announces Investor Relations Engagement
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (COL.V)OTHER OTC (NWMMF)
0.050+0.00%0.003+0.00%
TSX-V
CA$ 0.050
11/30 10:46 -
0%
Prev close Open
0.050 0.055
Low High
0.050 0.055
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.050 -%
Volume 1 month var.
14,000 -%
24hGold TrendPower© : -28
Produces Gold
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2020100.00%0.070.01
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.06+0.57%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 9.16-2.76%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.61-4.06%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+3.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.56+0.64%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.32-5.88%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.18+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.81+1.12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.46+2.07%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.